Now that IMO low sulphur guidelines are going to be in place by 2020, Indian refineries are being more than enthusiastic by seeking IMO regulation compatible vessels from now on to ferry crude to India. 8The refiners are making life difficult for Indian flagged owners of crude tankers, who have the right of first refusal. 8Not only are refiners demanding younger vessels but they want vessels which are already fitted with scrubbers 8It is time for Indian shippers to move the government on the subject Click on Details for more
Details
Is there a fixed match between pipeline manufacturers when it comes to bidding for ONGC tenders? 8The line pipe manufacturers are a highly organized lot. They usually lobby together. Not just that, they are able to extract concessions from the government. So much so, that the pipeline industry today enjoys an unprecedented level of protection. 8Can a case be made out of coordinated bidding in the procurement for large OD pipes where LOIs were placed recently? 8Yes, it seems Click on Details for more
Details
8Project Name: Drilling Site Development 8Project Cost: Rs 100 crore 8Project Description: A workover rig RFQ is coming up for a private developer. Environment clearance for the project was rejected once on account of non-furnishing the details of the previous EC of the oilfield. However, the issue has been resolved now but clearance is awaited. An EOI for sale of gas from the field is active for participation. The company first plans to start the workover operation for one well, which has been earlier drilled and abandoned byONGC. The block was awarded to the company under the discovered small fields round in 2016. Click here for more informationDetails
8Project Name: Exploratory Drilling 8Project Cost: Rs 200 crore 8Project Description: ONGC has awarded the contract for the Produced Water Treatment Facility to Alberta based Techno Canada for a bid amount of Rs 3.8 crores. Furthermore, the drilling for the gas bearing 3 well development drilling project has been completed by John Energy Limited. The project was the part of the 31 well development drilling programme in Nagayalanka, of which 28 wells have been dropped. 8Project Event: RFQ for hiring an EPC contractor for a gathering pipeline is expected by February 2019. 8Expenditure Approval: Q1/2018 8RFQ Date: Feb/2019 8Release Date: Apr/2019 8Start Date: Q3/2018 8Completion Date: Q4/2019 Click here for more informationDetails
How does a banned firm in ONGC win three tenders in one sweep 8The firm bagged contracts for the supply of Hydraulic Packers, Floating Equipment and Seal Bore Extension & Locator Assembly 8Partial bans -- where a firm is banned only for those products and services in which it was found to have violated norms and not for others -- is the new norm in ONGC Click on Details for more
Details
8Project Name: Panipat Refinery BS VI Project 8Project Cost: Rs 3529 crore 8Project Description: All long lead items and 99% of short lead items have already been ordered. Moreover 40% of short lead items and 5 out of 26 long lead items received at site. Tankage work is completed. civil work, underground piping work and composite work like aboveground piping fabrication work are in full swing for offsite, revamping unit and new units. Erection of cooling tower and erection of DHDT reactor is expected by January 2019. Further RFQs are expected soon. 8Project Event: RFQ the erection work for SRU-MCC (Main combustion chamber) package is expected by February 2019. RFQ for the erection work for the HGU reformer unit is expected by March 2019. 8Expenditure Approval: Q4:2016 8RFQ Date: Feb/2019 8Release Date: Feb/2019 8Start Date: Q2:2017 8Completion Date: Jul/2019 Click here for more detailsDetails
A new petroleum storage terminal is coming up 8It is a Rs 466 crore project 8RFQ for a PFR consultant is coming up soon Click on Details for more information, including key contactsDetails
8Project Name: LPG Bottling Plant Expansion Project 8Project Cost: 32crores 8Project Description: The bottling plant is being expanded from 1000 MTPA to 2800 MTPA. The erection and installation work is in full swing and is expected to be completed by end December 2018. 8Project Event: The project is expected to commissioned by January 2019. 8Expenditure Approval: Q2:2017 8RFQ Date: Jan/2019 8Release Date: Jan/2019 8Start Date:Q2:2018 8Completion Date: Q1:2019 Click here for more detailsDetails
Ammonia-Urea Energy Saving Project 8Cost - Rs 481 Crore 8Project Event: Bhoomi pooja has been completed and tender for the long lead item is likely to be released in January 2019. The construction work is likely to be started in February 2019. Click here for more details Ammonia Revamp Project 8Cost - Rs 200 Crore 8Project Event: The discussion process is ongoing and RFQ for the EPC contractor is likely to be released in January 2019, The actions have been initiated for implementation of revamping in Ammonia Plant, which is expected to be completed by the end of 2020. Click here for more details Effluent Treatment Plant Up-gradation Project 8Cost - Rs 101 Crore 8Project Event: The discussion is ongoing and RFQ for the LSTK contractor is likely to be released at the end of December or January 2019. Click here for more detailsDetails
For reference purposes the website carries here the following tenders: 8Rate Contract for Repair of Pipelines by Online leakage sealing and Strengthening of Pipeline using composite repair Details 8Retrieval, Installation and Analysis of Corrosion Coupons Details 8AMC for hiring of Contract Services for Hydrojet Cleaning and Hydroblasting of Heat Exchangers Details 8Procurement of Pipes and Fittings Details 8Carbon Steel Coated Line Pipes for JHBDPL Project Details 8Hiring of Torque Turn meter Equipment and services for a period of 3 years Details 8Hiring of Hydraulic Cranes 20 MT for Nhava Supply Base Details 8Entering into Rate Contract for two years for Procurement of 1750 MT of Hollow Glass Sphere Grade-IV Details 8Hiring of Services for Maintenance of Gas Supply System Details 8Carrying out Sheds Jobs at Rayagada Details 8Hire the services for Architectural and Engineering consultancy services Details 8Corrigendum: Procurement of Aviation Turbine Fuel Details 8Corrigendum: Procurement of High Speed Diesel Details 8Restoration of Trench of Gas Pipeline Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8ONGC gets $32 million payment from Venezuela's PDVSA Details 8Norway's Equinor to start talks with Tanzania over LNG project Details 8Germany's DEA to buy Mexico's Sierra Oil and GasDetails 8Tokyo Gas, First Gen to build LNG terminal in PhilippinesDetails 8China, Venezuela joint refinery complex slated for start-up in late 2021: CaixinDetails 8L&T Construction bags orders worth Rs 2,106 croreDetails 8Brazil's Petrobras says could raise up to $26.9 bn through asset sales Details 8Centre to spend Rs 70,000 crore for natural gas pipeline networkDetails 8Gas pipeline network to be expanded to BangladeshDetails 8Greenhouse gas emissions rise like a ‘speeding freight train’ in 2018Details 8SBI extends deadline for free 5 litre petrol scheme; here's how you can avail the offerDetails 8Final decision on OVL’s Mozambique project likely by first half of 2019Details 8Cairn ruling means any export can be bannedDetails 8The oil effectDetails 8Trade war: India can gain in the long term – Here is howDetails 8Why govt should revisit move to limit marketing margins of OMCsDetails 8Oil prices ease in cautious trading ahead of Opec meetingDetails 8India could gain $8 trillion with climate battle: Special WHO reportDetails You can also click on Newsclips for moreDetails
Project: The civil contractor HCC is getting delayed in a greenfield hydel power project. 8The E&M contractor BHEL has completed the erection of the machine hall. 8What kind of RFQs are still left? 8When the project is set to be commissioned? Click on Details for more. Project: Owner is carrying out the DPR itself instead of hiring a consultant for a hydel power project. 8Financial tie-up is still to go. 8EC is also pending. 8What are the upcoming RFQs? Click on Details for more. (Access to the site available only to those with a password to our sister site, www.energylineindia.com)Details
We have evolved an entirely new way of depicting a business development opportunity in the E&P sector in India 8We do not just provide you an opportunity along with a key contact but give you a detailed mapping of the E&P site. We provide multiple parameter mapping in terms of -- Block name and attendant details, along with maps -- Well maps, depth, drilling results, opportunities ahead -- Seismic maps and opportunities -- Rigs, rig movements, day rates -- Gathering and processing station details -- Gathering and drilling pipeline details in terms of length, diameter and type of pipelines, and opportunities ahead We have the most comprehensive mapping ever attempted of E&P business opportunities in India. Click here for more details on how the data is organized, along with the business opportunity Details
There are many reasons why GAIL's plea for a uniform tariff, particularly when it comes to considering the Hazira-Vijaipur-Jagdishput (HBJ) and the subsequent Gas Rehabilitation and Expansion Plan (GREP, which expanded the capacity of the HBJ pipeline along with a new 36-inch pipeline from Vijaipur to Dadri, along with the HBJ-GREP Upgradation Plan, involving the installation of parallel lines from Vijaipur to Dadri and Dahej-Vijaipur, as a single pipeline network, makes sense for one set of customers and not to others. 8Find out how new gas consumers, including those dependent entirely on LNG will be better off from a single tariff on this pipeline network and by how much Click on Reports for more
Details
Get the full update on the HBJ-GREP-HBJ-GREP Upgradation pipeline 8Know everything about dozens of spur lines that this cross-country pipeline has built over the years to serve gas consumers of all hues Click on Reports for more
Details
Is the common carrier principle, introduced with much fanfare to deregulate the gas sector and to free the gas industry from the stranglehold of monopoly pipeline operators, really taken off? 8At least one pipeline operator has claimed that ever since its pipelines have been opened up under the common carrier principle, it has not solicited one customer on its network. 8Clearly, just providing a common carrier link is not good enough when last mile connectivity is still under monopoly control. Click on Reports for more
Details
The PNGRB is seeking a steep hike in fees from pipeline and CGD companies. 8There has been a howl of protest from the industry on this move 8But there is one company which is not taking up cudgels with the PNGRB over fees, as it has got bigger battles to fight Click on Reports for more
Details
India will need a huge amount of investment to be able to meet its own climate change mitigation targets 8Clear research on this is now emerging. Find our more on: -- What kind of investments will be needed -- Where will it come from -- And how will it be distributed Click on Reports for more
Details
If you are an oil & gas company with significant solar assets, here are a few tips on how to keep your O&M costs low: 8Conceiving a bundled strategy for capex and opex 8Defining the right scope of activities to be outsourced to the O&M provider 8Setting the right KPIs and the right service-level agreements (SLAs) With these finetunings, you can get: -- Increasing in asset availability by 3%, e.g. from 96 to 99% -- Increasing performance ratio of 3% -- Decreasing O&M costs by 10% --Reducing the IRR deal leakage by 10% Even though many factors determine a project’s IRR,these examples underline the many opportunities asset managers have to impact project and portfolio profitability. Click on Reports for more
Details
8Project Name: Oil Field Development 8Project Cost: Rs 100 crore 8Project Description: Oil and Natural Gas Corporation Limited RFQs for the hiring of Cementing, Well logging and mobile Effluent treatment Services are expected soon. 8Expenditure Approval: Q4/2017 8RFQ Date: Mar/2019 8Release Date: May/2019 8Start Date: Nov/2019 8Completion Date: Nov/2020 Click here for more informationDetails
Final conditions for rolling out service contracts for two ONGC oil fields -- Kalol and Geleki -- are being hammered out by ONGC with three possible service providers, Schlumberger, Halliburton and Baker Hughes. 8One point of contention was about termination of contract arising out of a force majeure event. 8According to service providers, the conditions were one sided, wherein only ONGC was provided the right to terminate the contract. 8There were other issues as well, including compensation to be paid when a force majeure is invoked. 8To ONGC's credit, it is going out of the way to mitigate issues raised by the service providers, thereby indicating that the E&P major, under pressure to deliver higher output, is walking the extra mile to make things work Click on Details to find out what ONGC is willing to do
Details
For reference purposes the website carries here the following tenders: 8Drilling and installation of deep tube well Details 8Supply and Commissioning of Dual Stream Metering Skids Details 8Procurement of Pipe and Fittings for WWTP, Storage and Pipe Yards Details 8Procurement of Pressure and Differential Pressure Switches Details 8Procurement of Complete Shell-and-tube Type Heat Exchanger for Hexane Overhead Condensor installed in HDPE Plant Details 8Hiring of Services for getting License for Condensate Tanks Details 8Integrity assessment of pipeline metal and coating of the crude oil and gas pipelines in oil fields Details 8Procurement of BOPs for the Year 2018-19 Details 8Hiring of Slickline Services Details 8EOI for provision of Fire Tender and Fire Fighting Services for Mangla Development Pipeline Operations Details 8EOI for provision of construction of Living Quarters Details 8Procurement of Natural Gas Meters Details 8Supply of Liquified Petroleum Gas in bulk Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Revenue secretary says excise duty hike on crude needs 'analysis' Details 8India seen holding rates steady as inflation, growth soften Details 8Group-level resolution for crisis, debt unlikely: IL&FS boardDetails 8French government preparing to suspend fuel tax increasesDetails 8Eni's Indonesia gas project to start up in 2021 under new contract: Deputy ministerDetails 8UAE says all must be on board in adjusting oil outputDetails 8Shell says production at Prelude FLNG to start at end-2018 Details 8First time in 5 years, carbon emissions of advanced economies set to rise: IEADetails 8MNGL threatens to stop bus gas supplyDetails 8LNG buyers try to ditch U.S. gas commitmentsDetails 8If we can't export oil from Gulf, no one can: Iran president Hassan RouhaniDetails 8Oil prices slide on swelling US supply, global market slumpDetails 8Why Qatar has left OPEC, and how the decision will impact oil prices, IndiaDetails 8Oil India commissions Cyclic Steam Stimulation TechnologyDetails 8Niti Aayog-led panel mulls free-market pricing for all local natural gasDetails 8Argentina announces $2.3 bln joint shale oil project with Malaysia's PetronasDetails 8Replacing imported LNG with domestic gas can save 23,000 cr in fertiliser subsidy: FAIDetails You can also click on Newsclips for moreDetails
Is there a way for Meractor Oil & Gas Ltd to be compensated for all past dues incurred by it in the Sagar Samrat Conversion project, now that it has been ousted from the deal? 8Or is everything lost for the company, as the conversion job was delayed well beyond the original deadline. 8ONGC had moved the encash the bank guarantee given by Mercator. 8Mercator may have no option now but also to take on its previous consortium partner, Gulf Piping Company UAE, who was given the contract recently by ONGC to complete the conversion job by excluding Mercator from the deal, in order to be able to get what it thinks is it due from the contract Click on Details for more
Details
8Project Name: Offshore Field Development 8Project Cost: Rs 500 crore 8Project Description: Adani Welspun Exploration Limited has put the BRC offshore field on hold citing unknown reasons. 8Project Event: RFQs for the project are on hold. Click here for more informationDetails
Thankfully, the government's protective orders did not apply here. 8The reason is that no domestic bidders were qualified for the Rs 124 crore deal Click on Details for moreDetails
Oil and Natural Gas Corporation Limited is soon going to release the tender for casing pipes at Mehsana Asset Gujarat. The RFQ's for the services are expected to be floated by the last week of December 2018 and will be on ICB basis for 29 well exploratory drilling programme in Gujarat. 8Company owned rigs are planned to be deployed for the project. 8The project involves drilling in 10 PML Blocks namely Lanwa, Lanwa Extension, Mehsana City, Balol, Geratpur, Santhal, Dedana, Jotana Extension, Bechraji, Chanasma in Mehsana and Patan Districts of Gujarat. Further RFQ is expected soon. Click on Details for key contactsDetails
8Project Name: POL Terminal Expansion Project 8Project Cost: 119 crores 8Project Description: The owner is planning to expand its existing POL terminal from 191074 KL to 319874 KL by installing tanks with a capacity of 4 X 1,200 KL of ethanol, 4 X 25,000 KL of HSD and 2 X 12,000 KL of MS. The project is in an initial stage. A slight delay has occurred in the selection of a contractor on account of wildlife clearance issues. Further RFQs are expected soon. 8Project Event: RFQ for the PMC contractor is expected by January 2019. 8Expenditure Approval: Q3:2017 8RFQ Date: Jan/2019 8Release Date: Feb/2019 8Start Date:Q1:2019 8Completion Date: Q3:2020 Click here for more detailsDetails
8Project Name: Haldia Refinery BS VI Up-gradation Project 8Project Cost: Rs 2935 crore 8Project Description: Heater foundation in the PrimeG revamping unit and Reactor foundation work in the DHDT new unit has already completed. Above ground piping fabrication work and equipment erection work are in full swing for offsites involved with the revamped units. 3D model review of new DHDT unit is almost 60% completed. Further RFQs are expected soon. 8Project Event: RFQ for the installation work of the reactor for DHDT unit and heater for PrimeG unit is expected by January 2019. RFQ for the installation work for the amine absorber column is expected by March 2019. 8Expenditure Approval: Q3:2016 8RFQ Date: Jan/2019 8Release Date: Jan/2019 8Start Date: Q2:2017 8Completion Date: Q3:2019 Click here for more details 8Project Name: Guwahati Refinery BS-VI Greenfield Project 8Project Cost: Rs 557 crore 8Project Description: Basic Engineering Design Package will be done by the technology licensor. All long lead items have already been ordered. Soil investigation work is already completed. Piling work is in progress. At present approx 15% work of the whole project has been completed. Further RFQs are expected soon. Major short lead equipment requirements coming up are: flanges, valves, strippers, reformer tubes, foot valves, auto recirculation valve, amine cartridge filters, torque wrenches, level switches, thermocouples, thermowells, antifriction bearing, spray nozzle, columns, heat tracing system, tube inserts, bolt tensioners, filters, desalters, scrubbers, strippers, separators, reactors. 8Expenditure Approval: Q3:2017 8RFQ Date: Jan/2019 8Release Date: Jan/2019 8Start Date: Q4:2017 8Completion Date: Q1:2020 Click here for more details 8A short-term maintenance contract for storage tank coming up Click on Details for moreDetails
Ammonia-Urea Energy Saving Project 8Cost - Rs 217 Crore 8Project Event: The project has been signed up with Siemens for a long lead item and it is likely to be delivered in May 2019. Construction work is ongoing Click here for more details NPK-SSP & Sulphuric Acid Expansion Project 8Cost - Rs 15 Crore 8Project Event: RFQ for a contractor is likely to be released after environmental clearance. The public hearing has been completed but environmental clearance is due and it is likely to be elicited in February 2019. The RFQ for the EPC contractor is likely to be released in February 2019. Click here for more details Single Super Phosphate Greenfield Project 8Cost - Rs 10 Crore 8Project Event: The proposal for an environmental clearance is likely to be granted in January 2019, The tender for an EPC contractor is likely to be released in February 2019. Because the committee has not made yet Click here for more detailsDetails
8Project Name: Offshore Field Development 8Project Cost: Rs 800 crore. 8Project Description:The private owner has put the development plan for the field on hold Find out more Click here for more information Cementing services requirement coming up 8Project Name: Exploratory Drilling Project 8Project Cost: Rs 300 crore 8Project Description: Owner's RFQ for the hiring of services for the cementing services for the 5 well development drilling programme is expected soon. The contract for the hydrofracturing services has already been awarded. The equipment required will be Proppant, Casing pipes, Drilling pipes, Blow out preventer, Cementing services, Drilling fluid services and other oilfield chemicals. 8Project Event: RFQ for the cementing services is expected by February 2019. 8Expenditure Approval: Q2/2018 8RFQ Date: Feb/2019 8Release Date: Apr/2019 8Start Date: Q2/2019 8Completion Date: Q2/2021 Click here for more information Details
8The Adanis are going full steam ahead with the controversial Carmichael coal mine in Australia. Click on Report for more. 8LNG imports to produce power makes more economic sense for Pakistan than India but the use of LNG is causing a different kind of crisis in the refining sector for our neoghbour.Click on Report for more. 8What kind of shale oil and gas reserves are available in the Cambay Basin? Get a full analysis of what is in store.Click on Report for more. 8LPG prices have been revised downwards. Know more click on Report. 8Another Canadian LNG project is likely to get to FID stage. LNG cargoes from the terminal will take 17 days to reach India.Click on Report for more. 8GEECL's reserves go up by an eyebrow-raising multiple in the Raniganj Block within just one year. Is it necessary to take such claims with a grain of salt?Click on Report for more. 8Kolkata has some advantages that other cities do not have: A high public transport usage ratio, big pedestrian footprint and a compact urban area. A new plant to bring down air pollution may end up working better in Kolkata than in any other city in the country. Know more click on Report. 8Despite the robust supply growth currently coming on-line in global LNG markets over the near-term, the outlook for liquefaction capacity over the medium-term is starting to appear tight. Know more click on Report. 8L&T Group: Know more why there is a bull run ahead for it. Click on Report for more. 8The use of composites is picking up speed in the oil & gas industry, know more click on Report. 8One European country, strong in offshore wind, is pushing its companies to India. For all those offshore oil & gas serice companies, here is a forthcoming interaction coming up, which may allow for opportunities to pick up some collaborations which will become handy in the years ahead.Click on Report for more. 8Get details of on IT company, outside the big companies, who have made big inroads into oil & gas sector work globally. It recently designed an acoustic downhole transmitter, a design pressure test cell for equipment testing and a complete redesign of a drilling communication skid. Know more click on Report. 8Global upstream investment cost index has started looking upwards. Know more click on Report.
Details
Get the details of a new LNG terminal coming up with a 1 MMTPA capacity in India. 8It is low cost, modular in scale. 8It will ride piggyback on a much larger third party LNG terminal coming up. 8It has a hinterland of demand and a multiple evacuation modes to deliver LNG 8Clearly a lot of smart thinking went into its conception Click on Reports for more
Details
Indian and Chinese companies are still hunting for oil & gas acreages around the globe. 8These investments are based on the assumption of a continued increase in demand for oil in their own countries, and across the world as well 8A new risk factor is now increasingly coming into play 8And it is dubbed "geo-ecological risk". Click on Reports to know more
Details
Ordering a new tanker or even buying a second hand one is undoubtedly a big decision. 8More often than not the investment is driven by robust industry earnings, although at times the main reason is attractive asset prices, regulatory developments andr the need for replacement tonnage. 8Assuming a new vessel is bought,with a trading life of around twenty years, the decision to order should also be considered against the backdrop of projected developments in tanker demand both in the short and in long term. 8Factors such as slowing growth in world oil demand and environmental concerns should also be taken into account. 8Find out why the buying of a tanker today is becoming far more complicated for a shipping company today. Click on Reports for more
Details
The US has granted a waiver to India to import Iranian crude. 8The US administration's orders on which vessels can import Iranian crude however are less than clear. 8Indian flagged vessels can also legitimately import such crude but only under certain caveats 8And what about insurance coverage? 8Know more on the latest regulatory risks on these issues Click on Reports for more
Details
The Rupee has gained against the dollar in recent days 8But it is too early to say that the dollar has peaked. 8The Federal Reserves will deliver four more hikes. 8Dollar hedging costs will remain extremely expensive 8But as 2019 progresses, expect a bearish dollar narrative to develop on the dollar. Get your full analysis here click on Report.
Details
An independent survey has confirmed an increase not only in LPG connections but also in its use as the primary as well as exclusive cooking fuel since 2015. 8However, in spite of these improvements, most households continue to use traditional biomass (alone or with LPG) due to the high recurring cost of LPG and the availability of free-of-cost biomass. When this happens, the potential health gains of using LPG cannot be achieved as there is continued exposure to dangerous levels of indoor air pollution. 8Home delivery of LPG, though improved, remains a challenge; reportedly less than 50 per cent of LPG-using households in all the surveyed states, barring West Bengal, receive their LPG cylinders at home. As 8Affordability (recurring cost of LPG) continues to emerge as a concern across all LPG-using households. 8And this necessitates a targeted approach that includes differentiated support for households considering their ability to pay for the clean cooking fuel. Click on Reports for more
Details
A recent survey shows that the use of blockchain technology in the energy sector is still at an embryonic stage, comparable to the very early days of the internet revolution. 8Nevertheless the website carries here answers to the following questions: 8What are the applications of blockchain in the energy sector? 8What are the associated impacts of different energy blockchains in the oil & gas sector? 8Can blockchain disrupt existing business models? 8What is the outlook for energy blockchain in enabling a successful energy transition? Click on Reports for more
Details
E-mobility is eventually gaining the traction it needed. Recent reports are again forecasting an early peak oil demand scenario on the back of more optimistic forecasts on e-mobility spread across the world. 8This is one trend that oil refineries in India will need to keep track of 8The website carries here in one compact format, an amalgam of 53 market trend reports by various research institutes, consultancy firms and independent organizations. 8Target and plans for 66 countries, plans by 71 cities or regions and 48 companies, some Indian, provide a picture on e-mobility. 8Visions by 23 automobile companies are included. Click on Reports for more
Details
8The world is returning to boom & bust cycles in the oil & gas industry as demand gets to become more uncertain going ahead. 8For Indian explorers, the one point that should be kept in mind is that the world does not need any more exploration properties. 8Investments will be lower than what are being pumped into the oil & gas sector now. 8How does this kind of analysis fit into a scenario where oil demand continues to rise rapidly as of now? Click on Reports to understand the complicated world of demand and supply of oil & gas and what to look for 5 to 10 years from now
Details
8Project Name: Drilling Field Development 8Project Cost: Rs 1500 crore 8Project Description: A mess-up in clearance applications has set the project back by one whole year 8Project Event: RFQ for the hiring an EPC contractor is now expected by February 2019. 8Expenditure Approval: Q2/2017 8RFQ Date: Feb/2019 8Release Date: Apr/2019 8Start Date: Q3/2019 8Completion Date: Dec/2021 Click here for more information EPC contractor for pipeline laying needed 8Project Name: Oil Field Development 8Project Cost: Rs 300 crore 8Project Description: The owner is soon expected to release the RFQs for the hiring of an EPC contractor for the laying down of gathering pipeline to the production facility. The drilling rig and the well services tenders are in the stage of the finalization. 8Project Event: RFQ for the hiring an EPC contractor for the pipeline installation is expected by Q2 2019. 8Expenditure Approval: Q4/2017 8RFQ Date: Q2/2019 8Release Date: Q2/2019 8Start Date: Q3/2019 8Completion Date: Dec/2022 Click here for more information ONGC awards a seismic survey contract: Find out more Oil and Natural Gas Corporation Limited has awarded the contract for the 2D seismic data acquisition in an unappraised area 8The volume of the contract is Rs 28 crore 8The LOI has been handed over Click on Reports for more
Details
Ammonia-Urea Brownfield Project 8Cost - Rs 6000 Crore 8Project Event: The RFQ for the Water Pre- Treatment, DM & Condensate Treatment has been released and finalization is due in January 2019. Selection of a civil contractor is also under process. Click here for more details Naptha to Natural Gas Feedstock Conversion Project 8Cost - Rs 250 Crore 8Project Event: The gas availability is likely to be ensured in December 2018, after that plant will start production. J& K won the race to supply cum erection of NG Preheater(D1153) and NG feed Preheat Coil(D1206) in between Thermax, J& K, and Furnace Engineering. The NIT for Composite Contract for Mechanical, Electrical & Instrumentation has been released and bid due date is 27 December 2018. Click here for more details SSP Brownfield Project 8Cost - Rs 20 Crore 8Project Event: The proposal for the environmental clearance has been accepted and the tender for the EPC contractor is likely to be released in December in place of November 2018. Click here for more details (Access available only via indianfertilizer.com)Details
For reference purposes the website carries here the following tenders: 8Procurement of Gaskets Details 8Hiring of Services for ARC maintenance of Lighting & Associated system Details 8Supply, Installation and Commissioning of Micro Turbine and its integration with existing power system Details 8Selection of Consultant for EPMC to set up city gas distribution networks Details 8Procurement of HTHP Frac Fluid System Details 8Transportation of Packed Lube ex-Mumbai Details 8Supply of Pressure Type Dispensers Details 8Safety system instrumentation and allied jobs Details 8Supply of VG 8, VG 12 and VG 100 to Mazgaon and Silvassa Terminals Details 8Civil work for work over rigs at different locations Details 8Procurement of Mechanical Seal Spares at refinery Details 8Supply of Online Dew Point Analyzers Details 8Supply of Spares for Level Instrument Details 8Supply of Lubricants Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8World 'way off course' in climate change fight: UN chief Guterres Details 8Rupee tanks 87 paise to 70.46, logs biggest single-day fall since Aug Details 8Qatar to withdraw from OPEC as of January 2019, says ministerDetails 8CAD may widen to 3% in September quarter on higher crude prices, gold imports: ICRADetails 8Delhi's air quality oscillates between 'poor', 'very poor' due to local pollutantsDetails 8Air pollution: NGT slaps 25 crore fine on Delhi governmentDetails 8Brazil's Petrobras to explore for oil and gas with Murphy in Gulf of Mexico Details 8India to achieve key Paris climate goals 10 years before deadlineDetails 8GAIL (India) Ltd soars 3.16%, up for third straight sessionDetails 8Substantial interest for Pawan Hans sale: Disinvestment SecyDetails 8Maharashtra Seamless secures orders from ONGCDetails 8Possibility of oil, gas reserves in J&K: StudyDetails 8Brazil oil, gas production jump in October: oil regulatorDetails 8LPG cylinder now used by 89% householdsDetails 8Govt’s petroleum subsidy expenditure crosses 83% of budgeted target within first 6 monthsDetails 8Shell to set sector-leading emissions targets after investor pressureDetails 8Oil prices extend gains on expected OPEC-led supply cutsDetails You can also click on Newsclips for moreDetails
The E&P service company model is expected to gain a massive fillip in India. 8After ONGC, it was Vedanta which wants U.S. oilfield services companies to set up consortia to help develop the 41 blocks in India 8Even smaller companies, such as those who won the blocks in the DSF Round is looking at the service company concept, albeit in a modified way. Click on Details for more
Details
Project: DPR consultant, NTPC, is preparing a detailed project report for a WFGD. 8Administrative approval is still to go. 8RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by Q1 2019. Click on Details for more. Project: The EPC contractor BHEL has won a bid for the FGD system in a thermal power project. 8Currently, boiler erection, and ESP works are ongoing. 8What kind of RFQs are still left? Click on Details for more. Project: EIA consultant has been shortlisted in a 1600 MW expansion super-critical thermal power project. 8Owner is undertaking DPR activities by using in-house resources. 8When is the price bid for the EIA consultant to come up? 8What kind of RFQs to come up? Click on Details for more. Project: Major EPC contenders have participated in the FGD bid of a 3000 MW thermal power station. 8Technical evaluation is going on. 8Who are the parties involved in the bid? Click on Details for more. (Access to the site available only to those with a password to our sister site, www.energylineindia.com)Details
8Project Name:Refinery IndJet Unit Modernization Project 8Project Cost: Rs 189 crore 8Project Description: (NEW DESCRIPTION)Indian Oil Corporation Limited along with EPCM contractor Engineers India Limited and in-housing technology developed by IOCL R&D is carrying out engineering activities to install a new IndJet unit to produce 250 KTA of Aviation Turbine Fuel (ATF) and 75 KTA of Pipeline Compatible Kerosene (PCK) from Barauni Refinery. Get the latest update here, including key contacts and RFQs coming up ahead Click here for more details 8Project Name:Tie-in-Connectivity Pipeline Project 8Project Cost: Rs 50 crore 8Project Description: A private port is planning to do a Tie-in-Connectivity from proposed LNG terminal to a trunk gas pipeline network. The capacity of the 18" pipeline will be 1.2 MMTPA at 45 bars operating pressure at inlet and outlet points. The length of the proposed tie-in-connectivity is 4km from ports limit to the nearest tie-in point. 8Project Event: RFQ for the PMC contractor is expected by February 2019. 8Expenditure Approval: Q3:2017 8RFQ Date: Feb/2019 8Release Date: Feb/2019 8Start Date: Q1:2019 8Completion Date: Q2:2021 Click here for more details An Instrumentation work coming up 8A tenure based work schedule has been drawn up Click on Details for key contacts Crude Oil Tank Repair Services Coming Up: Find out more 8The owner is soon going to release the RFQs for overhauling of Crude Oil Tanks in an existing oil field. 8Bidders must have prior experience of at least 5 years in crude oil Tank Repair Services. 8The tender is going to be released by the month of February 2019. Click on Details for key contacts
Details
8Project Name: Greenfield Crude Oil Terminal Project 8Project Cost: Rs 3480 crore 8Project Description: The owner is planning to install a sub-sea pipeline from Single Point Mooring (SPM) to Crude Oil Terminal (COT) and shore connecting facilities. The total length of the crude oil pipeline is 530 Km. Moreover, they are also planning to install a crude oil terminal with a capacity of 840000 cubic meters per annum. PFR has been prepared by using in-house resources. Further RFQs are expected soon. 8Project Event: RFQ for the surveying work is expected by January 2019. 8Expenditure Approval: Q3:2018 8RFQ Date: Jan/2019 8Release Date: Feb/2019 8Start Date: Q3:2019 8Completion Date: Q3:2021 Click here for more details for project details and key contactsDetails
8Project Name: Visakhapatnam Refinery Greenfield Captive Power Project 8Project Cost: Rs 1034 crore 8Project Description: LSTK contractor BHEL has floated a bid for underground civil works and storage components for a 75 MW captive power plant for the Visakhapatnam refinery. Bid for land leveling and grading activities are expected shortly. Project requirements are material transportation and land leveling and grading activities. RFQ for the land leveling and grading activities has already come out. Further RFQs are expected soon. 8Project Event: RFQ for design and engineering of the cooling tower is expected by January 2019. 8Expenditure Approval: Q4:2016 8RFQ Date: Jan/2018 8Release Date: Jan/2018 8Start Date: Q4:2018 8Completion Date: Q4:2020 Click here for more details 8Project Name: Greenfield LPG Bottling Plant Project 8Project Cost: Rs 161 crore 8Project Description: The EPCM contractor is working on an LPG bottling plant by installing 3X600MT mounded storage bullets for storage of LPG with a bottling capacity of 60 TMTPA. RFQ for the long lead items and mounded storage vessel work is already out. Currently, electrical and instrumentation work is going on. Investment of Rs 35 crores has been already done. 8Project Event: RFQ for the non plant building, Drainage and roads work is expected by January 2019. RFQ for the fabrication and installation work of Carousel is expected by March 2019. 8Expenditure Approval: Q4:2016 8RFQ Date: Jan/2018 8Release Date: Feb/2018 8Start Date: Q3:2017 8Completion Date: Q4:2019 Click here for more details 8Project Name: Greenfield LPG Bottling Plant 8Project Cost: 155 crores 8Project Description: The owner is planning to install an LPG bottling plant with a capacity of 44 TMTPA in South India. The job will be executed by the owner directly.The requirement will come package wise. A local contractor has already been hired for civil work. Further RFQs are expected soon. Major equipment required: Tanks, Boiler, Refrigeration Compressors, LPG discharge pumps, Lube oil pump compressors, LPG Condensate, water Condensate, Mercaptane Dosing Pump, Discharge Pump, Cooling water pumps, Cooling tower pumps, Lube oil charging pumps, Diesel pumps, Air compressors, Smoke detector, Heat detector, Hooter, Jettys,Separator, Monitor module, Control module. 8Project Event: RFQ for the mechanical piping work is expected by December 2018 RFQ for the compressor installation is expected by March 2019. 8Expenditure Approval: Q2:2017 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date:Q4:2018 8Completion Date: Q3:2020 Click here for more details 8Construction of new marketing terminals is coming up It is a Rs 300 crore jon Click on Details for key contactsDetails
For reference purposes the website carries here the following tenders: 8Procurement of Intelligent ion Chromatograph Details 8Hiring of Comprehensive AMC for IIWS Hardware Details 8Hiring of Services for Facility Management Services Details 8Procurement of HP Mud Hoses Details 8Revamping of Plant Piping of Chemical Dosing System Details 8Selection of Contractor for Hiring of Transportation Services for a period of 2 years Details 8Procurement of Dimethyl Disulphide (DMDS) Details 8Biennial Rate contract for supply of Fresh Catalysts in refinery Details 8Spading, Pipe line Hydro testing, Despading jobs in refinery units during shutdown Details 8Replacement of reformer catalyst tube of reformer in HCU Details 8Procurement of Pressure Controlled Type Hydraulic Dynamometer Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8A K Tiwari takes charge as Director (Finance), GAIL Details 8‘India under PM Modi got its due in the global oil market’ Details 8Shale gas reserve in India, source of clean energyDetails 8Oil marketing companies reduce jet fuel prices; ATF cost in Delhi down by 11%Details 810 apps to save your fuel bills in IndiaDetails 8India to host G-20 summit for the first time in 2022Details 8Govt forms panel to look at selling of OIL, ONGC fields to private companies Details 8Gail India proposes swap of Cove Point LNG cargoes in first quarterDetails 8Govt forms 6-member panel to look at selling 149 fields of ONGC, OIL to pvt firmsDetails 8Saudi Arabia ready to help India meet growing energy demands: Prince to PM ModiDetails 8NDA government earned Rs 11 lakh crore oil tax revenue in last 4.5 yearsDetails 8Oil workers' discontent threatens Libyan output surgeDetails 8Prime Minister Modi discusses climate change issue with UN chiefDetails 8Alberta to announce if it will impose crude oil production cutsDetails 8Green energy financing blooms as investors look beyond profitsDetails 8Russia's Putin says no hard figures on possible oil output cutsDetails 8Fuel price: Soon, tanking up in Delhi to be cheaper than in UPDetails 8G-20 nations agree on trade, migration; not climate changeDetails 8Four petrochemical regions attract Rs 1.83 lakh crore investments, create 3 lakh jobs: GovtDetails 8Will fall in oil price help stock market investors?Details 8Govt eyes PSUs’ chests to shore up pre-poll fundsDetails You can also click on Newsclips for moreDetails