Haldia, Guwahati refinery upgrdation: Get the latest updates here
Dec 05: 8Project Name: Haldia Refinery BS VI Up-gradation Project
8Project Cost: Rs 2935 crore
8Project Description: Heater foundation in the PrimeG revamping unit and Reactor foundation work in the DHDT new unit has already completed. Above ground piping fabrication work and equipment erection work are in full swing for offsites involved with the revamped units. 3D model review of new DHDT unit is almost 60% completed. Further RFQs are expected soon.
8Project Event: RFQ for the installation work of the reactor for DHDT unit and heater for PrimeG unit is expected by January 2019.
RFQ for the installation work for the amine absorber column is expected by March 2019.
8Expenditure Approval: Q3:2016
8RFQ Date: Jan/2019
8Release Date: Jan/2019
8Start Date: Q2:2017
8Completion Date: Q3:2019
Click here for more details 

8Project Name: Guwahati Refinery BS-VI Greenfield Project
8Project Cost: Rs 557 crore
8Project Description: Basic Engineering Design Package will be done by the technology licensor. All long lead items have already been ordered. Soil investigation work is already completed. Piling work is in progress. At present approx 15% work of the whole project has been completed. Further RFQs are expected soon.
Major short lead equipment requirements coming up are: flanges, valves, strippers, reformer tubes, foot valves, auto recirculation valve, amine cartridge filters, torque wrenches, level switches, thermocouples, thermowells, antifriction bearing, spray nozzle, columns, heat tracing system, tube inserts, bolt tensioners, filters, desalters, scrubbers, strippers, separators, reactors.
8Expenditure Approval: Q3:2017
8RFQ Date: Jan/2019
8Release Date: Jan/2019
8Start Date: Q4:2017
8Completion Date: Q1:2020
Click here for more details 