Panipat Refinery BS VI Project: More RFQs coming up
Dec 06: 8Project Name: Panipat Refinery BS VI Project 8Project Cost: Rs 3529 crore 8Project Description: All long lead items and 99% of short lead items have already been ordered. Moreover 40% of short lead items and 5 out of 26 long lead items received at site. Tankage work is completed. civil work, underground piping work and composite work like aboveground piping fabrication work are in full swing for offsite, revamping unit and new units. Erection of cooling tower and erection of DHDT reactor is expected by January 2019. Further RFQs are expected soon. 8Project Event: RFQ the erection work for SRU-MCC (Main combustion chamber) package is expected by February 2019. RFQ for the erection work for the HGU reformer unit is expected by March 2019. 8Expenditure Approval: Q4:2016 8RFQ Date: Feb/2019 8Release Date: Feb/2019 8Start Date: Q2:2017 8Completion Date: Jul/2019 Click here for more details