Ammonia-Urea Energy Saving Project 8Cost - Rs 481 crore 8Project Event: The long lead item purchase is ongoing. Erection work is ongoing for the mechanical equipment. Click here for more details Ammonia Brownfield Project 8Cost - Rs 250 crore 8Project Event: The project is in the initial phase and discussion is ongoing, RFQ for the process licensor is likely to be released in April 2019. The proposal for the environmental clearance is likely to be submitted in March 2019. Click here for more detailDetails
4 bidders were disqualified before one was selected 8Among those did not make the bar were: -- Botil Oil Tools -- American Completion Tools -- Super Company DMCC, -- Superior Energy Services Click on Details for more
Details
8Project Name: Pipeline Repair 8Project Cost: Rs 150 crore 8Project Description: Oil and Natural Gas Corporation Limited's RFQs for the repair and maintenance of hydrocarbon pipelines as well as dredging in the shallow waters of the Western Offshore Basin under a 3-year contract basis has been delayed. The dredging contract will be floated separately after the repair contract. Currently, the project is undergoing assessment form the ONGC's end and will take some time. 8Project Event: RFP for the hiring contractor for O&M cum LSTK contractor is expected by May 2019. RFP for the hiring of hiring dredging services is expected by June 2019 8Expenditure Approval: Q4/2018. 8RFQ Date: May/2019 8Release Date: Jul/2019. 8Start Date: Q4/2019 8Completion Date: Q4/2022 Click here for more details for key contacts and other detailsDetails
8Project Name: Shale Gas Development 8Project Cost: Rs 200 crore 8Project Description:Essar Oil and Gas Exploration and Production Limited along with its consultant US-based Advanced Resources International has been granted the environment clearance for the exploratory drilling of 20 shale gas wells for the RG (E)-CBM-2001/I (Raniganj East) CBM block, in the Damodar Basin in West Bengal till Feb 2023. However, the tender for the hiring a drilling rig has not been floated till now and is expected by mid-March 2019. 8Project Event: RFQ for hiring a drilling rig is expected by mid-March 2019. 8Expenditure Approval: Q4/2017. 8RFQ Date: 15/Mar/2019 8Release Date: Apr/2019. 8Start Date: Q3/2019 8Completion Date: Q2/2021 Click here for more detailsDetails
8Project Name: Kochi Refinery Greenfield Propylene Derivative Petrochemical Project 8Project Cost: Rs 4588 crore 8Project Description:Bharat Petroleum Corporation Limited (BPCL) is the owner PMC contractor is Engineers India Limited and the licensor is Air Liquide Global E&C Solutions for the Propylene Derivatives Petrochemical complex at Kochi refinery to produce products such as Acrylic acid, Oxo-alcohols, and Acrylates. The project is regularly getting delayed. Till now from December 2018, the deadline had been rescheduled four times 8Project Event: RFQ for residual mechanical work for PDPP offsite work is expected by April 2019. RFQ for the pre-commissioning work is expected by last week of July 2019. 8Expenditure Approval: Q2:2015 8RFQ Date: Apr/2019 8Release Date: Apr/2019 8Start Date: Q4:2015 8Completion Date: Oct:2019 Click here for more details to know what else is going on with the projectDetails
8Project Name: East Champaran Greenfield LPG Bottling plant 8Project Cost: Rs 137 crore 8Project Description: Fluor Daniel India Private Limited as a PMC contractor. Get more update on the project 8Project Event: RFQ for the mechanical piping work is expected by May 2019. 8Expenditure Approval: Q2:2018 8RFQ Date: May/2019 8Release Date: Jun/2019 8Start Date: Q4:2018 8Completion Date: Q3:2020 Click here for more details 8Business Opportunity for the maintenance contractor for Delayed Coker Unit- Know more details, including key contactsDetails