Software updates: Fertilizer projects
Mar 01: Ammonia-Urea Energy Saving Project 
8Cost - Rs 481 crore
8Project Event: The long lead item purchase is ongoing. Erection work is ongoing for the mechanical equipment.
Click here for more details
Ammonia Brownfield Project   

8Cost - Rs 250 crore
8Project Event: The project is in the initial phase and discussion is ongoing, RFQ for the process licensor is likely to be released in April 2019. The proposal for the environmental clearance is likely to be submitted in March 2019.
Click here for more detail


**********************************