8A rare 90 percent EMD cut and expanded feed-spec obligations redraw the contract’s financial and technical architecture. Whether these corrections spur wider global participation will be clear
8Bidders objected to dependence on PMC approval for final BEDP acceptance and payment, arguing lack of contractual control.
8The removal of the “banning order by another Oil PSE” phrase from eligibility criteria narrows the scope of disqualification and could allow return of some international vendors previously barred elsewhere.
Click on Details for more Details
8The tender formalises an inter-PSU settlement
Click on Details for more
Details
8Clearly the instructions are to set up a string of projects
Click on Details for more
Details
8GAIL’s latest HPRT procurement for Pata comes as a twin tender, separating technical and performance bids into distinct e-IDs. EIL’s zero-clarification rule and strict API 610 compliance mark a notable shift in rotating-equipment governance. The structure may become the template for future energy-recovery packages across its gas-processing grid.
Click on Details for more
Details
1) Sole-bidder tests documentation discipline on short-tenor HOC call-out in ONGC Cambay asset
8One bidder is in for ONGC Cambay’s five-month HOC call-out.
8The evaluation now hinges on paperwork precision and unit readiness rather than a crowded price fight.
 
2) OIL MBP drops pre-bid meet and locks 4 December close in charge rig-hire
8The Mahanadi onshore rig charter just shed its pre-bid conference and fixed a hard closure.
8A new option clause lets OIL swing quantity or duration by a quarter.
8Bidders now have six days to lock clarifications and price in the optionality.
 
3) ONGC Mehsana corrigendum centralises tie-break in BEC, extends EMD validity, and tightens post-bid governance
8The turnover-based tie rule inside work-distribution is gone—and reborn as a single BEC clause after a cartel check in civil works for deployment of drilling rigs at various drill sites in Mehsana.
8EMD stays parked longer, and post-bid conferences now trigger at a far lower threshold.
8The direction is unmistakable: tighter paperwork, fewer grey zones, and an edge for stronger books.
 
4) Bid window pushed to 02 December for CTU/NPU/FPU well-servicing package in Oil India Limited
8OIL has moved the bid clock to 02 December 2025 while keeping the risk envelope intact.
8Technically, the tender pushes reliability to the front: ≥5-year residual life anchored to the original BCD and pre-mobilization TPIA sign-offs make aging CT/N2 fleets harder to pass without refurbishment records.
8That should reduce down-time risk in coiled-tubing and nitrogen operations and improve HSE posture around pressure-control assemblies.
 
5) Corrigendum-I moves bid closing to 26 November without softening terms in ONGC Hazira plant (ARC repair/fabrication/valves)
8ONGC has pushed the bid window to 26 November 2025 and aligned the opening to 27 November.
8The risk spine—EMD/PBG, 24×7 readiness, emergency stock and TPIA-verified BEC—stays unchanged.
8That tilt widens participation but preserves execution discipline.
 
6) OIL pushes 3,000 KLPD ZLD-desalination bid to 02 December 2025, widening the field for compliant BOO offers
8A complex BOO ZLD scope rarely clears on a tight clock.
8OIL has moved the bid close from 12 September 2025 to 02 December 2025, even as high EMD/ePBG guardrails stay intact.
8The real story is what this extra 81 days does to participation quality and by-product risk planning.
 
Click on Details for more
Details
1) Cairn surveyor services EoI sets strict technical pedigree and flexible parent-consortium financing gates
8Cairn has opened an EoI for surveyor services that puts metrology credibility ahead of everything else.
8The financial door is wider—if you can back it with a parent guarantee or a proportionate consortium.
8The real tests, from standards to liability caps, are still to come at the NCB stage.
 
2) Cairn iPCPs EoI sets CO-ready PCP pedigree and tight proportional guarantees for consortia in Barmer
8Cairn wants insert-type and conventional PCPs that can survive Aishwarya’s CO-rich reality.
8The door is open to mid-scale OEMs—if they can backstop with parent guarantees or share risk proportionately in a consortium.
8The real contest will hinge on elastomers, metallurgy, and warranty-LD math when the RFP drops.
 
3) ONGC fixes OEM-tooled inspection and e-PBG discipline for cable telemetry seismic systems
8ONGC’s seismic TPI tender shifts power to measured, OEM-witnessed checks rather than paperwork alone.
8A quantified sampling regime and commissioning sign-offs push reliability assurance upstream.
 
4) Award consolidation signals single-vendor preference for ONGC Hazira TPIA
8All three line items under the Hazira third-party inspection package were awarded to Certification Engineers International Ltd.
8The absence of competing L2/L3 disclosures and the “non-divisible” note indicate ONGC’s deliberate move toward a single-vendor oversight structure.
8That consolidation prioritises uniform governance and accountability over price spread visibility, reinforcing a tighter, centralised inspection model.
 
5) One clears, one falls as ONGC Ankleshwar tightens compliance in leak sealing contract
8The Ankleshwar leak-sealing package is now running on stricter policy rails and a cleaner price sheet.
8The real story lies in how the corrigendum and ATC have reshaped the gates bidders must cross.
 
6) Time relief, money discipline: eight-month revamp cleared but price rails and LDs held in ONGC Ahmedabad ETPs (ZV8BC25004)
8Bidders won time but not softer terms.
8ONGC stretched the revamp window to eight months and tied tenure to take-over, yet kept payment staging, caps and LDs intact.
8The bid clock also moved after replies, and financial criteria were re-based—not relaxed.
 
Click on Details for more
Details
8OIL’s Baghewala study is shaping up as a quality-first contest with tight delivery rules.
8A high cut-off, Petrel-ready handovers and a no-subcontracting bar are redrawing the field.
8The qualified set reflects who can actually run inversion-to-prospect workflows end-to-end.
Click on Details for more
Details
In India’s largest gas conduit, demand continues to trail far behind its design throughput.
8The pipeline is ready, the steel is sunk yet industrial offtake hasn’t caught up.
8Even as new city-gas networks mushroom, the core backbone is underused.
8The mismatch underscores a deeper policy dilemma — demand creation hasn’t kept pace with infrastructure ambition.
8The irony is that supply hubs are full and industrial draw lagging. Details
8The PSV tender’s corrigenda move money, forms and timelines into sharper focus.
8Bid-bond validity stretches to 150 days while the financial BEC now demands Rs 175 crore turnover and Rs 52.5 crore working capital.
8Consortium routes close under PPP-MII even as a narrow CPSE comfort-letter lane stays open.
Click on Details for more
Details
8Here's what's happening today in the E&P, midstream-downstream, and CGD section
Click on Reports for more Details Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal & Coke
8LPG
8Ammonia

Click on Reports for more. Details
For reference purposes the website carries here the following tenders:
8Tender for fabrication and supply of fixing plates studs with nuts and foundation studs for surface team Mehsana asset Details
8Providing service support for diffuser control system (Rockwell PLC) on door delivery basis Details
8Tender for HPRT electric generator package Details
8Global expression of interest for provision of conventional and insert type rod driven progressive cavity pumps and accessories for wells Details
8Tender for hiring third party inspection agency for procurement of cable telemetry seismic data acquisition systems Details
8Tender for 360° media campaign development featuring Rahul Dravid across TV, digital, print, and BTL platforms Details
8Annual maintenance contract for motor operated valves with Rotork actuators Details
8Tender for stability testing and certification of structures at BPCL Barauni TOP by authorized agency Details
8Tender for repair of 4 nos. Vermont make flowmeters Details 
8Tender for Construction of Shivji Temple Details
8Tender for reimbursement of expenses for EC & CRZ report preparation of gas supply infrastructure Details
8Tender for reliability, development, and disaster management room relocation works in GR2 units Details
8Tender for modular desalination plant (zero liquid discharge basis) of 30002KLPD capacity at STF Madhuban under build own operate (BOO) concept for 3 years (corrigendum no5) Details
8Tender for complete electrical & mechanical overhauling & maintenance of EOT cranes Details
8Charter hire of 1 (one) no. 1400 HP (minimum) drilling rig package for drilling, completion, testing and abandonment of exploratory wells (amendment1) Details
8Expression of interest for supply of surveyor services for crude and produced water loading/unloading across pan India Cairn operations Details
8Procurement of 400 MT DMDS (dimethyl di sulphide) Details
8Annual maintenance contract for Detect3D and inFlux software Details
8Supply of Teflon tapes (122m length, ¾ inch width) for KASO based LPG bottling plants Details
8Procurement of SS cage for 102kg composite cylinders Details
8Supply of 25 kg trolley mounted DCP fire extinguishers Details
8Tender for T4S audit services Details
8Procurement of nylon string used in safety cap for self closing valves of LPG cylinders Details
8Tender for supply of valves Details
8Lining up an agency for procurement of PET/plastic bottle crushing machine Details
8Procurement of Tushaco make pump spares for 603 P 501 A/B Details
8Procurement of compressor spares from M/s Kirloskar Details
8Procurement of compressor spares from M/s Hoerbiger Details
8Supply and installation of spare modules for FIBCOM make telecom panel Details
8Tender for testing, servicing and calibration work of electrical equipment Details
8Procurement of tamper evident seals Details
8Annual maintenance contract for TEM Details
8Annual rate contract for extending support services and pantry services Details
8Procurement of pumps and systems Details
8Procurement of remote seal transmitter Details
8Tender for replacement of telecom battery bank Details
8Procurement of wireless repeater instruments Details
8Procurement of positive displacement flow meter Details
8Procurement of reagents for fully automated hormone analyzer (TOSOH) and fully automated HPLC analyzer Details
8Procurement of additives ST1740 and ST6214 Details
8Annual maintenance contract for period of three years of 1 no. of servo gauge Details
8Procurement of Woodward make TM25LP hydraulic actuator Details
8Supply of fabricated stainless steel mechanical spares for process industries Details
8Providing services for performing regular operations & maintenance related jobs of data center of IS department Details
8Rate contract for revisioning, testing and maintenance of lifting tools & tackles in P25 units Details
8Tender for procurement of heater bundle Details
8Procurement of foam inlet with male coupling Details
8Procurement of cotton hand gloves with polka dots Details
8Software integration of M/s Emerson make TFMS with SAP ERP for automatic daily dip posting of storage tanks Details
8Procurement of fittings and flanges Details
8Tender for procurement of XPSA board P/N Details
8Procurement of radar tank gauge with local display unit Details
8Supply of 6.6 kV switchboard panel extension for SS 331S and SS 336S Details
8Lining up of tender for nitrogen unit performance improvement and troubleshooting on proprietary basis Details
8Provision for conducting audit for ERDMP document re certification Details
8Procurement of CPLG, Jaw Flex, RRS 190/140 coupling Details
8Tender for supply of hardware spares Details
8Tender for procurement of O Ring Details
8Procurement of DCS screen mounting stand for DCS system Details
8Procurement of rotary device VFD Details
8Tender for supply and installation of cassette air condition system Details
8Procurement of walnut husk on two year rate contract Details
8Supply of PTFE Teflon tapes (50,000 nos) Details
8Tender for statutory in house pressure testing and painting of LPG cylinders Details
8AMC for PCS instruments make HFRR lubricity tester (1 no.) in QC laboratory Details
8Tender for foundation field bus barrier Details
8Supply of breather valves for Petchem terminal Details
8Tender for drinking water line modification Details
8Tender for design and supply of static mixture Details
8Supply of isolating spark gap of type EXFS L300 Details
8AMC for data analysis of corrosion probes and coupons, and calibration of loop Details
8Supply of isomerization catalyst along with support balls Details
8Tender for adequacy check of existing QC building proposed vertical expansion Details

You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips (These are public domain newsclips and the website is not responsible for their content):
8Balrampur chini mills unveils ambitious growth strategy focusing on ethanol and green energy Details
8Novonesis Innova® Delta set to transform ethanol production in India Details
8Ethanol used only for petrol blending, Malbros tells NGT Details
8India’s maritime dream alive as SDHI wins $220m export deal Details
8SDHI signs letter of intent with European company 6 IMO type II chemical tankers Details
8Indian shipbuilder to construct six new hybrid chemical tankers Details
8Consortium partners have decided to resolve ‘force majeure’ in Mozambique LNG project: Bharat Petroleum Details
8PNGRB committee proposes boost for CNG in city gas distribution sector Details
8Restore APM allocation for CNG sector, include gas under GST regime: Panel Details
8Aegis Vopak reports 26% revenue growth in Q2, unveils strategic expansion plans Details
8GBL & ICT Mumbai launch CO2-to-DME pilot project Details
8Indian Oil sector faces sanctions and ethanol turmoil Details
8U.S. sanctions push Indian refiners away from Russian crude Details
8Putin and Tokayev to discuss gas cooperation, U.S. sanctions fallout Details
8Middle Eastern oil producers boost crude supplies to India Details
8Iraq to raise oil supplies to India in December Details
8Survey of India and Indian Oil rope in MapmyIndia Mappls for digital maps, deep-tech products and IoT suite of solutions Details
8ONGC declares results for Q2 FY’26; posts consolidated net profit of Rs. 12,615 crore up by 28.2% Details
8Shri M Angamuthu gets additional charge of Chairperson at Visakhapatnam Port Authority on interim basis Details
8India aims to create 5.7 million skilled workers in mining sector by 2030 for clean energy development Details
8India set to miss 2030 hydrogen goal due to demand uncertainty Details
8Aim to make India global hub for green hydrogen production: Pralhad Joshi Details
8Oil prices little changed as markets eye US government reopening Details
8‘Prioritise Indian shipyards in Platform Supply Vessel tender of ONGC by amending terms’, shipyards group to Oil Secy Details 
8IOCL, BPCL, HPCL and other Indian refineries to produce 2 lakh tonnes of green hydrogen by 2030 Details
8GAIL chief's dissent note shows rift in PNGRB gas reform panel Details
8Indradhanush Gas Grid commences natural gas supply to Numaligarh Refinery Details
8India cuts December imports of Russian crude amid US trade talks and sanctions pressure Details
8Saudi Arabia, Iraq allocate full term crude volumes to Indian refiners in December, sources say Details
8State-run oil firms scale down ship requirement by half to 59 Details
8JSW Energy commissions first green hydrogen plant in Karnataka under PLI scheme Details
8India cuts Russian crude oil buys for December amid Trump tariffs Details
8Godavari Biorefineries and ICT Mumbai launch CO2-to-DME pilot plant Details
8India set to miss 2030 hydrogen goal due to demand uncertainty Details
You can also click on Newsclips for more
Details
8Project Name: Hyderabad District City Gas Distribution
8Project Cost: Rs 300 crore Click here for more details Details
8Project Name: Faizabad and Sultanpur District City Gas Distribution
8Project Cost: Rs 200 crore Click here for more details Details
The LNG capex boom is now being followed through with another  kind of storage boom
8And that covers storage infrastructure into a cross-fuel logistics network—from cryogenic LPG to ammonia and industrial liquids.
8And this private enterprise has lined up a whopping Rs 42,000 crore of capex in the next five years Details
New Page 1 8Progress of PNG (D), CNG and Pipeline (Inch km) in the Country September 2025 [PNGRB] Details
8Financial results for the quarter and half year ended 30th September 2025 [GSPL] Details
8Investor presentation on quarter 2 FY 2025 26 [GSPL] Details
8Intimation of conference call for Q2 financial results (F.Y. 2025 26) [OIL] Details
8Link for audio recording of conference call with analyst(s) & investor(s) [ONGC] Details
8Financial results for the quarter and half year ended 30th September 2025 [Selan] Details
8Investor presentation on quarter 2 FY 2025 26 [Selan] Details
Details
8Find a snapshot of thermal, hydro, pumped storage,
solar, wind, BESS and T&D contracts related updates for the day
Click on Reports for more Details
A private campaign shows that depth is not the monopoly of heavy rigs.
8A 3,900-metre well drilled with a 1,000 HP setup demonstrates that efficient well design and disciplined execution can narrow India’s onshore cost curve.
8The result: lower horsepower, lower costs, and a new baseline for inland drilling capability. Clearly, horsepower ratings don’t define limits — engineering intent does. Details
A CEO conceded that LNG stations “are not picking up that fast.” Even by year-end, only 10–15 new sites may materialize
8This is a fraction of earlier expectations, exposing how thin the downstream gas build-out really is.
Click on Details for more Details
1) Bid deadline pushed by 14 days for offshore wireline perforation package
8ONGC has extended the bid timeline for its offshore wireline/perforation and intervention package by two weeks.
8The shift gives empanelled vendors more runway to lock CIS compatibility and multi-category mobilization.
8The commercial and qualification architecture remains unchanged, sharpening a competition on readiness and rates.
 
2) Two-week bid timeline extension for onshore wireline, perforation package — ONGC ZV5GL25003
8ONGC has pushed the onshore wireline/perforation tender by 14 days to 25–26 November 2025.
8The move preserves the strict evaluation and CIS-heavy obligations while giving bidders breathing room on readiness.
8That combination could lift participation depth without diluting the risk allocation.
 
3) Two-week extension lands for TCP-DST and specialized services tender
8ONGC has pushed its TCP-DST and specialized services tender to 25–26 November 2025.
8The move preserves strict CIS and pricing discipline while easing mobilisation and documentation pressure.
8Expect deeper multi-line participation without any softening of risk allocation.
 
4) Pre-bid timing and venue reset via corrigendum for nitrogen pumping units hire
8ONGC has issued a corrigendum that overwrites all earlier pre-bid parameters.
8The new window tightens procedural certainty without disturbing the technical or commercial spine.
8Expect sharper, telemetry-compliant bids as vendors recalibrate their pre-bid engagement.
 
Click on Details for more
Details
1) Customs/GST concessional rates aligned to 18% and group-support guarantees added under latest corrigendum in ONGC Western Offshore ILI
8ONGC has reset the concessional tax baseline for ILI imports and domestic procurements to 18% with an explicit merit-rate caveat.
8New appendices allow bidder–group technical backing without diluting accountability.
8The ATC now mixes easier security instruments with a hard penalty for late performance security.
 
2) Bid deadline pushed to 02 December 2025 after no-extension PBC stance for hiring of 9-5/8 & 7 Whipstocks
8ONGC has shifted the bid calendar by three weeks.
8The same package where PBC minutes said “no extension envisaged” is now open till 02 December 2025.
8The added time could widen participation — if bidders convert it into cleaner compliance and sharper pricing.
 
3) Bid due date pushed to 17 November 2025 without commercial relaxations in workover rig package
8SunPetro has moved the bid clock but left the risk envelope untouched.
8The 120-day validity, LD/PBG architecture and strict submission protocol remain in place.
8That combination could widen participation without diluting discipline.
 
4) Bid due date extended to 17 November 2025; QCBS and securities unchanged for offshore rig valuation
8ONGC has pushed the clock by seven days on its rig valuation tender without touching QCBS weights or securities.
8The move aligns with a pre-set auto-extension window and gives TPAs time to firm up inspection logistics.
8Expect deeper technical submissions rather than looser terms.
 
5) Bid due date pushed to 04 December 2025; risk terms and ATCs intact in OIL HPWBM + centrifuge
8OIL has granted a 20-day extension on its four-year HPWBM and centrifuge call-out tender.
8The shift lands alongside pre-bid responses while leaving securities, option clause and policy anchors untouched.
8Expect deeper technical submissions without loosening risk allocation.
 
Click on Details for more
Details
1) Formula-priced CNG fleet hire aims to lock uptime and handling performance in ONGC Mehsana
8ONGC has moved to a three-lever evaluation for trucks — daily availability, km run, and MT handled — collapsing logistics performance into one comparable monthly number.
8Groupwise minimum quotes and prior-service bars will filter the bidder pool toward operators with real capacity.
8The only glitch is procedural: the portal still needs a single EMD entry even when the actual EMD is quantity-linked.
 
2) Six-month industrial gas supply anchors rig uptime under dual turnaround clauses in ONGC Drilling Services, Frontier Basins
8Oxygen, acetylene and nitrogen will be trucked to rigs in Bihar and Uttar Pradesh under IS-compliant cylinder and pressure controls.
8ONGC’s bid text blends a 48-hour response trigger with a 7-day LD schedule, leaving suppliers to price for the tighter bar unless clarified.
8PPP-MII is off for this sub-Rs 1 crore buy, but MSE preference still shapes the award split.
 
3) Deadline pushed to 2 December for fire-protection LSTK across 18 sites in ONGC Ahmedabad Asset
8ONGC has moved the bid clock by three weeks on its multi-site fire-protection revamp.
8The shift lands just after a quiet but meaningful tweak to financial-criteria evidence.
8The combination could reshape who can credibly bid — but not the performance bar.
 
4) Bid deadline pushed to 25 November for ONGC wireline logging & TCP-DST (ZV5GC25002)
8ONGC has added two weeks to its multi-basin logging and TCP-DST tender.
8The shift dovetails with earlier financial-criteria clarifications that peg audit currency to the final closing date.
8That combination eases documentation risk without touching the operational bar.
 
5) PoA rules tightened and security instruments widened under third corrigendum for ONGC O&M Juhu AFS
8ONGC has clarified who can sign, how to notarise, and when originals may be demanded — and it has expanded the ways bidders can post securities.
8Operationally, it has reaffirmed that refuellers and QC discipline sit squarely with the contractor.
8The numbers haven’t moved much, but the risk-allocation signals are sharper than before.
 
Click on Details for more
Details
1) Greenleaf Engineering wins design contract in IOCL Mathura Refinery
8IOCL has finalised a one-year embedded-engineering contract to support process-modification schemes at Mathura Refinery. Six bidders entered, but only two qualified under tight software and experience filters. The award signals a controlled pricing environment and a shift to man-month based design deployment.
 
2) Swayin & Associates bags HPCL’s Chandrapur–Nagpur LPG pipeline survey
8HPCL has finalised the reconnaissance survey award for its 145-km Chandrapur–Nagpur LPG pipeline, selecting Swayin & Associates as L1 on GeM. The bid came in over 30 % below the nearest qualified rival, signalling tight pricing in midstream survey contracts. HPCL’s tender marks a procedural shift toward digitised front-end pipeline design via GeM.
 
3) Progressive Engineering wins BPCL Mumbai PRFCC pre-project design job
8The contract covers multi-disciplinary design and drafting for PRFCC unit relocation jobs. Five firms qualified; Progressive’s quote came nearly 47 % below the next bidder. BPCL’s hybrid GeM–refinery framework sets a new procurement benchmark for consultancy packages.
 
4) BPCL awards nitrogen plant contract to General Energy Management Systems
8A two-bid GeM tender for supply and installation of a 5 Nm³/hr nitrogen plant closed with a wide 506 percent price gap between L1 and L2.

Click on Details for more
Details
8The timeline relief arrives without changing the technical, HSE, or contractual bar.
8That mix could widen participation while keeping the risk allocation exactly where the promoter wants it.
Click on Details for more
Details
1) IOCL Guwahati locks ER-probe servicing to Chemtreat India under tight legal and audit controls
8The refinery’s new two-year contract formalises OEM-exclusive calibration of ER probes in its crude, coker and hydro-desulphur units. A 39-month bank-guarantee and Rs 10-crore arbitration limit mark IOCL’s toughest commercial stance yet on proprietary O&M work. Behind the closed eligibility lies a broader shift toward litigation-averse, audit-compliant refinery procurement.
 
2) Pre-tender meet announced for sulphur pelletizer unit in CPCL Manali Refinery
8CPCL has scheduled an online pre-tender meet on 14 November 2025 for its proposed sulphur pelletizer system at Manali Refinery. The session will clarify technical scope, PQCs, timelines, and commercial terms. A structured questionnaire seeks audited financials and execution credentials from prospective bidders before the main NIT release.
 
3) HBL bio-compost evacuation hard-wires risk transfer and LDs amid conflicting award logic
8HBL’s bio-compost tender moves title and risk to the buyer at Gate Pass and prices schedule slippage at 0.5% per week. Yard clean-out dates are locked for legacy and current stock through July 2026. But the document alternates between plant-wise H1 awards and a single-party award, leaving strategy-critical ambiguity.

Click on Details for more
Details
1) Repeated bid extensions mark design-freeze lag in IOCL Panipat PBR cooling-water network package
8Five sequential extensions have pushed the composite-works bid from mid-August to December. With no change in qualification or scope, the slippage points to engineering deliverable delays and bidder-pool constraints. The tender remains pivotal for completing the PBR utilities corridor before commissioning alignment in 2026.
 
2) Five-fold bid-deadline shift marks tight vendor screening in Petronet LNG PDH-PP Dahej
8EIL has extended the rotary-lobe pump tender deadline five times, taking the submission window to 11 November 2025. The move reflects the impact of UOP-linked NDA requirements and complex qualification proofs for OEM subsidiaries. Experts see it as part of a wider pattern of schedule stretch across PLL’s PDH procurement chain.
 
3) Bid deadline for Bina Petchem compressor tender extended five times
8The bid window for BPCL’s flagship Bina Petchem compressor package has now stretched to mid-November. Engineers India Ltd has approved five successive extensions totaling nearly two months as OEMs finalize compliance with API 617 and licensor-linked NDA terms. The drawn-out schedule underscores the narrowing pool of qualified hydrogen-service compressor manufacturers.
 
4) Five bid extensions granted for BPCL Bina GC package under EIL supervision
8The high-specification Gas Chromatograph package for BPCL’s Bina Petchem expansion has seen five deadline revisions, stretching the tender cycle by nearly two months. Strict licensor-linked NDA and proveness requirements appear to be the chief drivers. EIL has so far avoided scope changes, keeping the focus on compliance and document integrity.
 
5) EIL extends Bina Petchem reciprocating compressor bid deadline to 17 Nov under tight NDA regime
8Three date extensions have stretched the limited tender by over a month, largely due to licensor-linked NDA clearances. Vendors must submit digital confidentiality undertakings before accessing technical files. The unusual no-EMD structure marks a shift in EIL’s risk allocation for licensed equipment.

Click on Details for more
Details
1) Deadline for centrifugal-compressor tender extended to 28 Nov in BPCL Bina Petchem project
8EIL has granted a second extension for the Rs 50-lakh compressor package at BPREP, pushing submission to 28 Nov 2025. The move acknowledges licensor-linked NDA complexities and API 617 compliance requirements. Bidders welcome the breathing space as documentation with foreign principals tightens.
 
2) EIL extends carbon-steel column tender for BPCL Bina project to 24 November
8Bid submission for the Bina Petchem column package has been pushed twice, now closing 24 November. The 40-day stretch reflects tight U-stamp vendor capacity and NDA-linked data-access delays. BPCL and EIL aim to secure wider participation before freezing fabricator line-ups.
 
3) Gujarat Gas extends Sanchore LNG facility bid deadline by 10 days
8The Sanchore LNG station tender will now close on 17 November. GGL has allowed a short extension amid industry feedback on OEM alignment and document finalisation. While scope and terms remain unchanged, the move aims to broaden participation in a tight vendor field.

Click on Details for more
Details
Two bidders clear IOCL Barauni reprography technical stage under wage-tight contract model
8The reprography-services bid at IOCL Barauni Refinery advanced with two firms passing the technical gate out of three contenders. Behind the modest Rs 11-lakh scope lies a stringent no-profit wage-reimbursement formula and a 33-month security lock. The structure offers cost discipline for IOCL but adds liquidity stress for small service vendors.
Click on Details for more
Details
8OIL’s new onshore rig charter codifies ODR/SDR boundaries, a demobilization floor and a mobilization cap with deferred excess.
8This reduces the grey zones around logging, BOP testing and production tests that typically trigger invoice disputes
Click on Details for more
Details
8BPCL’s CRDC has initiated the refinery’s first ISCC-CORSIA audit to qualify sustainable aviation fuel produced via co-processing.
8The single-vendor GeM tender tasks COTECNA with full-cycle certification, including GHG verification and chain-of-custody checks.
8With ISCC fees set to rise in January 2026, schedule adherence becomes the critical commercial variable.
Click on Details for more
Details
8The promoter is testing the market for partners who can design, supply, and scale capture plants, not just pitch lab results.
8Qualification bars centre on delivered plants and solvent supply filters that reward proven execution. 
8Dates and securities are light at this stage, but the two-bid structure signals a rapid move to a shortlist.
Click on Details for more Details
8The owner has invited bids for end-to-end project management of the feeder line under a 25-month PMC contract.
8The package adopts an 80:20 QCBS model, marking a shift from the earlier L-1 route.
8Clause-level tightening around ISO, EPFO, and HR traceability reflects IGGL’s bid to professionalise pipeline oversight.
8Five points are reserved for firms with an operational office in the state.
8The incentive supports on-ground coordination and regional employment.
8It also de-risks logistics for site-level supervision.
Click on Details for more Details
8EIL has invited competitive bids from global PVC technology providers for BPCL’s flagship Andhra Pradesh complex. The two-train design will produce 600 KTPA of suspension-grade PVC using VCM feed from upstream EDC units. Tight qualification rules and compressed BEDP timelines set a high entry bar for licensors.
Click on Details for more Details
8The company cites land and salt-management constraints as key reasons for seeking effluent discharge within consent limits.
Click on Details for more Details
8It is a brownfield expansion
8So expect a lot of contracting
Click on Details for more Details
8Here's what's happening today in the E&P & midstream-downstream section
Click on Reports for more Details Details
For reference purposes the website carries here the following tenders:
8Procurement of ON-OFF butterfly valves for PDH-PP plant with ethane and propane handling facilities Details
8Procurement of ON-OFF switching eccentric disc valves for PDH-PP plant with ethane and propane handling facilities Details
8Design, Engineering, Supply, Installation, Testing, and Commissioning of Pipeline Leak and Intrusion Detection System Details
8Supply, Installation, and Commissioning of 200 kW VFD panel Details
8Tender for Replacement of Impeller Assembly and Accessories for Fire Engine Details
8Procurement of M/S Mather and Platt Pumps Pvt. Ltd. MAKE Spares of Pumps Details
8Tender for Crude Oil Transfer / Booster Pumps each of capacity 200 KL / hour for Bhaskar-I Field Details
8Hiring of Mobile Land Work Over Rig (100MT Capacity) on Callout Basis Details
8Tender for IT infrastructure facility upgradation at Bhaskar-I field Details
8Procurement of custody transfer meter including all accessories for Bhaskar-I field Details
8Tender for Multiphase Flowmeter including all accessories for Bhaskar-I field Details
8Tender for Procurement of Natural Gas Details
8Procurement of carbon steel and Hastelloy plates Details
8Three-year rate contract for supply of Personal Protective Equipment Details
8Tender for Sale of bio-compost on “as is where is” basis from HBL Sugauli and Lauriya plant Details
8Hiring of Bundled Services (comprising of Cementing and Mud Engineering Services) for 06 drilling wells under Frontier Basin Project (Amendment -4) Details
8EOI for Accreditation and Delivery of NEBOSH and IOSH Trainings Details
8Supply and Installation of 7 nos. of Automatic PMCC Flash Point Apparatus Details
8Tender for Intelligent pigging in NSU heater tubes Details
8Supply of lead for sealing and sealing wire Details
8Procurement of PPCP compail containers for lubricants – 20L Details
8Tender for Agency for RCO verification audit Details
8Procurement Spares of M/s KSB Limited Make Pump spares Details
8Tender for Ultrasonic thickness Testing of above-ground and underground piping, Storage Tanks, and Mainline suspended crossings Details
8Procurement of Dresser valve spares for new unit Details
8Procurement of Eagle make Seal Spares Details
8Procurement of Pipe fittings for various process scheme jobs Details
8Tender for Procurement of Electrical Items Details
8Tender for GR for Calibration, Servicing, Inspection, and Rectification of ER probes on proprietary basis Details
8Tender for Three-year AMC of 03 CFR engines Details
8Tender for Hiring of security services Details
8Procurement of Bhagwati make Filter Element spares for M SQU & LAB units Details
8Comprehensive maintenance contract for one unit of Agilent HPLC system, Model No. Agilent 1260 II Infinity Details
8Procurement of hydrocarbon detection sensors of Netsafety make Details
8Procurement of compressor spares from Neuman & Esser Details
8Procurement Of Portable H2S Detectors Details
8Procurement of John Crane sealing seal spares Details
8Tender for Procurement of quartz sand Details
8Tender for Annual Maintenance Contract of 08 Nos. of Servo Gauges for 03 Years Details
8Tender for T4S audit services Details
8Procurement of large format display (LFD), size 75"/84" Details
8Tender for Mechanical Works For Process Modification Schemes Details
8Procurement of cascade hydrogen system Details
8Procurement of pipe fittings related to sprinkler systems for MOC schemes Details
8Three-year AMC of DSC & TGA with all related accessories Details
8Providing flow meter and volumetric measure calibration assistance Details
8Tender for Supply, Installation, Testing, and Commissioning of UPS and allied systems for the new laboratory building Details
8Tender for Revamping of washing unit Details
8Procurement of torque tube for ChemControls Details
8Supply and Implementation of Unified Endpoint Management Subscription for Endpoints and Windows Server Details
8Procurement of filter element, PN: 32012957, for compressor Details
8Tender for Procurement of SS single sink unit Details
8Tender for Consultancy services for Liaisoning and identification of Government Lands in Various Tehsils of Uttar Pradesh for Compressed Bio Gas (CBG) projects Details
8Tender for ISCC-CORSIA certification for SAF (Sustainable Aviation Fuel) production Details
8Supply, Installation, Testing, and Commissioning (SITC) of open-path type hydrocarbon detector Details
8Tender For The Supply Of Writing Pad Chairs Mangalore LPG Plant Details
8Tender for 2-year AMC for cathodic protection system of mounded storage vessel Details
8Supply of all items of Group A for MR Sr. No. 1.001 and Sr. No. 1.002 of MR top sheet Details
8Procurement of fixed-type H2S gas monitor Details
8Supply of online corrosion monitoring system Details
83-year Rate Contract for Servicing (OEM) of Atlas Copco Mobile Compressors Details
8Procurement of pour point depressant for HSD Details
8Tender for for Transportation of 30 KL Containerized Unit Details
8Providing services for handling of LPG cylinders Details
8Tender for supply and installation of new washing units Details
8Supply, Transportation, and Filling of odorant liquid and absorbent Details
8Hiring of services for application development, maintenance, and support for SAP systems Details
8Tender for Procurement of studs with nuts Details
8Procurement of slotting machine with 450 mm working stroke Details
8Tender for Supply of LT Cables Details
8Hiring of Services of 24 Nos. of CNG Trucks (09 Nos. 3MT trucks, 11 Nos. 9MT Trucks and 04 Nos. 15MT Tucks) for a period of three years Details
8Supply of know-how/license (BEDP), Proprietary catalyst, Proprietary items (if any), and related services for Poly Vinyl Chloride (PVC) unit in Refinery-cum-Petrochemical Complex Details
8Tender for Sulphur Pelletizer unit Details

You can also click on Tenders for more
For reference purposes the website carries here the following Newsclips (These are public domain newsclips and the website is not responsible for their content):
8Aemetis reports increased RNG capacity, higher ethanol production for Q3 Details
8ONGC delivers robust Q2 FY’26 performance under leadership of CMD Arun Kumar Singh Details
8Godrej Interio powers Kerala Metro projects Details
8Petronas gets two new exploration blocks offshore Suriname Details
8Masdar to join Austria's biggest green hydrogen project Details
8USA natural gas price pulls back before skyrocketing Details
8Shell cancels plans to build 2 wind farms off Scotland Details
8SDHI cuts first shipbuilding order worth $220 million for six chemical tankers from Rederiet Stenersen Details
8Oil rises on shutdown hopes Details
8Godavari Biorefineries, ICT Mumbai unveil CO2-to-DME green fuel innovation Details
8ONGC Q2 net profit rises 28.2% to Rs.12,615 crore; announces Rs.6 interim dividend Details
8Oil retreats on oversupply worries Details
8Mahanagar Gas charts new course in clean energy; expands into EVs, bio-gas, and solar power Details
8Lukoil declares force majeure at Iraqi oilfield following sanctions Details
8Indonesia Pertamina initiates start up of Balikpapan refinery's RFCC unit Details
8KPMG India urges integrated policy and investment push to scale sustainable aviation fuel adoption Details
8HPCL, MRPL buy 5 million barrels US, Mideast oil, sources say Details
8Electric cooking could power India’s clean energy future: IEEFA study Details
8State-run oil firms scale down ship requirement by half to 59 Details
8A new oil price war is now underway Details
8Venture Global swings to massive Q3 profit as LNG sales explode Details
8China's $468 billion energy drive sparks global oil market shakeup Details
8India races to replace Russian oil with U.S., Iraqi, and UAE crude Details
8ONGC shares worth Rs. 18.97 crores traded in NSE block deal Details
8Engineers India inks MoU with UAE's NMDC Energy for Saudi oil and gas projects Details
8Hindustan Oil Exploration Company's credit rating outlook revised to stable by India Ratings Details
8HPCL, MRPL buy 5 million barrels US, Mideast oil, sources say Details
8'India have stopped doing it': Donald Trump repeats Russian oil claim; US prez says he will ‘bring down’ tariffs Details
8Trump says US will lower tariffs on India soon, claims New Delhi has ‘stopped’ buying Russian oil Details
8Synergia Energy (AIM: SYN) advances Cambay field work program in India Details
You can also click on Newsclips for more
Details
We had said that the company has to go on to the next level a week earlier, and the management has just proved us right
8EBP20 capacity is already in place.
8Greenfield orders have slowed.
8The company now has to manufacture its own momentum through SAF, IBA-diesel blending, and lifecycle upgrades, not rely on the ethanol cycle to do the lifting.
Will it be able to do that?
Click on Details for more Details
New Page 1 8Report of the high-level expert committee on Vision 2040 – natural gas infrastructure in India [PNGRB] Details
8Audio recording of earnings call conducted on November 10, 2025 [GES] Details
8Transcripts of analysts’ call of Praj Industries Ltd. [Praj] Details
8Financial results for the quarter & half year ended 30th September 2025 [Aban] Details
8Transcript of earnings call [Adani Port] Details
8Intimation of Q2 FY26 earnings group conference call [EKCL] Details
8Investor presentation Q2 FY 2025-26 [Seamec] Details
8Financial results for the quarter and half year ended September 30, 2025 [Seamec] Details
8Audio recording of post-results conference call held on 10th November 2025 [Petronet] Details
8Update on Mozambique LNG project – resumption of development activities following improvement in security situation [OIL] Details
8Financial results for the quarter and half year ended on 30th September 2025 [ONGC] Details
8Financial results for the quarter and half year ended on 30th September 2025 [GGL] Details
8Investor presentation Q2 FY 2025-26 [GGL] Details
8Gujarat Gas announces Q2 FY 26 financial results [GGL] Details
8Audio recording link of earnings call held on 10th November 2025 [DIL] Details
8Intimation on continuation of credit rating for bank loan of Rs 500 crores [HOEC] Details
Details
8Propane is giving the company a run for its money in the industrial sector 
8And CNG and PNG will never give it the wings it so desperately needs
Click on Details for more Details
The PNGRB has come out with a Vision 2040 document
8From Direct Benefit Transfers for household PNG connections to Viability Gap Funding for pipelines and Market Development Assistance for biogas plants, the roadmap remains driven by fiscal incentives.
8India continues to present natural gas as a “market fuel,” but its economics still depend on government support to make the shift viable.
8The report acknowledges that gas demand has hit a roadblock as also domestic gas supply, and a subsidy driven push is the only way out, for now is the time as LNG oversupply will keep import prices down
8The report claims that India does not have the luxury of a 20-year glide path. It has a 7-year coordination challenge — between fiscal support, infrastructure rollout, pricing reform, and demand aggregation.
8Fair enough, the core reforms also hinge on transparency, institutional alignment, and political will — historically the weakest links. Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days.
Get the daily updates for :
8LNG
8Crude
8Chemicals
8Fertilizers
8Coal & Coke
8LPG
8Ammonia

Click on Reports for more. Details
1) Corrigendum scraps “proven source” waiver, hardens sub-contracting and corrects warranty PBG to 5% — ONGC Odalarevu CAAQMS/CEMS
8ONGC has removed a legacy fast-track experience waiver and fenced off sub-contracting in core engineering and QC.
8It also corrects the warranty PBG to 5% and tightens LD wording on mobilization.
8The scope and timelines stay firm, but the bar to qualify and deliver just got higher.
 
2) Bid deadline slides to 15 November with core terms intact in Oil India KG Basin helicopter charter
8Oil India has pushed the bid deadline to 15 November while keeping evaluation and security unchanged.
8The move buys bidders time to lock aircraft, crews and compliance packs.
8The payoff is better bid comparability with minimal schedule risk to drilling logistics.
 
3) Corrigendum hard-codes PoA rules, expands EMD/BSD framework, and adds anti-cartel guardrails — ONGC Ahmedabad scrapping winches
8ONGC has moved to close administrative loopholes while keeping the scrapping scope intact.
8Power-of-attorney is now codified down to entity-type, and bid security rules add teeth via a bid-securing declaration.
8The market will like the e-BG flexibility, but collusion warnings and longer EMD cover raise the bar for casual bidders.
 
4) Corrigendum stretches EMD cover, lowers post-bid threshold, and codifies PoA in ONGC Mehsana civil works RC
8ONGC has firmed up bid discipline for its Mehsana civil works rate contract.
8EMD validity now runs 135 days, post-bid conferences kick in from Rs 25 lakh, and entity-wise PoA rules are spelled out.
8The rules don’t change the scope — they change how cleanly and quickly it gets awarded.
 
5) Pre-bid pushed to 20–21 November with confirmation till 18 November; all terms unchanged for OIL coiled tubing unit
8OIL has slipped the pre-bid conference by roughly ten days, but kept the commercial spine intact.
8That gives OEM-backed bidders room to tighten Annexure-AAA responses and TPIA-verified dossiers.
8The gates on security, validity, and LD still hold, tilting the field toward fully documented plays.
 
Click on Details for more
Details
1) Two firms clear IOCL Mathura design-services technical round amid strict qualification filters
8IOCL Mathura’s engineering-services tender saw six participants but only two survived scrutiny. The scope spans full mechanical, civil, and electrical detailing using licensed CAESAR-II and STAAD software. Behind the numbers lies a tightening of PQC norms and compliance oversight that may redefine future design outsourcing in refineries.
 
2) HPCL shortlists four consultants for Chandrapur–Nagpur LPG pipeline reconnaissance survey
8Four firms cleared technical evaluation for HPCL’s 145 km Chandrapur–Nagpur LPG survey. The scope ties directly to PNGRB route authorization and expands HPCL’s LPG grid towards central India. Clause-level conditions reveal a compressed delivery model and tight risk allocation.
 
3) India’s first desi bio-ATF plant: Eight bidders

8For a crucial segment of the project, there seems to be adequate bidder response
8But the proof of the pudding is in getting the work done

Click on Details for more
Details
1) Winner for BPCL Patna LPG carousel contract
8BPCL has awarded its Patna LPG plant carousel upgrade to MEGAWORK Design & Engineering. The 12-station electronic system will replace the ageing 10-head unit, adding roughly 5,000 cylinders/day of bottling capacity. A tight 6% spread separates all three bidders, underscoring aggressive pricing and high compliance thresholds.
 
2) Greenleaf wins IOCL Gujarat Refinery tank audit consultancy
8A near-identical bid from Bridge & Roof narrowed the price gap to just 0.12 %. IOCL’s GeM-based consultancy tender compresses scope, risk, and pricing into one deliverable-driven model. The refinery’s tank integrity validation now moves to a unified API + OISD framework.
 
3) Bonace Engineers bags IOCL supervision contract for Kandla–Gorakhpur LPG pipeline
8IOCL has finalised Bonace Engineers as the Supervising Agency for its Kandla–Gorakhpur LPG pipeline works. The Rs 5.23 crore award covers all three regional groups under a six-month term. New Integrity Pact and Insolvency Code clauses mark a policy shift toward compliance-driven outsourcing.
 
4) Mazda Limited wins PLL Dahej ejector package as Chem Process trails by 86 percent
8Petronet LNG’s Dahej PDH-PP complex has moved a step closer to execution with EIL finalising Mazda Limited for the unengineered ejector package. The low Rs 80 lakh L1 quote beat Chem Process Systems by nearly double. Behind the numbers lies EIL’s new digital NDA and zero-deviation framework that is quietly reshaping vendor discipline for licensed process equipment.
 
5) Tempsens wins electric heater package for PLL Dahej PDH-PP project under EIL bid
8The Electric Heater tender for PLL’s Dahej PDH-PP complex has been finalised under EIL’s limited global bidding route. Tempsens Instruments emerged L1 at Rs 80.32 lakh, beating Alleima and Sona BLW by around 16 %. The award cements EIL’s tight-vendor strategy for flameproof electrical packages within critical fuel-gas systems.
 
6) K. Chandra Sekhar wins HPCL Visakh Refinery instrumentation services contract at Rs 4.93 crore
8A tight 0.17 % price spread defined HPCL’s latest instrumentation services award under the Visakh Refinery Modernization Project. Corrigendum C3 aligned the bid to GeM governance and eliminated brand-specific terms. The shift-service bundle now sets a template for HPCL’s future operations contracts.

Click on Details for more
Details
8Find out more
Click on Details for more Details
8Find out what is the progress made by ONGC so far in its contracting process
Click on Details for more
Details
1) Date pushes and blue-category design tighten Agartala CBG play
8OIL has slid the Agartala CBG bid from 28 August to 20 November while keeping two-bid discipline intact.
8Corrigenda re-anchor design to a 30% capacity safety factor, ten-year spares, and CPCB’s Blue category.
8The softer O&M policing and sharper statutory alignment could reshape bidder math.
 
2) Corrigendum tightens bid security, hard-codes 18% IGST regime, and calibrates penalties while holding PGTR gates
8ONGC has pushed enforceability up front and discipline downstream without loosening the revamp-under-operations mandate.
8The bid bond window is longer, the bid-securing penalty is explicit, and the tax playbook is locked to current notifications.
8The maintenance-delay recovery now has a cap, but the performance bar remains high.
 
3) Seven-day extension to 13 November sharpens bid hygiene on Part-2 pipeline works — OIL Dinjan–Dhakuwal–Makum project
8OIL has shifted the bid clock to 13 November 2025 without touching the commercial fundamentals.
8The move gives bidders more room to line up securities and portal-compliant uploads.
8The stakes now rest on who converts the extra week into cleaner bids and sharper pricing.
 
4) Sole participant on Hazira foam systems faces tight LD and post-commissioning cash cycle in ONGC semifixed foam retrofit, Hazira
8Only M/s GOI Engineers turned up for the Hazira tank-foam retrofit.
8The paperwork is unforgiving and the cash unlocks only after commissioning.
8What ONGC confirms or refuses in clarifications will decide whether a single-bidder path is viable or a reset looms.
 
5) L1 pick tightens rod-servicing turnaround with dual penalty levers
8A limited-vendor yard job just priced in weekly throughput discipline.
8A corrigendum narrowed scope wording while keeping destination inspection and rectification bite.
8The pricing spread signals both rational competition and one dramatic outlier.
 
Click on Details for more
Details
8A late corrigendum added stress-analysis lines and tightened price break-up rules.
8There were eight bidder in all
Click on Details for more Details
1) IOCL Paradip floats power trading tender under Category-I licence rules
8The Paradip Refinery has issued a tender to appoint a Category-I CERC-licensed power trader for open-access procurement via IEX. The contract eliminates EMD requirements but bars MSE and start-up relaxations. Its one-year ARC structure signals a controlled shift towards market-linked energy buying.
 
2) HPCL Visakh Refinery floats O&M tender for VRCFP substations
8HPCL has invited bids for two-year operation and maintenance of nine VRCFP electrical substations at Visakh Refinery. The tender introduces tightened PQC thresholds, reverse auction, and mandatory Integrity Pact compliance. Bidders must mobilise within 15 days of award with no rate escalation throughout the contract period.
 
3) Independent survey services tightened for Mangala–HRRL pipeline
8HPCL Rajasthan Refinery Ltd has reissued its surveying services tender for the Mangala–Barmer crude corridor with new IFIA certification and reporting norms. The document adds financial liability for losses and enforces two-vendor allocation to avoid transfer delays. Its tight scope underscores HRRL’s renewed focus on custody-transfer precision and data integrity.
 
4) Revamp tender issued for Ennore OWS-ETP by BPCL
8BPCL has floated a six-month revamp tender to modernise the Oil Water Separator and Effluent Treatment Plant at its Ennore Coastal Installation. The work covers complete replacement of pumps, filters and cabling to restore corrosion-affected systems. GeM migration and zero-EMD rules mark a notable shift in BPCL’s maintenance procurement model.
 
5) IOCL Mathura Refinery floats design services contract for on-site engineering support
8IOCL Mathura Refinery has invited bids for a two-year comprehensive engineering services contract to support process modification and ENCON jobs. The tender seeks 15 dedicated technical personnel on site with full hardware and software infrastructure under vendor scope. Unusual clauses on librarian deployment, vehicle supply and fixed penalty triggers set a new benchmark in refinery service outsourcing.