What is the latest update on BPCL's Bina-Panki multi-product pipeline? 8The EPCM consultant is readying the specifications 8When are RFQs expected? Click on Details for more.Details
For reference purposes the website carries here the following tenders: 8Hiring Services of Water Tankers Details 8Hiring services of 20 MT Crane Details 8Procurement of Electrical Panel of Well Services Details 8Design and completion of 4 x 500 MT Capacity Mounded Storage Vessels for storage of LPG Details 8Hiring EPMC Consultant for City Gas Distribution Project Details 8Coated Line pipe for Srikakulam Angul Pipeline Project Details 8Acquisition of 2-D seismic data in Kobochapori falls under Assam & Arunachal Pradesh Details 8Development of Digital Portal and Monitoring Dashboard for MOPNG – Phase 2Details 8Procurement of DG Sets Details 8Supply of SS Valves Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8Centre trying to 'surreptitiously sell' BPCL: Congress Details 8Raman Ojha succeeds Mansi Tripathy as country head of Shell Lubricants India Details 8Petrol, diesel prices slashed across the country today Details 8Reliance puts off gas bid to Nov 6 on bidders requestDetails 8Brazil authorities raise environmental concerns around oil auction Details 8Canada's Alberta moves closer to creating 'energy war room' Details 8Petrobras, Equinor tie up for natural gas projectsDetails 8China refiner issues $140 mln green bond to fund new capacity Details 8Several Asian refiners to get full Saudi oil supplies in November Details 8Oil prices rise as OPEC pledges decision on supply Details 8EIB to discuss end to fossil fuel lending at Oct 15 meeting Details 8Venezuela rejects Brazil accusations over beach oil spills Details You can also click on Newsclips for moreDetails
What is the latest status on Essar LNG terminal at Hazira 8Clearly, the location is advantageous and Essar's own steel mill and power plant will consume a large volume of gas from the floating-cum-onland LNG terminal. 8When are RFQs expected to come in
Details
Progress has been made in the Rs 1500 crore 50-well development drilling programme in the East and West Godavari districts. 8A public hearing is slated ahead 8RFQs are also being prepared Click on Details for moreDetails
With 5 LNG liquefaction projects reaching final investment decision (FID) so far in 2019, representing a record 63 mtpa, there is expectation that least another 10 mtpa of FIDs in the remainder of 2019 to balance growing demand post-2023. 8With 7 mtpa/month FIDed so far in 2019, record low LNG prices did not stop the industry going forward in addressing the post-2022 supply-demand imbalance. Click on Reports for more on how prices may stay low longer than expected
Details
What is the progress made by Atlantic Gulf and Pacific Company in setting up the I MMTPA Karaikal Floating Storage LNG Unit? 8It will have an offshore gas storage unit and an onshore regasification facility, accompanied by a LNG truck loading and pipeline transfer systems. 8The terminal is going to be strategically placed, right next to IOC's Ennore-Tuticorin pipeline Click on Reports for more
Details
The outlook for the economy has a whole may be bleak 8Q2 earnings are expected to be tepid 8But not for the oil & gas sector Click on Reports for more
Details
For reference purposes the website carries here the following tenders: 8Transportation of ATF Ex Mangalore Details 8Procurement of Bio-diesel Details 8Supply and Installation of Diesel Generator Sets Details 8Dismantling of Old Flare System at refinery Details 8Procurement of Centrifugal and Vertical Centrifugal Pumps for North Locations Details 8UPS System for Pipeline Project Details 8Hiring of services for Statutory Internal Inspection, Hydro Testing & Wet Calibration of LPG Mounded Storage Vessels Details 8Supply, Installation & Commissioning of Gas Analyser Apparatus/ Chromatographs Details 8Condition monitoring service rate contract for Drilling/ Work over Rigs & Workshop Equipment Details 8Integrated Shot Hole Drilling & Seismic Job Services for VSP seismic surveys to be carried out in Onland wells of Cauvery Basin and KG-PG Basin Details 8Hiring of services for repairing of Mud motors at Ankleshwar Asset Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8BPCL privatisation: Past challenges push govt to get fresh legal opinionDetails 8Reliance to resume Venezuela oil loadings after 4-month pause Details 8Centre trying to 'surreptitiously sell' BPCL: CongressDetails 8Investors get lost in Big Oil's carbon accounting maze Details 8China to prioritise fuel supply to 22 high-tech utilities Details 8Saudi Arabia assures world oil needs will be met Details 8OMCs Q2 earnings to recover after a dismal Q1 performance Details 8PetroChina's Kunlun Energy plans to repair Rudong LNG site by November Details 8Thai energy ministry sets March target to resolve Chevron dispute Details 8Oil prices drop as hopes for US-China trade progress wilt Details You can also click on Newsclips for moreDetails
Two events are anticipated 8RFQ for hiring an EIA consultant is expected by Q1 2020. 8RFQ for hiring of two drilling rigs is expected by Q4 2020. Click on Details for moreDetails
We are trying to map all DSF Round -1 & II fields for easy so that our subscribers can see them for easy reference and latest updates. In some cases, the identifying of contacts itself is a big challenge 8Here is an offshore block with a cluster of 6 fields named D-9, D-10, D-11, D-15, D-20, and D-21 8The PML is sought to be elicited 8Initial studies are ongoing 8The project involves development drilling of wells and laying of an offshore pipeline to connect with the nearest production facility. Click on Details for more.Details
It is a Rs 600 crore POL terminal 8Capital approval will only be sought after statutory clearances 8A tender for an EIA consultant is expected soon Click on Details for moreDetails
ONGC has begun negotiations with the L-1 bidder against its tender platform supply and anchor handling tug supply vessels. 8Find out what kind of rates ONGC is looking at through the negotiation process Click on Details for more
Details
There has been talk of a resource crunch at Nayara and yet the company is going ahead with the evaluation of bids for its capacity expansion and petrochemical projects, worth Rs 6000 crore. 8Find out what kind of packages are likely and who could be bidding Click on Details for more
Details
Potential bidders have begun seeking clarifications on the implication of the sale of BPCL on the investment plans of its subsidiary, Numaligarh Refinery Ltd 8Numaligarh is currently on a massive expansion spree, worth Rs 22,000 crore, but its viability is based on a 50% excise duty relief and a Rs 1000 crore capital subsidy from the government. 8"If BPCL is privatized, then the private owner may not want to go ahead with the expansion based on doles from the government", a potential bidder for the NRL refinery expansion told this website. 8Unless Numaligarh is sold separately to Oil India Ltd, which together with the Assam government, have a stake in Numaligarh, the future hangs in balance, it seems. While OIL may not have the appetite for NRL, Indian Oil Corporation, which has three refineries in the North East, may have the resources to take over NRL from BPCL. 8"Currently, there is too much uncertainty over everything", admits a top NRL officer. 8"So far not much money has been spent on the project, only a consultant has been hired and tenders have been published. But when it comes to bidding, there is effort required, and it costs money to bid as it involves a lot of homework. If the future is uncertain, then what the NRL management should do is wait and watch the developments and keep tendering on hold," the bidder said. Click on Details for moreDetails
For reference purposes the website carries here the following tenders: 8Supply of Mainline Centrifugal Pumps Details 8Civil, Structural and Architectural Work for LPG Pipeline Details 8Transportation of ATF Ex Vijaywada Details 8Supply, installation and commissioning of High Frequency Linear -Oscillating, Friction, Wear (OFW) test machine/ rig & Sonic Shear Tester with temperature bath facility Details 8Appointment of C&F operator cum secondary transporter at lubes depot Details 8Supply of MCT Blocks for BS-VI Project Details 8Rate Contract for Heat Exchanger Overhauling Details 8Supply of High Performance Silicon Sealant for Industrial Gasketing and Sealing purpose Details 8Revamping of exisitng hydrant system and replacing the existing deluge valves Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8EIL to soon start work on $1.2 bn Mongolian refinery projectDetails 8BS VI fuel will be available in country from April 1 next year: Javadekar Details 8$100 billion can be saved by the oil industry through digitalisation Details 8Setback for oil ministry: SC declines request to stay sharing of documents on RIL penalty Details 8Dharmendra Pradhan witnesses start of refinery work in Mongolia Details 8Mongolia thanks India for line of credit to support oil refinery project Details 8A first for NCR: Piped gas gensets for 5 city societies Details 8Russia's Rosneft tenders to sell first batch of oil products for 2020 Details 8Oil rises, buoyed by gains in industrial commodities Details 8Saudi energy minister, Russian minister discuss stability of oil marketsDetails 8Exxon to make $500 mln initial investment in Mozambique LNG project Details 8U.S. natural gas output, demand seen rising to record highs in 2019 Details 8Oil prices extend slide to third straight day, US-China trade doubts growDetails You can also click on Newsclips for moreDetails
ONGC's tender for the chartered hiring of 6 workover rigs seems to have grabbed a lot of attention. But keeping in view that there can be more bidders, ONGC has again extended, the bid submission date to 15th October 2019, with the previous one being 18th September 2019. 8Another extension up to November cannot be ruled out. 8The tender will involve deployment of 1,3,1,1 rigs to Ahmedabad, Mehsana, Cauvery and Rajahmundry respectively with a capacity of 50 MT, 50 MT, 100 MT and 150 MT respectively. As per the sources following players have shown interest in the tender: Find out who the potential bidders are
Details
Ahead of Adani Gas' stake sale to Total, the company is recruiting some fresh high level talent 8The promoters believe that ahead of the French connection, the company's management needs more management depth Click on Details for more
Details
As many as 11 candidates are in the race for the GAIL CMD's slot 8It is indeed a crowded field, but interviews will be held from a smaller subset of candidates Click on Details for more on these candidates
Details
8ONGC's tender for the hiring of 3D seismic survey services for Assam and Assam Arakan Basin has received a good response. More than three bidders are expected
Details
Get the latest update on: 8ONGC's offshore seismic tender for the GK-28/42 block along with C series and MB-OSHP-2017/1 blocks (Only two companies seem interested as of now) 86 well platform project (5 for GK-28/42 and 1 platform for GS-OSN-2004/1) and a 65 km subsea pipeline for connecting with the gas processing facility. (When is an EPC contractor RFQ expected?)Details
ONGC's tender for hiring a 1000 HP rig for six months was meant to be a one-horse race 8And the deal was meant to go to the company who already had a rig deployed 8But clearly, a competitor is interested in bidding too
Details
It is a brownfield polypropylene unit 8Investment is Rs 750 crore 8PMC already selected 8Find out when the licensor RFQ will come out Click on Details for moreDetails
It is a greenfield, Rs 1300 crore gas pipeline project 8Route survey is on 8The PMC route will be followed 8RFQ for FEED is expected in November, 2019 Click on Details for moreDetails
Adani Gas has set itself a Rs 9000 crore city gas distribution capex over the next 8 years 8For cities not connected to the gas grid, the company is going to truck in the LNG 8The company, like several others, are also eyeing the key markets of Mumbai and Delhi once open access rules are relaxed 8Also know more on the kind of valuation the company is expecting out of its 30% stake sale to Total 8Adani believes that LNG prices will remain soft right up to 2024, and it plans to leverage this development to push in spot LNG into India. Click on Reports for more
Details
PLL's investment deal with Tellurian is fraught with all kinds of risks 8The biggest being an upfront capital cost funding for supply of gas in the future 8After an initial negative reaction, analysts are now warming up to it Click on Reports for more
Details
8A public sector oil marketing company is now looking for an owner consultant to provide comprehensive business-ahead advisories and assistance for a thorough revamp of its existing interaction platforms.It is a big project by any standards, and a long list of consultants are expected to line up for it. Details 8Another company is looking at a technical E&P consultant for M&As in India and globally. Details 8Yet another public sector company is looking at a consultant to advise on management of power projects, DetailsDetails
What is the feedback that Petronet LNG has elicited from Qatar subsequent to the high level meeting on bringing down the price of long term gas? 8Now that spot prices are way cheaper than the Qatar contract price, and likely to stay lower for at least a year if not more, will Qatar renegotiate the price slope? Click on Details for more
Details
LNG demand faces headwinds in a country such as India. 8Affordability is a big question mark 8But there are other issues too Click on Details for more
Details
For reference purposes the website carries here the following tenders: 8Supply of U-Tube Bundles Details 8ARC for Supply, Fabrication and Installation of Transformer Gates Details 8Appointment of Technology Service Provider for Digital Transformation Details 8Supply of Igniters and Portable Igniters Details 8Electrical and Instrumentation Composite Works Details 8Supply and Installation of Flexible HDPE pipeline Details 8Transportation of Bulk POL products MS HSD and Branded fuels Details 8MFL and IRIS Inspection services Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips: 8BPCL's stake sale may prompt bond redemption: Moody's Details 8HPCL-MRPL merger plan yet to reach board level: HPCL chief Details 8Malaysia's Petronas sets up $350-mn venture capital fund Details 8Big greenhouse gas emitter moves to join climate initiativeDetails 8Madhya Pradesh: Transporters’ strike may leave your fuel tank dry Details 8PM Modi expected to visit Saudi Arabia soon Details 8BPCL nationalisation act repealed in 2016; way clear for privatisation Details 8CNG, piped cooking gas rate cut in Delhi, adjoining towns Details 8Petrol, diesel prices maintain dip as oil companies slash rates Details 8ONGC planning to drill 24 wells in Cauvery Asset at a cost of Rs 672 croreDetails 8Nayara Energy plans to add jetty at Vadinar port at a cost of Rs 500 crore Details 8Oil prices slip again amid gathering gloom over global economyDetails 8Iran says Chinese state oil firm withdraws from $5B deal Details 8Dharmendra Pradhan to visit Mongolia on October 8 Details You can also click on Newsclips for moreDetails
It will take time for Bharat PetroResources to come out with RFQs for the Karaikal field 8RFQs for the hiring of a EIA consultant and a PMC consultant is expected by Q4 2020. Click on Details for moreDetails
Cairn India COO Suniti Bhat has big dreams for the offshore block he has acquired under DSF-2 8The investment envisaged can eventually turn out to be quite large 8Find out more on when RFQs are going to be coming out Click on Details for moreDetails
Russian giant Rosneft, the owner of Nayara Energy, has had to take recourse to unconventional financing to meet its insatiable appetite for funds in the face of western sanctions 8Clearly, Rosneft has financed its global expansion by relying on its close relationship with the Kremlin 8But in the process, Rosneft has amassed debt ratios and costs of financing far above competitors. Click on Details for more
Details
The Indian gas market has a number of gas prices. 8There is domestic gas valued either at a government determined price or at "market price". 8There is long term gas, contracted by Petronet LNG, coming out of Qatar and other places, which is currently the most expensive. 8There is the US Henry Hub linked price, with cargoes brought in by GAIL. 8And there are spot prices of various hues 8The taxation regime is complex and vexing. Click on Details for an analysis of these prices, and when taxes are added, how they get eventually priced at the factory gate in India
Details
The National Green Tribunal order has forced the Indian ceramic hub, Morbi, to shift from coal to gas. Consumption is around 6 mmscmd. 8But the ceramic community is deeply unhappy. "The switch was meant to be more cost effective but is is not," said an industry representative 8Find out more on the cost economics involved for the industry 8What has happened to their attempts to find alternative gas supply sources, including delivery of trucked LNG? Click on Details for more
Details
A 5 MMTPA FSRU RFQ is likely to attract quite a few players, it seems 8There are at least three interested players, according to the project promoters, for this PPP project Click on Details for more
Details
The contracting process is going ahead in earnest in Numaligarh refinery 8More consultants are set to hired even as tenders are out for technology providers 8Find out what is up ahead Click on Details for moreDetails
IOC has been finetuning its Gujarat refinery expansion project 8The project cost has now been formally revised 8Find out more on what kind of configuration changes have been done 8The refinery expansion cost is now pegged at Rs 15,000 crore to Rs 20,000 crore 8The expansion is accompanies by a HGU revamp and a N-Butanol plant 8IOC is expected to give capital approval soon for the refinery expansion first and this is expected soon Click on Reports for moreDetails
What will be the impact of the current revision of gas prices on the urea industry? 8The cost of production of urea changes by around Rs. 1600-1800/MT for every $1/mmbtu change in the pooled gas price. 8But then only 42% of the industry's gas requirement comes from domestic production Click on Reports for more
Details
Elections, agitations, bandhs, and sometimes a hostile neighbourhood had deterred OIL for holding public consultations for major E&P projects in the North East 8But that seems to have cost the company dearly 8Here is a Rs 3500 crore drilling field development plan, which will mean that RFQ dates have to be rescheduled. Here is the update -- RFQ for hiring third party drilling rig is expected by Q1 2020. -- RFQ for hiring equipment and other oilfield services is expected by Q1 2020. -- RFQ for hiring an EPC contractor for production installation is expected by Q1 2020 Click on Details for moreDetails
Seismic tenders are now coming out in large volumes against OALP acerages 8The market is active 8And there are only a limited number of players in the fray 8But the going is not all that easy for everyone Click on Details for more
Details
What is the latest update on the LNG deal that Petronet LNG had signed with Tellurian? 8There is already a lot of activity inside Petronet on the next steps ahead 8Even a quick RFQ for a consultant is not ruled out Click on Details for more
Details
Low workover rig rates offered by OIL are troubling rig operators, so much so that at least one of them have decided to walk away from a deal 8Heavy competition, particularly by local companies, have commoditized this business, it seems Click on Details for more.
Details
In yet another case, OIL had put off a public hearing for a Rs 300 crore extended reach drilling programme for 7 development wells 8This will mean that the hiring process for a rig and well logging services will be delayed till Q2, 2020 Click on Details for more
Details