New online tendering mechanisms are now being hammered together in the aftermath of COVID-19
8This will possibly lead to more transparency and a permanent change in the entire tendering system.
Click on Details for more
Details
Planners in oil marketing companies may need to keep a close watch on mobility trends in the aftermath of COVID-19
8These trends already evident in areas already impacted badly by COVID may bring about changes in consumption patterns of petrol, diesel and CNG
Click on Reports for more.
Details
For reference purposes the website carries here the following tenders:
8Supply of ERW line pipes Details
8Procurement of API 6D Plug Valves Details
8Integrated Operation & Maintenance of ONGC Supply Base Details
8Architectural services for above ground structures for LPG Cavern project Details
8Supply of Medium Density Polyethylene Pipes Details
8SWC works Hyderabad-B Sales Area under Secunderabad Retail RO Details
8Supply of 450 SCMH Booster Compressor Package Details
8Annual Boiler IBR Inspection Jobs Details
8Supply & Installation of Condition Monitoring System on old MLPs at MDT & WIPS Details
8Requirement of ARC - Technical consultancy services for process & detail Engineering Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8Centre notifies land acquisition process for laying oil pipeline Details
8Demand for petrol increases in Pune Details
8Fuel prices may rise by Rs 5/litre after daily revision restarts Details
8Govt seeks USD 520 mn from Cairn Oil & Gas; co slaps arbitration notice Details
8Crude oil futures slump on weak global cues Details
8China, India soak up oil from floating storage as demand recovers Details
8OPEC, Russia bargain over oil cuts ahead of June meeting Details
8Oil prices fall as US fuel demand remains weak Details
8Court rejects bid to revive cancelled US pipeline program Details
8Russia's Rosneft finds extended oil cuts painful: sources Details
You can also click on Newsclips for more   Details
8Vendors are going through a step-by-step approach to fighting ONGC's revised price bid norms
 Find out more Details
8No work fronts are available right now, according to a pipeline supplier vendor
Click on Details for more Details
8Why are vendors being extra careful while dealing with the JV of Afcons Infrastructure Ltd and Sapura Energy Berhard which is working on a Central Processing Platform ordered by ONGC for the KG-DWN-98/2 block?
Find out more
Details
What is the latest status on H-Energy's attempt to build a connecting line from its LNG terminal at Jaigarh to GAIL's trunk pipeline at Dabhol?
8Why is it taking such an inordinately long time?
8And when is it likely to be completed now? Details
8Get a full insight into the LNG cargoes coming into India next week
8Who is getting what
Click on Reports for more Details
8The lockdown has not deterred the government from pursuing its divestment agenda of BPCL, it seems
Find out more
Details
Cairn India has been severely impacted by the lockdown and low prices
8Customers are not picking up cargoes, forcing wells to close
8There were 7000 workers on site
8Find out how many are left now, and what is next. Details
For reference purposes the website carries here the following tenders:
8Hiring of Services for Miscellaneous Petty Jobs in Engineering Services Details
8Road transportation of bulk POL products Details
8Supply of ARC Flash detective devices for distribution boards Details
8Supply of Spares for Tank Rim Seal Fire Protection System Details
8Rate contract towards procurement of anti friction bearings Details
8Procurement of Electrical Measuring Instruments Details
8Repair of Pipe Support Work at NCR Details
8Design and Commissioning of Clean Agent System for 200 KVA UPS and Battery Room Details
8Hydro testing refilling spare supply of co2 clean agent flooding system Details
8Supply, Installation and Commissioning of Manual Valve to Remote Operation for location under Dibiyapur Region Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8OPINION: How trading is a key missing link in India’s Oil & Gas armory Details
8Govt extends BPCL bid deadline to July 31 Details
8Middle East’s oil is still a favorite for India’s top refiner Details
8Oil well explodes in Assam, villagers evacuated Details
8Oil India reports blowout at well in Assam Details
8Govt looking at bringing natural gas under GST, pricing freedom: Petroleum Secy Details
8Low crude oil prices helped India save Rs 25,000 crore: Dharmendra Pradhan Details
8Rajasthan: Lockdown fails to hit oil & gas production Details
8Gas sector finds itself in bright spot Details
8Prices may be rising for world's cheapest gas in Venezuela Details
8Chevron to cut up to 15 per cent of staff amid restructuring Details
8Tamil Nadu inks deals for over Rs 15,100 cr investment, Energy in focus Details
8Judge strikes down US energy leasing rules in bird habitat Details
8Russia plans to drill oil wells and pump in 2022 when OPEC+ deal expires Details
8Virus sparks record drop in energy investment: IEA Details
8Crude oil prices fall on US-China tensions over Hong Kong Details
8Why US energy CEOs will get big payouts despite oil meltdown Details
You can also click on Newsclips for more
Details
The Mozambique LNG terminal in which the Indian trio of ONGC, OIL and BPCL are heavily invested, is in again in the news for the wrong reasons
8With worries mounting, the focus is now on the gas contracts which were served up to ensure FID in June, 2019
Find out more Details
Where there is a will, there is a way.
8And no one elucidates this principle better than this one company, which continued to deliver to clients despite the lockdown
Click on Reports for more Details
ONGC has started a fresh price bidding format in sync with the current times
8The idea, rightfully perhaps, seems to be to extract a lower price
8But vendors are upset Details
8Find out why for this particular industry, effecting a crew change is not just risky but also very expensive
8As a consequence, many players have not done the changeover yet but are under pressure to do so. Details
8Here is a public sector oil & gas major which has not reported a single virus case
8There is 100% office attendance five days a week, but for private contractors life is less than rosy
Know more
Details
8When is the next crew change going to take place in ONGC's offshore installations?
8Under normal protocol, crew change is effected every two weeks
Details
8ONGC had a big offshore coronavirus scare
8Find out how the company dealt with it quickly. Details
A Build Open Operate (BOO) model is used by refineries which want to outsource storage terminals, as well as other offsites and utilities to third parties
8This a good business model, where the BOO owner can look forward to steady incomes while the refinery is assured of a continuous supply of feedstock, fuel and gas needed to keep it running.
8But in India, the model is fraught with problems
Click on Details for more Details
Public sector oil & gas companies are under pressure to make available work fronts
8Lack of labour seems to be one big constraint for contractors working on oil & gas sites
8But there is another more worrying problem
Click on Details for more Details
For reference purposes the website carries here the following tenders:
8Procurement of Calibration Gas Details
8Road transportation of bulk petroleum products MS/ HSD/ Branded Fuels Details
8Supply of Di Ammonium Phosphate Details
8Supply of Anhydrous Ammonia Details
8Procurement of Orifice Plate Details
8Up keeping Services of GAIL Installations Details
8Polysulphide based Corrosion protection coating in cold area of NCU Details
8Supply of Freon Gas Details
8Procurement of check valve for Gas Turbines Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8NGT appoints panel to probe into ammonia leak in Manali Details
8Gas leak: SC grants 30 employees of LG Polymers access to its sealed plant at Vizag Details
8Vedanta seeks shareholders nod for delisting; e-voting till Jun 24 Details
8Hydrogen-fuelled mobility maybe the most enduring solution: S S V Ramakumar, Director, R&D IndianOil Details
8Modi govt denying people benefit of low oil prices; no other nation doing so: Moily Details
8BPCL launches cooking gas booking via WhatsApp Details
8Petronas in talks to acquire assets of Acme Solar Details
8Coronavirus: Oil and gas producers looking at substantially lower revenue Details
8OPINION: How advanced technology integration can transform the Oil & Gas industry Details
8Venezuela celebrates docking of tanker with Iran gasoline Details
8Oil climbs as suppliers stick to output cuts, coronavirus lockdowns ease Details
8Russia sees global oil market balancing in June-July - RIA cites source Details
8Higher margins to help offset volume dip for city gas companies Details
8US drilling industry says offshore ban would crush jobs, government revenues Details
8Crude oil futures rise on spot demand, global cues Details
8Crude oil prices climb as faith in supply cuts grows Details
8Oil slips on demand worries, Hong Kong tensions Details
8Pandemic forces virtual safety checks for oil tankers Details
You can also click on Newsclips for more   Details
What is the latest update on the much anticipated Daman Upside project
8Is a tender likely soon? Details
What is the latest on the Nandasan Suface Facility project.
8The EPC contractor was selected but has the award been given?
Click on Details for more Details
LNG imports were dramatically down in April, find out by how much.
8Also, what was the cost of these imports?
Click on Details for more Details
8Gas offtake was dramatically down in April , which are the pain points?
8Also GAIL finally clarifies on the Force Majeure clause and its applicability to domestic buyers of gas. Details
Indianpetroplus.com spoke to Shekhar R. Balvalli, an IIT alumni and Senior Vice President, Sales & Marketing of TechnipFMC India, on the recent grant of an LOA as the "Managing  PMC" for the Rs 22,000 crore Expansion of the Numaligarh refinery from 3 to 9 MMTPA. He was excited about the award, and was looking forward to working again in India's North East. Balvalli, who has nearly 40 years of work experience, spoke on a range of subjects, from the award of LOA from NRL to the outlook for the refinery sector and the impact of COVID-19 on the industry.
 
Tell us about the Numaligarh LOA. What will the job entail? 

 We have received  the LOA for the Numaligarh Refinery Expansion Project.
 One of our role is to perform basicdesign of open art units, including the 6 MMTPA CDU/VDU, the Amine Regeneration unit and Sour Water Stripper units as well as for utilities and offsites including tankages, bullets, pumps and loading as well as blending systems, power, raw water, cooling water, nitrogen unit, DM plant, natural gas distribution, fire fighting etc.
 We have the role as the Project Management Consultant (PMC), managing EPC contractors for the 6 MMTPA CDU/VDU, 3.55 MMTPA DHDT – a licensed unit and a Sulfur Recovery Block including ARU/SWS with 2*240 TPD SRU/TGTU as licensed units. 
 We will also perform the EPCM role (Detailed Engineering, Procurement Services and Construction Management services) for the licensed LPG Treatment Unit as well as utilities and offsite systems. Additionally, we will also be managing a BOO contractor to build the hydrogen plant and would also be coordinating and integrating with other EPCM contractors for two other packages.
 Thus as the Managing PMC we will work as an integrator of the entire complex.
 We are quite excited about this work, not just because we have won against tough competition but also because it will significantly add to the economic strength of the North East, providing jobs and opportunities to the local populace. 

The North East is one corner of India, will it be difficult for you to work there? 

 We are not new to the North East. I had camped in Guwahati while working on a CDU/CVU and Delayed Coker revamp for IOC’s refinery there. We were also the EPC contractor for the Guwahati’s refinery's Hydrogen and Diesel hydrotreater plants. We are currently in the last stages of commissioning  the Prime G unit in Bongaingaon and have executed a Hydrogen Reformer unit in Digboi refinery and  Hydrocracker heaters in NRL in the past.
 The current NRL job is bigger in scope, it is spread over about four years of execution and more than 3000 man months of construction supervision.
 Also, the government prioritized the Oil & Gas sector in the North East through its Vision 2030 statement and the NRL expansion project is an example of it. The NRL management has been very procative. Decision making has been very fast, and there is a determination from all sides to forge ahead. I believe this expansion is going to bring about an all-round development in the region.

Going beyond Numaligarh, how do you think COVID-19 is impacting your business?
 

 It is a new situation and our first priority is to keep people safe, not just our own employees but everyone connected with us. And then of course there are business repercussions as well. We are discussing the repercussions of work stoppages, and of migrant labour who have moved out. Even if we took care of labour working at our sites, they perhaps felt stranded, and wanted to go back to the safety of their families.
 We have resumed at all the sites i.e Bongaigaon , Haldia, Barauni, Sindri, Vizag and Panipat although at slower pace due to limited availability of workers and “new working norms”. We expect more clarity once the restrictions are lifted  on movement of people and we will have more clarity pertaining to completion of projects. We are restarting work at the Halida refinery, where we are mobilizing local people in the stage of commissioning of the DHDT Unit. In Vizag refinery expansion, where we are the EPC and have completed the EPCC 5 and are in the tail end of construction of the HGU (Hydrogen Generation Unit) and NIU (Naphtha Isomerisation Unit); whichever fronts are being made available, we are working on them. Wherever we could work, we have restarted work. There are places, where we are yet to begin work due to shortage of material supply, such as steel and cement
 With regard to New business opportunities, I think all our clients are moving ahead with their proposed projects and we are actively participating in the bidding process even during the period of lockdown.

Are you invoking the Force Majeure clause with your clients during the lockdown period? 

 Yes, we have had to invoked Force majeure clause in our contracts with clients, in some contracts the client itself has invoked the same. The government too has declared COVID -19 pandemic a force majeure event and it has proposed extension of time for infra projects such as ours. Although, we will be able to start work on all active projects but we face issues such as payment of wages to stranded labour at the project sites through the lock down period and now even after lock down is lifted partially in some project areas, force majeure continues as there is lack of transport to reach project sites and labour is wanting to return to their home towns. Then we have to abide by social distancing norms for executing the works which will impact productivity for quite some time. All these issues have been presented to our clients for resolution. We are hopeful that we will arrive at amicable solutions. Nevertheless, we will ensure our projects are completed with no compromise on quality. 

What about your own employees, will you retain all of them, as many companies are already issuing pink slips? 

  We have a very skilled and committed workforce totaling up to 3000+ people and we have no intention of letting anyone of them go. They do work on domestic projects as well as for our international requirements where we support our Group. Two years ago, around 30% of the work was done for domestic clients and the rest were global jobs, but last year, the ratio reversed, and this year less than half the workload is due to local projects. Our workforce remains occupied if not on local clients then on our international ones. Details
8Public sector companies have begun taking out indigenous bidders only clauses in its tenders
Click on Reports for more Details
8Get complete vessel-wise data of US exports of LNG here
8Also for contractors, find out which CGD work fronts are in red, orange and green zones
Click on Reports for more Details
The new BP chief executive has decided to sack half his top management team
8Many favourites of former CEO Bob Dudley have been told to go
8Will this move reverberate in India as well? Details
8Get complete vessel-wise data of US exports of LNG here
8As well price data
Click on Reports for more Details
Ports have been hit hard by the lockdown
8The ministry of shipping has given some relief but will that be enough?
Click on Reports for more Details
The cash back for US LNG terminals remains negative on forward prices for LNG deliveries right through till September or more
8Many non-US LNG suppliers can live with this level of pricing at least for the short term but not offtakers of LNG from US terminals
8In this context, what happens to GAIL cargoes to be lifted off the US terminals? GAIL needs to lift 5.8 MMTPA of LNG every year from the US
8A well placed GAIL source spoke to this website and clarified where GAIL is placed in this context.
Click on Details for more
Details
There was a fear among gas suppliers that high cost ammonia-urea plants may eventually become white elephants because of their high cost and a much higher level of government subsidy needed to keep them going.
8The urea is sold at a sixth of the cost of production of a new unit, and the rest is given as a subsidy from the exchequer.
8Each urea unit consume a massive 2.4 mmscmd of gas
8Is that fear justified?
Click on Details for more Details
For reference purposes the website carries here the following tenders:
8Procurement of Low Density Ammonium Nitrate Details
8Supply of Nucleonic Level Instruments Details
8Supply of BPCL make Pump Spares Details
8Annual Rate Contract for Supply of Mass Spectrometer Spares Details
8Transportation of Product Sample Containers from Vadodara Terminal to Ahmedabad TML Details
8Supply and installation of Pre-fabricated office buildings with associated electrical works at refinery Details
8Retail Outlet Automation - CAMC for existing ORPAK/ GVR outlets for one year with an option of extension for 1 more year Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8Repos Energy plans producing over 3,000 mobile petrol pumps in FY21 Details
8Odisha ready for next level of industrial growth in post- COVID scenario: Pradhan Details
8IL&FS invites EoI to sell its 26 per cent stake in OTPC Details
8Moody's revises outlook on Adani Abbot Point Terminal's rating to stable, affirms Ba2 rating Details
8India's April crude processing in biggest drop in at least nearly two decades Details
8NGT appoints panel to probe into ammonia leak in Manali Details
8Oil climbs as suppliers stick to output cuts, coronavirus lockdowns ease Details
8Higher margins to help offset volume dip for city gas companies Details
8Oil, gas giants may get tax sop as govt works on lifeline Details
8City gas operators seek tax relief, loan restructuring to deal with lockdown impact Details
8China's 'hermit' investors fill doubled oil storage with crude bet Details
8Qatar ready to discuss India’s demand to cut long-term LNG prices Details
You can also click on Newsclips for more   Details
Public sector oil marketing companies are unwilling to oblige contractors beyond a point in the aftermath of the lockdown
8Find out more on what they are willing and unwilling to give on account of the lockdown. Details
On a Rs 10,000 crore work front involving building process facilities, L&T seems to be have run headlong into trouble in the aftermath of COVID-19
8Completion times lines will now have to be extended by at least six months if not more.
8Around 5 mmscmd of gas supply will be stranded as a result
Click on Details for more Details
8A new entrant wants to get into the watertight ATF distribution system
8It will be up against entrenched vested interests but in the process it has set the cat among the pigeons
Click on Reports for more. Details
PLL has backed out of the Tellurian LNG terminal
8Did the Indian LNG major miss out on a good opportunity, even in the post-COVID aftermath?
Click on Details for more Details
8Cairn India's face off with its service providers is costing the company dearly
Click on Details for more Details
City gas distribution companies did not pass on the entire reduction in APM gas prices (from USD3.23/mmbtu to USD2.39/mmbtu) starting 1st Apr’20 to end customers.
8So, these are now favourties of punters as the economy revives
Click on Reports for more Details
How bad was the POL demand degrowth in India?
8Exact numbers have come in
Click on Reports for more Details
India is meant to be gas resilient economy, with a high gas price elasticity to demand.
8Even under the crisis, global gas demand is expected to go up not down in 2019 in comparison to 2020
8But, according to latest estimates by a reputable institute, why is it a different story in India?
8Also, how will global gas prices behave through 2020?
Click on Details for more Details
In a first, monopoly player GAIL has shown a willingness to play second fiddle in the Indian gas market
8What brought about a change in the mindset?
Click on Details for more Details
Indian retail outlet prices should ordinarily have gone done but they will go up despite crude prices being down
8Not just that refineries will also be in a spot in more ways than one
Click on Reports for more Details
The rout of US-origin LNG continues, with GAIL in a particularly tight spot.
8June looks bad, and this trough will continue until September at the least
8Our weekly arrival data shows US LNG cargoes are still streaming into India. How is that happening?
Click on Details for more Details
An extraordinary inter-regional project is in the offing which looks at eliminating plastic waste by replacing 20% of coal usage by the cement industry
8This will mean that these companies will co-process the plastic waste
8The model can be replicated in other energy-intensive industries
Click on Reports for more Details
For reference purposes the website carries here the following tenders:
8Supply of Epoxy Grouting material Fosroc Conbextra EP75 for Mainline pumping unit Details
8Annual Maintenance Contract for Emission Monitoring Analyzers at refinery Details
8Conducting Quantitative Risk Analysis (QRA), Hazardous Operability Study(HAZOP) and Updation of Emergency Response and Disaster Management Plan (ERDMP) for the locations under Koyali Base Details
8Supply of Fasteners at refinery Details
8Procurement of Pressure Gauges at refinery Details
8Supply of 210 Ltr HDPE Containers for HPCL Mazgaon and Silvassa Terminal Details
8Providing maintenance of manpower at all RRKPL locations Details
8Supply, Installation and Commissioning of Odorizing System Details
8Annual Rate Contract for the operation of Effluent Treatment Plants Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8CPCL to raise Rs 1,000 cr through bonds issue in FY21 Details
8Gail India issues tender to buy and sell LNG cargoes: sources Details
8Indian economy to contract in FY21; lockdown compounds economic challenges, says Moody's Details
8India's petroleum product demand to fall 8 per cent in 2020: IEA Details
8Haryana gets its first grid connection biogas plant Details
8Dharmendra Pradhan reviews pipeline projects worth approximately Rs 8000-crore, pitches for Aatmanirbhar Bharat Details
8India's crude oil imports fall, product exports surge in April Details
8Pradhan sees fuel demand reaching pre-Corona level next month as India gets back to work Details
8No one can predict where oil prices will stabilise: Dharmendra Pradhan Details
8Govt working on relief measures for oil producers Details
8Seize LG Polymers premises, orders Andhra HC over gas leak Details
8Reliance estimates USD 200-400 million liability in KG-D6 cost recovery dispute Details
8Odisha ready for next level of industrial growth in post- COVID scenario: Pradhan Details
8The trader who called the 2020 oil crisis Details
8Lockdown easing traffic upsurge drives gasoline higher Details
8Saudi Aramco's Bahri puts LNG tanker plan on hold Details
8U.S. shale bust slams rural economies as oil checks shrivel Details
8BP's Looney halves top management roles in energy transition plan Details
8UK court throws out Nigerian oil corruption case against Shell, Eni Details
8Spot LNG price crash set to make life harder for Indian suppliers of long-term gas Details
8The oil and gas sites hit by coronavirus in Russia, Kazakhstan Details
8Sebi to seek timeline from MCX on upgrade of technology platform Details
8Iranian fuel starts arriving in Venezuelan waters despite U.S. warning Details
You can also click on Newsclips for more   Details
Shell Hazira terminal seems to be busy all of this week
8Four cargoes are transacting at the terminal
8This clearly means that the terminal is not under tank top conditions
8Cargoes are coming in for Shell, RIL as well as GAIL
Click on Details for more Details
8A tender is coming out for offshore rigs
Find out for how many rigs and when Details
ONGC has completed crew change not just in its offshore installation but across its onland assets
8The protocols are very strict and private contractors will also have to fall in line
8"It is vital that we keep the virus out from out installations," a top ONGC official told this website.
Click on Details for more Details
 1 2 3 >  Last ›

Showing 1–50 of 212 items