Technical Ammonium Nitrate Greenfield Project 8Cost: Rs.1170Cr. 8Project Event: 70 % of the construction and Construction activities have entered the final phase. All major equipmentincluding the ammonia converter, neutralizer, and absorption columnhas been installed and tested. Structural and piping works are now fully completed. Electrical and instrumentation (E&I) installation has substantially progressed, with loop checking and system energization currently underway. Pre-commissioning activities such as hydro-testing, system flushing, and equipment dry runs are nearing completion. Integration of Casale SA technology with the plant’s distributed control system (DCS) is in the final stage, with performance validation and safety interlocks being tested. The project is likely to be commissioned by October 2025. SSP/GSSP Greenfield Project 8Cost: Rs.59Cr. 8Project Event:The company is still awaiting environmental clearance for its greenfield SSP and GSSP plant at Roha, Maharashtra. The clearance process is in its final stages, with approval now expected by the end of Q2 2025. Internal planning and technical evaluations are ongoing. The RFQ for the local contractor, initially delayed, is now anticipated to be issued shortly after the environmental clearance is granted.Details
8Extension of charter hire for vessel SEAMEC III [SEAMEC] Details 8SEAMEC awards contract to Adsun Offshore for diving services on PRP-VIII & DUDP projects of ONGC [SEAMEC] Details 8Notification for ROU acquisition under PMP Act, 1962 – Cauvery Asset Pipeline Project in Ramanathapuram Taluk, Tamil Nadu [Gazette] Details 8Land acquisition notification for Cauvery Asset Pipeline Project under PMP Act, 1962 – Nagapattinam, Tamil Nadu [Gazette] Details 8Snapshot of India’s oil & gas data [PPAC] Details 8Revised date for open house on draft PNGRB amendment regulations, 2025 [PNGRB] Details 8Comments received on PCD for tariff review of EWNGPL by Pipeline Infrastructure Limited under PNGRB tariff regulations, 2008 [PNGRB] Details 8Appointment of Ms. Sneha Parab as company secretary and compliance officer [Agis] Details 8Financial results for the quarter and financial year ended March 31, 2025 [AES] Details 8Asian Energy Services Limited reported robust performance for FY25 [AES] Details 8Investor presentation May 2025 [AES] Details 8Change in board of directors of the company [EIL] Details 8Results presentation for Q4 and FY25 [KPIL] Details 8Transcript of Q4 & FY25 earnings conference call [MIL] Details 8Appointment of Shri Moti Lal Meena as independent director w.e.f. May 17, 2025 [OIL] Details 8Change of investor relations advisor [HOEC] DetailsDetails
From February to May, has seen nine date shifts. 8Revised BECs, rig sourcing constraints, and Make-in-India rules appear to be slowing bidder readiness. 8Though bidders quote for 1–3 rigs, pricing must be for 5, creating valuation friction on GeM. Award split rules add further layers of uncertainty, prompting requests for more time. 8Whether it's owned, leased, or under purchase, every rig needs proof—MoUs, OEM POs, RCs. Bidders not ready with paperwork are pushing for time, causing repeated deferments. Click on Details for moreDetails
In a QCBS-style bid, this company has been awarded a high-end seismic imaging job 8The job involves complex thrust zones of Assam and Arunachal Pradesh 8A 5-month timeline includes test processing, PSTM, PSDM, parameterization, and final presentations—each tightly bound to QC checkpoints and contractual penalties. 8This marks its entry into national geophysical consulting. Click on Details for moreDetails
Away from headline sectors like PNG and EVs, parallel LPG has built quiet influence in logistics, bulk heating, and industrial kitchens. 8But scale remains elusive. Click on Details for more
Details
8PIL warns of price spikes and planning failures if future capex is ignored now and backloaded later. 8Their fix: accept 75% of validated capital projections now, rather than wait for the truing-up cycle. 8It’s a call for tariff stability vs rigid compliance.
Details
8PIL warns of price spikes and planning failures if future capex is ignored now and backloaded later. 8Their fix: accept 75% of validated capital projections now, rather than wait for the truing-up cycle. 8It’s a call for tariff stability vs rigid compliance.
Details
8GSPL highlights the risk that capex from other GAIL arms (like TEL) is being absorbed into pipeline tariffs. 8The regulator is being urged to ring-fence the tariff base and prevent cross-subsidization between gas infrastructure and other businesses. 8Then again, following the merger of multiple pipeline systems into one by GAIL, GSPL argues that data granularity has been lost and tariff calculations muddied. 8The integration, while simplifying operations, may be undermining price neutrality and regulatory clarity. 8In a pointed remark, GSPL reminds PNGRB that it was required to submit detailed spur-line breakups in past filings—and demands the same from GAIL. The call reflects an industry-wide concern over perceived asymmetries in regulatory treatment.
Details
GSPL shows side-by-side capacity data to argue that GAIL revised normative volumes downwards post-network integration. 8The move, they claim, distorts tariff rationality by increasing unit recovery unfairly. 8This, it is alleged will potentially setting a precedent for future tariff filings.
Details
8SHM, SS Offshore, Alphard, and Hoger Marine all in the fray 8ONGC’s pre-qualified panel could emerge as India’s definitive offshore support fleet for the next cycle.
Details
8GAIL’s tariff submission is under attack from peers and investors alike. 8GSPL alleges inflated OPEX and volume manipulation, 8PIL challenges the exclusion of prudence-cleared future capex. 8But the regulator is unlikely to reassess the cost foundation of India’s largest gas utility. 8Then again, PIL warns that ignoring forecasted capex until purchase orders are raised creates tariff volatility. GSPL, meanwhile, urges strict exclusion of capex from GAIL’s non-transmission businesses—raising the broader question: Is India’s tariff-setting logic truly forward-looking?
Details
Several bidders flagged mismatch between international certificates and ONGC’s format demands. 8The PSU offered some leeway but maintained its insistence on documentation uniformity. 8Also, with vessel age and DP class now major scoring parameters, many older AHTS and OSVs could be pushed to the sidelines in this round of empanelment.
Details
This isn’t just another L1 race. 8The empanelment process has evolved into a documentation-heavy, spec-sensitive filtration for long-term fleet planning.
Details
8Which contract are these companies in the race for? 8Tecnicas Reunidas 8JNK Heaters Co 8ITT SPA 8Thermax Babcock and Wilcox Energy Solutions 8The competitive bidding process signals robust international interest in India’s expanding downstream infrastructure. Click on Details for more
Details
8Vendors caution that continuous duty operation of air vaporizers may cause freezing. EIL responds with vague reassurances but no formal design relaxation. 8From motor sourcing to analyzer configurations, vendors raised over two dozen clarifications. 8Yet corrigenda focus only on deadlines, not design refinements. 8A pattern of vague acknowledgments marks EIL’s replies to key commercial and technical queries. No scope reduction or relief has been granted. Click on Details for more
Details
8Four engineering majors battle for a critical integrity assessment and refurbishment package at this big gas separation hub. Click on Details for more
Details
8With no competitors, L&T now faces detailed scrutiny on its plans 8The sole participation underscores both the package’s complexity and L&T’s confidence in high-spec solutions. Click on Details for more
Details
There is a limited vendor list 8Clarifications are needed on material choices and erosion control in high-pressure environment 8Answers have to be given on mechanical seal integrity for 50 bar service, signaling zero tolerance for fugitive emissions. 8With addenda rolling in, vendors must realign their data-sheets to match revised suction conditions and NPSH requirements. 8Crafting a vertically oriented, single-stage pump for a critical petrochemical loop, suppliers must marry precision hydraulics with rugged reliability. Click on Details for more
Details
8IOCL wants full-cycle PMC support—from design vetting to commissioning oversight—for its polymer unit upgrade. 8The contract duration indicates the scale and risk of execution. 8Interestingly, the contract explicitly removes all alternate dispute redressal routes. Vendors must prepare for direct legal escalation in the event of conflict. Click on Details for more
Details
8From depots to terminals, Indian Oil is hunting for watchdogs to monitor construction excellence. 8Two-year PMC opportunity opens up Click on Details for moreDetails
This refiner now looking at getting into the possible manufacture of the following products 8Iso-Propyl Alcohol (IPA): Used in chemical, pharma, and cosmetics. 8Polymer Grade Propylene: Critical for plastic and synthetic manufacturing. 8R290 Propane (Refrigerant Grade):Eco-friendly refrigeration solution. 8White Oils: Spanning pharma, cosmetics, industrial, and technical applications. 8Find out how the company is going about doing Click on Details for more
Details
It is easy to get month-old import data but it is difficult to solicit forthcoming shipment information in India. We go through a laborious process of data collection to get you full import information, including company-wise, quantity-wise, port-wise, vessel-wise cargoes which are coming into India in the next 15-to30 days. Get the daily updates for : 8LNG 8Crude 8Chemicals 8Fertilizers 8Coal and Coke 8LPG 8Ammonia 8All tankers 8Bulk and Dry cargo Click on Reports for more.Details
For reference purposes the website carries here the following tenders: 8Hiring services for the replacement of existing damaged or overloaded cable trays Details 8Tender for ice cleaning jobs during LEB, DHDT, NHGU and Ref-I M&I shutdown-2025 Details 8Tender for mechanical and electrical equipment testing Details 8Hiring of third-party inspection agency for conducting topographical survey Details 8Tender for carrying out annual maintenance contract for high volume long range monitors Details 8Supply, installation, testing and commissioning (SITC) of 1500 KVA step-down transformer and 11 KV / 630 A vacuum circuit breaker Details 8Tender for non-comprehensive annual maintenance contract for the PLC-based ILSD system Details 8Maintenance contract for gas monitoring system for a period of three years Details 8Annual rate contract for vibration monitoring and signature analysis of vibration data of rotary equipment Details 8Comprehensive maintenance contract for fire detection, fire alarm, fire hydrant, and sprinkler systems Details 8SITC of 45 intrinsically safe handheld VHF set and 2 analog base stations & disposal of 45 VHF Details 8Supply of fire fighting and safety items Details 8Hiring of PMC services for supervision & quality oversight of plan/non-plan works Details 8Tender for annual maintenance contract of fire engines Details 8Supply of Xtragreen diesel fuel Details 8Tender for production, operation, and maintenance services for diesel exhaust fluid manufacturing plant Details 8Tender for operation of in-house statutory testing & painting facility Details 8Hiring of OEM business promoters for liaisoning of OEM business Details 8Hiring of consultancy for decommissioning cost estimation – OGT, OOT, EOA & HPHT onshore facilities Details 8Tender for repair of air end (LP stage) of airpack compressor of SCA process complex Details 8Tender for repair of suction valve, discharge valve and pocket valve assembly of C 1470-B booster compressor Details 8Tender for empanelment of vendors for charter hiring of vessels i.e. AHTS, OSVs and PSVs for offshore Details 8Tender for repair and maintenance of AC of DC PCR of E 2000 9 rig Details 8Supply of testing and calibration of protective relays Details 8Supply of fasteners for AG/UG piping in MSB, PFCC, GDS, and FF units Details 8Design, development, fabrication, supply, installation and commissioning of 425 kg evacuation system with tilting arrangement Details 8Supply of fasteners for aboveground and underground piping in MSB, PFCC, GDS, and FF units Details 8Procurement of MI instrumentation spares required for GT-4 major inspection Details 8ARC for overhauling and servicing of Easun make tap changing system for 110 KV yard transformers Details 8Tender for laying of ductile iron pipeline along the Shahdara drain for DJB water supply project Details 8Supply of spring hanger supports Details 8Supply of coupling for 7" x P-110 BTC casing Details 8Procurement of pilfer-proof plastic seals Details 8Supply of trolley-mounted water-cum-foam monitor Details 8Supply of SPX pump spares including compatible parts Details 8Providing assistance in day-to-day maintenance activities of mechanical equipment Details 8Supply of FS Elliott make compressor spares Details 8Expert services for troubleshooting and maintenance support for BHEL make Metso governor system of STG4 Details 8Supply of junction box and panel Details 8Procurement of sand for LPG sand filter & gasoline sand filter in FCCU Details 8Supply of spares for Forbes Marshall make control valves Details 8Supply of steel pipes for water and sewage Details 8Supply and servicing of FRP fan blades Details 8Supply of Maxflo make thrust bearing for industrial equipment applications Details 8Supply of CS gate valve Details 8Procurement of HONEYWELL spares Details 8Tender for commercial vehicles arrangements for proposed parliamentary committee Details 8Tender for online valve changing machines equipped with robotic arm for automated industrial operations Details 8Procurement of fittings Details 8Tender for repairing of roads in plant area Details 8Tender for overhauling or servicing of CDU2 RCO pumps GA41014A/B/C during phase-2 refinery turnaround Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips (These are public domain newsclips and the website is not responsible for their content): 8Aramco to explore refinery upgrade, LNG stake as part of $90 billion deals with US heavyweights Details 8US LNG player brings Jamaican assets into its fold Details 8Italy’s Edison welcomes inaugural LNG cargo from Louisiana plant Details 8Glencore to offtake 2 million tpy of LNG from Commonwealth LNG Details 8RIL secures $2.98-billion loan, India’s biggest since 2023 Details 8India, EU launch joint research calls on marine litter and green hydrogen Details 8Odisha Plans $14 Billion Petchem Hub, Indian Oil to Invest Details 8Net Zero Pathways: Centre approves setting up of 5 carbon capture and utilisation testbeds Details 8Gas leak after chemical tank collapses in Tamil Nadu factory hospitalises 29 Details 8India, EU launch joint research calls on marine litter and green hydrogen Details 8LPG sales grow 5.1% in FY25, 43.6 lakh new customers enrolled Details 8IGL expands PNG supply to 111 more Delhi villages; total coverage reaches 241 Details 8Mukesh Ambani's Reliance gets $2.9 billion in biggest India loan since 2023 Details 8Oil falls more than 1% on expectations for US-Iran nuclear deal Details 8Petronet LNG requests extra land for Dahej petrochemicals complex project Details 8South Korea’s LNG Tankers to be Fully Lined with Russian Plywood Details 8India, EU launch joint research calls on marine litter and green hydrogen Details 8Allocate govt land for Bio-CNG plants: CG govt to collectors Details 8Amid plan to shrink legacy waste, Deonar dump ‘grapples with’ energy and bio-CNG projects Details 8Korean clean fuel company Bio Friends to set up $30 million DME plant in Assam's Namrup Details 8Illegal LPG cylinder refilling station busted, eight arrested Details 8Cairn Oil & Gas reaffirms conservation efforts in Kaziranga on National Endangered Species Day Details 8Tripura Enters Hydrocarbon Map as Oil India Drills First Well Debtamura, Gomati District Details 8Oil spills and industrial waste in rivers and coasts put marine life and human health at risk Details 8India's oil demand to surge by 3.39% in 2025, doubling China’s pace: Opec report Details 8Vedanta’s 2030 vision, 30% of its workforce will be women Details 8Oil India commences production activities in Tripura via Well Debtamura 1 Details 8India’s Oil Imports Hit Record High as Demand Surges Past China Details 8OPEC sees India's oil demand rising 3.4% in 2025, double the pace of China Details You can also click on Newsclips formoreDetails
Coal to Ammonium Nitrate Greenfield Project 8Cost: Rs.11782Cr. 8Project Event: The bid submission deadline for the Ammonia Synthesis Plant under the Joint Venture project has been extended from May 15, 2025, to May 30, 2025. Additionally, the Nitric Acid & Ammonium Nitrate project's deadline has now been extended from May 15, 2025, to June 23, 2025. These changes follow a series of earlier extensions from the initial deadline of February 28, 2025, to March 31, 2025, and then to April 30, 2025, primarily due to a lack of suitable bidders. Suphala Plant Revamp Project 8Cost: Rs.50Cr. 8Project Event:The Expression of Interest (EOI) from vendors for revamping the Suphala plant's Reaction Scrubbing A system to handle higher loads has been released. The bid submission deadline, initially set for May 10, 2025, has now been extended to June 5, 2025Details
8Appointment of cost auditor [IRM] Details 8Financial results for the quarter and year ended march 31, 2025 [IRM] Details 8Investor Presentation Q4FY25/FY25 [IRM] Details 8Monitoring agency report for the quarter ended march 31, 2025 [MAN] Details 8Successful drilling of well ksg-71 and spudding of well ksg-72 in kharsang block [HOEC] Details 8LPG profile report for fy 2024-25 [april 2024 – march 2025] [PPAC] Details 8Pre-empanelment conference for tpas on consumer satisfaction survey scheduled on may 16, 2025 [PNGRB] Details 8Comments received on pcd for tariff review of ingpl of gail (india) limited under pngrb tariff regulations, 2008 [PNGRB] Details 8Additional session in auction market [IGX] Details 8Financial results for the quarter and year ended march 31, 2025 [CSL] DetailsDetails
A big price spread across delivery hubs shows that state taxes and transmission charges remain key distorters of market parity. 8Also, Infrastructure bottlenecks and tax edges continue to shape India's gas geography 8Then again, a large movement of gas through Gadimoga complex under the domestic ceiling price regime—raising concerns about how “free” India’s gas market truly is
Details
8Despite rapid infra build-out and guaranteed offtake, Adani’s flagship terminal lags behind in throughput. 8What is happening with the take or pay contracts with IOCL and GAIL? Click on Details for more
Details
By allowing only pre-approved ETPs for this contract, the door remains firmly shut for newer players, despite rapid global advances in electrolyser technologies. 8This could delay domestic diversification in green hydrogen tech. 8The exclusion of open competition contradicts the broader Make in India push for technology localization. 8Experts warn this model may keep India tethered to a narrow innovation pipeline. Click on Details for moreDetails
For reference purposes the website carries here the following tenders: 8Tender for operation and maintenance of electrical systems Details 8Annual maintenance contract for clean agent fire suppression system and fire alarm system Details 8Procurement of Liquid Mounted Foam-Type Rim Seal for Floating Roof Storage Tank Details 8Annual maintenance service for desktops, laptops and peripherals Details 8Comprehensive maintenance contract for IT infrastructure of database group Details 8Supply of dissolve acetylene Details 8Tender for rectification testing and commissioning of already laid MDPE gas pipeline in Sangli Satara GA Details 8Tender for Turnkey Package for Mechanical & Instrumentation (M&I) Jobs Details 8Supply of lithium-ion cells and batteries for portable application Details 8AMC of tank wagon unloading operations Details 8Expression of Interest (EOI) for Supply of Roto Press Seal Details 8Providing services for subscription of codes and standard Details 8ARC for External ECT, OD Laser Scanning & Rapid RLA of Reformer Tubes in HMU-1 & HMU-2 during TA-2026 Details 8Tender for hiring API/BPCL approved third-party inspection agency for metals, fabricated products & oil & gas Details 8Providing expert services for Koden make radar equipment Details 8Tender for Branding of Tank Trucks (TTs) Transporting POL Products Details 8Tender for repair of Simplex make fire alarm system Details 8Tender for electrical & instrumentation works including supply Details 8Tender for Refurbishment of INERGEN System Details 8Three-year rate contract for in-situ machining of flanges above 42 inches Details 8Annual rate contract for operation assistance in critical process units Details 8Tender for remnant life assessment (RLA) study of two captive power boilers Details 8Tender for supply, transportation, and fixing of hoardings, banners, and other substrates at retail outlets Details 8Tender for collection & disposal waste management service Details 8Procurement of 3” full bore ball shutdown valve and wafer type butterfly valve Details 8Supply of flanges Details 8Tender for 3D laser scanning, structural analysis (FEA), and drawing modification for product tank TK17 Details 8Tender for procurement/fabrication of carbon steel tower Details 8Tender for site enabling works: grading, roads, drains, and barricading for lube modernization & bottom upgradation project Details 8Expression of interest notice for technology licensing of a methyl amine plant Details 8Annual rate contract for third party inspection services of goods purchased Details 8Tender for above ground GI installations including last mile connectivity Details 8Tender for supply of spares for 5-ton capacity cane unloader Details 8Tender for repair and servicing of two 400 KW, 1400 RPM NGEF motors including bearing replacement, rotor shaft metalizing (ND side), and testing Details 8Three-year rate contract for supply, installation & commissioning of BMS/CMS with process loops for heater treaters and BMS for IDBH Details 8Tender for repair works and spare parts supply for fire engine No. 4 Details 8Supply of chain and its spares on door delivery basis Details 8Procurement of spare shafts for RO high-pressure pumps Details 8Procurement of submersible pump for sewage recovery Details 8Tender for service assistance contract for CBR operations Details 8Tender for mechanical works for process modification schemes Details 8Supply of tap set, die, nut, and handle Details 8Supply and installation of storage drives for CCTV NVR servers Details 8Supply of Hilliard make filter spares Details 8Supply of O-ring kit Details 8Procurement of pipes Details 8Tender for overhauling and maintenance of high-pressure CFU-type heat exchangers in the DHDT unit Details 8Supply of Tushaco make lube oil pump spares Details 8Supply of sodium nitrite Details 8Supply of soft soap Details 8Annual rate contract for Ms BASLER make excitation system Details 8Rate contract for preventive maintenance and troubleshooting of ABB make PAC motor through its OEM Ms ABB Details 8Supply of finalizing contract for processing 1500 KL of Whitepol by lube complex Details 8Supply, installation, commissioning and CAMC of analyzer system Details 8Procurement of viscometer Details 8Procurement of bladder assembly of EPE make in DCU Details 8Tender for service contract of Flowserve Limitorque makes actuators Details 8Procurement of pilfer proof plastic seals Details 8Supply of Emerson spares Details 8Supply of induction motor fan cover Details 8Tender for hydro carbon detector services and works Details 8Providing of 1no high skilled and 1no semiskilled workmen for electrical maintenance Details 8ARC of consumables spares Details 8Supply of aviation micro filter elements Details 8Supply, installation, testing & commissioning of evacuation compressor Details 8Tender for retubing of boil off gas condenser (shell and tube type of heat exchangers) excluding supply of tubes Details 8Tender for M&I jobs for LPG mounded bullets shutdown Details 8Supply of tee pipe fittings Details 8Supply of internal coating of exchanger bundles Details 8Supply of potassium hydroxide Details 8Supply of nitrogen gas Details 8Hiring photography and videography services in the operational areas Details 8Hiring of services to carry out ultrasonic thickness measurement survey/NDT on different piping Details 8AMC for automatic fire detection and foam based extinguishing system for rim seal protection Details You can also click on Tenders for more For reference purposes the website carries here the following Newsclips (These are public domain newsclips and the website is not responsible for their content): 8Japan under pressure from U.S. to invest in Alaska LNG pipeline Details 8US player’s FSRU gets multiyear gig in North America Details 8New Fortress Energy charters FSRU for LNG terminal in the Dominican Republic Details 8Aramco eyes stake in Woodside's Louisiana LNG project Details 8Global LNG fleet’s annual CO2 emissions exceed 12 billion tonnes Details 8Offtake deal locked in ahead of US LNG terminal’s FID Details 8Mozambique inks deals for new refinery, pipeline; advances projects Details 8Adani commissions India’s first hydrogen truck for mining logistics Details 8EU riles nuclear industry with delay to 'low-carbon' hydrogen rules Details 8Strong signs for North American bioethanol Details 8Karnataka promotes biofuel policy with international collaborations for sustainable development Details 8OPEC expects slower 2025 oil supply growth from rivals after price drop Details 8Global oil demand growth forecast cut by 500,000 b/d for 2025: S&P Global Details 8GAIL to expand Dabhol terminal to 12.5 mtpa by 2031-32, gets five US LNG equity proposals Details 8Industrial boilers behind 7% of India's greenhouse gas emissions: Report Details 8The Greek billionaire secretly sold a gas carrier: such vessels carry Russian LNG Details 8Russia, Egypt in talks to build LNG terminals Details 8Petronet LNG seeks more land at Dahej Details 8GAIL plans 5-6 MTPA LNG expansion by 2030, stock gains 1.27% Details 8MSRTC to add 25,000 new buses in 5 years, majority to run on CNG and LNG Details 8India sets sail for shipbuilding growth with Rs.20,000 crore push Details 8NDRF conducts mock drill at LPG bottling plant Details 8EKA Mobility secures LOA for 750 electric buses to be deployed across Andhra Pradesh Details 8LPG prices per cylinder: Will 14.2 KG, 19 KG LPG prices rise or fall in June 2025 price Details 8Oil India announces hydrocarbon exploration breakthrough in Tripura with Debtamura 1 wellDetails 8Illegal LPG refilling unit busted at Daria Details 8L&T wins Indian Oil auction for 10 KTPA green hydrogen supply in Haryana Details 8Pakistani crew on Hong Kong-flagged ship not allowed to disembark Details 8Oil sector ensured jet fuel supplies, emergency readiness amid Pakistan-India tensions: OCAC Details 8Operation Sindoor: Crude oil rules India’s trade with Azerbaijan Details 8Indian Rupee ends slightly higher at 85.28/$ as crude oil prices fall Details 8GAIL (India) to invest Rs. 10,000 crore capex in FY26 Details You can also click on Newsclips formoreDetails
8From systems rationalization to synergy tracking, Deloitte has been roped in to streamline BPCL’s merged operations 8This is being done under a fast-tracked review. 8Deloitte’s brief includes evaluating cultural alignment, supply chain overlaps and stakeholder readiness. 8And a 15-day sprint will see Deloitte interview key teams, validate synergy assumptions and flag potential integration risks before final submission. 8Also find out who lost this race Click on Details for more
Details
A legacy classification under the Factories Act is complicating fuel retail expansion. FIPI wants “pumping” to be derecognized as a manufacturing activity altogether. 8In another vein, with land title delays, access issues, and premature terminations plaguing NHAI WSA projects, there is now a demand for lease date recalibration and protective clauses for fuel station investments.
Details
8Six firms vied for this refiner’s safety and environment studies, but only two cleared the rigorous technical bar. 8Insistence on a combined EIA-QRA-HAZOP package reflects tightening regulatory norms. 8Experts note the integration of environmental and safety assessments is becoming standard for major downstream projects. Click on Details for more
Details
This GST study lays bare the inefficiencies of dual tax regimes. 8The exclusion of five fuels is distorting the tax system and harming downstream margins.
Details
8This is a limited tender 8Find out which are the companies involved 8This could set the tone for upcoming projects in India’s growing petrochemical sector. Click on Details for more
Details
A recent report pegs current green hydrogen costs as high but scalable. 8The cost is seen falling below $2/kg with policy and tech gains by 2030. 8Find out on what basis is the projection made Details
8Vendors must deliver a 20 MW cooling solution with minimal drift and high mechanical stability in humid ambient conditions. 8Four bidders in the race Click on Details for more
Details
Inspection data shows offshore vessel types consistently underperforming on compliance. 8MODUs, OSVs, and SPSs show zero “clean” inspections in 2024. 8Data shows zero nil-deficiency scores and rising technical gaps. 82024 inspection logs show 50% detention rate for offshore supply vessels. 8It’s not just paperwork, critical safety systems are failing checks and this shows India’s offshore oilfield logistics may be skating on thin ice. 8Are we under-policing the most complex assets in our maritime fleet? Click on Details for more
Details