All content in this website is sourced legitimately

Archives


All the news items since the launch of our web site are preserved in the archive section. The archive entries are freely accessible to all the users.


Mar 2019

Soul searching is on within OIL over the sudden drop in production.
8"Miscreant activity" is what has been the official response so far
8But within the company, there is heated debate over the lapse.
8And it all seems to point towards one shocking conclusion
Click on Details for more Details
Well placed sources are claiming that only three bidders are likely to apply
8Who are they?
Click on Details for more. Details
8A global LNG glut is pushing spot LNG prices further down. Click on Reports for more
8Storage facilities are getting fuller, pointing to even lower prices
Click on Reports for more
IMO 2020 updates:
8If HSFO prices plunge subsequent to the IMO 2020 regulations, what happens to bitumen prices, which are pegged to HSFO prices?
8Those refineries investing heavily on Low Sulphur Fuel Oil may need to stop and do a rethink, it seems. Their investments may not pay off
Click on Reports for more
Details
Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 5000 crores
8Project Description: A hydropower project located in the neighboring country but promoted by Indian companies is getting delayed.
8Find out the RFQs coming up ahead
8Start Date: Q4:2019
8Completion Date: 2024
Click here for more details

Project Name: Thermal Power Station - Renovation, Modernization, and Up-gradation Project
8Project Cost: 250 crores
8Project Description: A R&M of boiler and turbine in a thermal power project has been put on hold.
8The plant is kept shut for 2 years from now.
8But no actions are taken by the state government to revive it.
8Start Date: 2020
8Completion Date: 2022
Click here for more details
8Complete O&M of ash handling plant is coming up
Find out more
Details
ONGC's  publication of the tender for floating of a jack-up rig tender has been put off temporarily.
8The reason is that they want to wait for a particular rig which is in service with ONGC to also qualify for bidding
Click on Details for more Details
How long is it going to take OIL to build back its crude production to normal levels?
8There is some confusion over the time it will take
Click on Details for more Details
What is the latest status on the bidding for three 300-foot F&GL design rigs?
8There is speculation on whether Jagson International will stand disqualified, given that it violated ONGC's Integrity Pack while submitting a tender for two rigs, leading to the cancellation of the contract.
Click on Details for more 
Details
The bidding date has been extended
8It is learned that as many as 6 bidders are interested
Click on Details for more Details
8Project Name: Greenfield LNG Terminal Project
8Project Cost: Rs 1800 crore
8Project Description: Land for establishing on-shore receiving facility has been allotted. Moreover, Front End Engineering (FEED) work is under completion. A further requirement for the PMC contractor and charter hiring of FSRU will come out.
8Project Event: RFQ for the PMC contractor is expected by June 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jun/2019
8Release Date: Jul/2019
8Start Date: Q3:2019
8Completion Date: Q4:2021
Click here for more details

8A sewage treatment plant is coming up
8Get to know more about the project
Click on Details for key contacts
Details
For reference purposes the website carries here the following tenders:
8
Rate contract for laying of flow-lines Details
8Hiring of Services for Facility Management Services (FMS) for DSA Geleki for the period of three years Details
8Procurement of Nonyl Phenol Ethoxylate and Linear Alkyl Benzene Sulphonic Acid Details
8Rate contract for Fabrication and repair works Details
8Corrigendum: Basic engineering and cost estimate of cross-linked acrylic monomer polymerization plant Details
8EOI for supplying Renewable Energy Solar or Wind or other Renewable Sources Details
8PLC, Turnkey instrumentation works for LPG pipeline project Details
8Providing PSARA Security in Rajasthan Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8India’s natural gas production at 3-year high Details
8India’s oil imports from sanctions-hit Iran fell 50 per cent in Feb Details
8GAIL sells US LNG cargo to Europe amid high stocks in India Details
8Sempra wants to become one of North America's biggest LNG exporters Details
8Australia's east faces gas shortage from 2024, market operator warns Details
8Crude oil futures drop 0.6% on global cues Details

8GasLog signs 12-year LNG charter deal with JERA Details
8Germany takes steps to spur more investment in LNG terminals Details
8Britain's greenhouse gas emissions fell 3 per cent year-on-year in 2018 Details
8Vitol's head of LNG expects supply shutdowns due to market glut Details
8Denmark asks Nord Stream 2 to assess third route option for gas pipeline Details
8Commissioning for Bangladesh's second LNG import terminal delayed to April Details

8Exxon hires ex-BP crude oil trader in Singapore Details
8Japan extends state-backed insurance for Iran oil imports: Govt official Details

8Gabon oil workers' strike halts Vaalco terminal output: Union Details
8Domestic crude output shrinks 4% in 11 months Details
8Oil pares losses, shrugs off Trump calls for OPEC to boost output Details
8Oil prices rise amid OPEC's ongoing supply cuts, US sanctions Details

8U.S. orders foreign firms to further cut down on oil trades with Venezuela Details
You can also click on Newsclips for more  
Details
Ammonia-Urea Brownfield Project
8Cost - Rs 6000 crore
8Project Event: Chemin, EDAC Engineering Ltd, Galacon Infrastructure and Projects Private Limited, Konstelec Engineers Pvt. Ltd. and Satnam Global are in the race to Supply & Erection of Electrical & Instrumentation Work for Offsite & Utilities at Sindri & Barauni Urea-Ammonia units.
Click here for more details
Phosphoric Acid Greenfield Project

8Cost - Rs 10 crore
8Project Event: Public hearing is completed and proposal for the environmental clearance is likely to be elicited in April 2019. The hiring process is ongoing for an EPC contractor.
Click here for more details
Details
8Project Name: Subsea Pipeline Repair and Platform Jacket Strengthening
8Project Cost: Rs 100 crore
8Project Description: Know the companies who have shown interest in the tender.  The bidding is expected to close by 8th April 2019. Further RFQs for the project are expected shortly.
8Expenditure Approval: Q1/2019.
8RFQ Date: Feb/2019
8Release Date: 8/Apr/2019
8Start Date: Q3/2019
8Completion Date: May/2020
Click here for more details
Details
The Shapoorji Pallonji group knew that to thrive in the oil & gas business in India you have to depend on partnerships. And partnerships is what the group knows how to build and nurture.
8The company currently owns and operates two FPSOs (floating production storage and offloading) units through its 51:49 JVs with Malaysia-based Bumi Armada Berhad (BAB).
8Both the FPSOs are under time-charter contracts with Oil and Natural Gas Corporation Limited at designated oil fields (C7 and D1).
8A new JV between Bhumi Armada and the group, dubbed SP Bumi Armada Godavari Pvt Ltd, is all set to pick up a contract for an FPSO for ONGC's KG-DWN-98/2 project
Click on Reports for more Details
NPK Fertilizer Greenfield Project
8Cost - Rs 1517 crore
8Project Event: RFQ for EPC contractor was floated in February 2017 and price bid was opened in Jan 2018, due to high price bid prices, finalization has been delayed. Still, the discussion are ongoing between bidders and the owners, and a final decision has been put off till April 2019 in place of March 2019
Click here for more details
Ammonium Sulphate Expansion Project 

8Cost - Rs 9 crore
8Project Event: The proposal for environmental clearance has been accepted in March 2019. RFQ for the EPC contractor is likely to be released at the end of April 2019 in place of March 2019.
Click here for more details
Details
For a long time now, domestic gas producers have been demanding a level playing field for gas prices.
8It has now been granted, with the domestic price pegged to the LNG price off Dahej.
8But producers waiting for first gas out of the KG Basin discoveries will also have to take in their stride the sharp fall in LNG prices too, as is the case now, when spot LNG prices could hover at the below $5/mmbtu mark
8These kind of prices are below the breakeven points of ONGC if not of the RIl-BP combine
Click on Details for more Details
The sharp fall in spot prices is forcing some Indian companies to relook at their LNG sourcing policies.
8Spot cargoes for onward deliveries are at less than half of what it was in December, 2018, and it will not be surprising if prices go below the $5/mmbtu mark
8Three main players GSPC, Torrent and Reliance have accordingly reworked their plans Details
Find out more on how ONGC shot itself in the foot while laying the terms and conditions for the selection of an FPSO for the KG-DWN-98/2 block.
8In the process of doing so, it eliminated all the competition for the FPSO, leaving just the Bhumi Armada-Shapoorji Pallonji JV in the race.
8The website traces the decision-making process that led to such an eventuality
Click on Details for more Details
Three companies were in the race
8One bagged the contract
Click on Details for more Details
Now that IOC's Ennore terminal is working, who are its major customers?
8How much of the capacity is likely to be utilized,  for now?
Click on Details for more Details
8Project Name: ETP Modernization
8Project Cost: Rs 30 crore
8Project Description: Oil and Natural Gas Corporation Limited's RFQs for the hiring of a Project Management Consultant for the modernization of an Effluent Treatment Plant Unit. Meanwhile, it is processing the price bids for the LSTK contractor for plant.
8Project Event: Tender for hiring PMC services will close by 15th April.
8Expenditure Approval: Q1/2018.
8RFQ Date: 25/Mar/2019
8Release Date: 15/Apr/2019
8Start Date: Q3/2019
8Completion Date: Q3/2020
Click here for more details
Details
8Project Name: Greenfield Propylene Pipeline
8Project Cost: Rs 95 crore
8Project Description: Owner is planning to lay a Propylene pipeline. The tentative route length is 46 kilometers. The capacity of the proposed Propylene pipeline will be 0.6 MMTPA. Fluor Daniel India Private Limited was appointed as PFR consultant.
8Project Event: RFQ for EPC contractor is expected by June 2019.
8Expenditure Approval: Q4:2017
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: Q3:2019
8Completion Date: Q3:2021
Click here for more details

8 Mechanical maintenance work is coming up upon shutdown of GPU
Get work details and key contacts here
Click on Details for more
Details
8Project Name: POL Depot Greenfield Project
8Project Cost: Rs 570 crore
8Project Description: RFQ for the FEED work has already come out and the bidding process is on. Environment clearance for this project is expected soon. Further RFQs are expected soon.
8Project Event: RFQ for the EPC contractor is expected by June 2019.
8Expenditure Approval: Q3:2018
8RFQ Date: Jun/2019
8Release Date: Jul/2019
8Start Date: Q3:2019
8Completion Date: Q3:2022
Click here for more details
Details
For reference purposes the website carries here the following tenders:
8
Procurement of 250 MT Pentane for LLDPE HDPE unit Details
8Diaphragm operated pneumatic control valves Details
8Supply of electric motor driven online compressors Details
8Selection of contractor for paving using paver block Details
8Supply of Pre-fabricated Canopies Details
8Laying of Pipeline and Associated Works Details
8Procurement of Caustic Soda Lye in tankers Details
8Supply of foot slip for 2.7/8” OD EU Tubing Details
8Supply of Casing Scrappers Details
8Procurement of Pipe Fittings at refinery Details
8Design, installation commissioning of Effluent Treatment Plant Details
8Supply of Carbon Steel Welding Neck and Socket Weld Flanges Details
8Service Assistance to Engineering and Inspection Department Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8
India’s target of raising natural gas share in energy mix to 15 per cent too ambitious? Details
8Vedanta reports oil discovery in Krishna-Godavari basin Details

8IOC, BPCL, HPCL, GAIL exceed capex targets for current financial year Details
8L&T dispatches India's heaviest hydrocracker reactor to HPCL ahead of schedule Details
8Oil companies have more expertise than GAIL in operating city gas business: Fitch Details
8Algeria's oil, gas production unaffected by unrest: IEA Details
8Brazil's Petrobras fines Bolivia for failing to meet LNG deliveries Details
8Oil prices dip after U.S. inventory gain Details

8Oil extends losses into second session as U.S. stocks rise Details
8BP's 'for sale' sign covered by snow in Wyoming oil and gas field Details
8Germany unveils plan to spur liquefied natural gas imports Details
8Iraq resumes southern oil exports after stoppage: Oil officials Details
8Kuwait explores new eco sectors with India to reduce dependence on oil for development schemes Details
8Brazil likely to sign energy cooperation agreement with Israel: Minister Details

You can also click on Newsclips for more  
Details
Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 500 crores
8Project Description: NEEPCO has been handed over this greenfield hydel power project.
8Check out the latest status on the project
8RFQ for a PFR consultant for site survey activities and grant of TOR is expected soon.
8Start Date: 2023
8Completion Date: 2027
Click here for more details

Project Name: Thermal Power Expansion Project
8Project Cost: 10000 crores
8Project Description: This is an under-construction super-critical thermal power project which is expected to be commissioned in the Q3 2019.
8Work at the coal handling plant and ash handling plant is under progress.
8GE Power India has started mobilization of FGD equipment at the site.
8Check out the list of contractors involved in the project and also know more about  upcoming RFQs
8Start Date: Oct/2015
8Completion Date: Q3:2019
Click here for more details
Details
8Project Name: Kandla-Gorakhpur Greenfield LPG pipeline project
8Project Cost: Rs 6000 crore
8Project Description: The PMC contractor is Engineers India Limited is planning to lay a 2,000-km, 6 MMTPA pipeline to carry liquefied petroleum gas (LPG) from its Kandla import terminal on the west coast to Gorakhpur. The project work is divided into three stretches, 650 km (approx) each. Deshpande - Patil Consultants Pvt. Ltd., N.K. Buildcon Pvt. Ltd. and Theodesh Consultants Pvt. Ltd. is appointed for the route survey and geotechnical investigation work for the pipeline. RFQ for compressors, drives and the mainline pipe has already come out and the bidding process is on. 
8Project Event: RFQ for the valves and short lead items is expected by May 2018.
8Expenditure Approval: Q3:2016
8RFQ Date: May/2019
8Release Date: Jun/2019
8Start Date: Q3:2018
8Completion Date: Q3:2021
Click here for more details

8Project Name: Agartala Greenfield POL Terminal Project
8Project Cost: Rs 432 crore
8Project Description:  Engineers India Limited is appointed as DFR consultant. Agartha Project Consultancy Services Pvt. Ltd. is carrying out detailed geotechnical soil investigation survey of this project. RFQ for the long lead items has already come out and the bidding process is on. 
8Project Event: RFQ for the civil and structural work is expected by June 2019.
8Expenditure Approval: Q3:2017
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: Q2:2019
8Completion Date: Q2:2021
Click here for more details

8A big two-year pipeline maintenance contract is coming up
Click on Details for key contact Details
Latest projections show that a "second revolution is in the offing in US shale oil.
8This will dramatically alter the dynamics of world trade, putting the Middle East and OPEC under increased pressure
Click on Reports for more Details
Is the proposed Mumbai-Nagpur-Raipur-Angul gas pipeline unviable?
8Is viability gap funding the only way out?
8Should the pipeline be split up into two independent segments for better viability?
Click on Reports for more. Details
GAIL's trunk Dahej-Uran gas pipeline seems to be running out of spare capacity.
8All the common carrier capacity has been booked, it seems.
8Soon, capacity constraints are expected to crop up.
Click on Reports for more Details
Find out more about how, once the country is connected to gas sources in the East Coast, the cost of gas is going to be far more expensive for customers than if the gas was supplied from the West Coast
8The pipeline tariffs are just too high from the East Coast, it seems.
Click on Reports for more Details
Spot LNG prices have hit a new low on tapering demand and higher supplies.
8The latest spot prices are well below the $5/mmbtu mark.
8These prices are unlikely to prevail at these levels for too long, it is projected.
Click on Reports for more Details
Bringing fuel products under the ambit of GST has been long deliberated by the government.
8But if petrol and diesel were to be brought under the GST regime, a different tax system would have to be structured for petro products.
8Find out what kind of GST rates will petrol and diesel attract?
Click on Reports for more Details
Is Sapura likely to get a windfall from out of the arbitration proceedings over differences with ONGC over the construction of the 26-well platform
8It is a huge sum of money
8A ruling is expected in June.
8And Sapura seems confident of winning the battle
Click on Reports for more Details
L&T is not giving up on a Rs 6000 crore ammonia-urea brownfield project despite the fact that China's Wuhuan Engineering has emerged as the L-1 bidder. But the Chinese company has also emerged as a dogged fighter
Ammonia-Urea Brownfield Project
8Cost - Rs 6000 crore
8Project Event: The technical evaluation of bidder for EPC contractor is completed, the price bid has been opened on 25 March 2019, Wuhuan Engineering is an L1 bidder, but consumption ratio of L&T is good, the race between L&T & Wuhuan is ongoing, and is likely to be finalized in April 2019, while the country is under a caretaker government.
Click here for more details
DAP/NPK Greenfield Project 
8Cost - Rs 300 crore
8Project Event: The PDIL has been selected for the preparation of Techno-Economic Feasibility Report. Based on the feasibility report of PDIL, future action shall be planned. The RFQ for the EPC contractor is likely to be released in May 2019
Click here for more details
Details
Project Name: Thermal Power Station: FGD Addition Project
8Project Cost: 500 crores
8Project Description: Fichtner Consulting Engineers is carrying out cost estimate and study of equipment for development of WFGD system in a thermal power plant.
8Technical parameters are under review.
8RFQs for the supply and installation works is expected soon.
8Start Date: 2021
8Completion Date: 2023
Click here for more details
NTPC is planning the development of a 500 MW wind energy project in India.
8Find out more Details
A new big new area of demand for gas turbine-generators is coming in from a fresh bunch of solid waste to power projects now.
Here is one such project.
Project Name: 
Solid Waste Power Project
8Project Cost: 2000 crores
8Project Description: A 250 MW waste to energy power project is planned.
8Site surveys are yet to be taken.
8While a USA agency will cater the need for the latest plasma technology required in the project.
8Find out the RFQs expected
8Start Date: 2020
8Completion Date: 2022
Click here for more details

(Our project monitoring software tabulates all power projects from difference feestocks. Get in touch with us for more) Details
Now that the proposal for an MOPU for the Ratna R Series field has been dropped, ONGC is hurrying up the scope of work of the additional surface facilities, including a Minimum Facilities Platform in the field
8Find out what kind of scope of work, there is likely to be
8Also, will ONGC be better off giving the project away on nomination basis to save time on tendering and processing?
Click on Details for more
Details
The Cluster-7 Redevelopment job has been bagged by L&T
8But the tight completion deadlines are likely to challenge the engineering major in more ways than one
8Failure to adhere to the deadline win mean that the job will not make money for the contractor.
8 Find out why it is going to be touch and go for L&T.
Click on Details for more Details
What are the other important offshore equipment tenders expected from ONGC in the coming months?
8Jobs worth around Rs 2200 crore are in the offing, for supply of special equipment and services
8The indents have been generated and they are currently under various starges of approval
Click on Details for more
Details
For reference purposes the website carries here the following tenders:
8
Hiring of Wellsite Services on Call-out Basis for Onshore Blocks in Gujarat Details
8Procurement of Hydrogen Peroxide in tankers Details
8Tankage and Gantry Jobs at Radhagaon Depot Details
8ARC for Consultancy Services for Pre-Project activities Details
8Service contract for composite jobs inside reactor installed in LLDPE-II Details
8ARC for ROU maintenance works and modification of pipeline & installation Details
8Procurement of Sulphuric Acid Details
8Supply of DMDS in drums for refinery Details
8Site grading works for 2G Ethanol Bio-Refinery Project 
Details
You can also click on Tenders for more

For reference purposes the website carries here the following Newsclips:
8
India records lowest crude oil production in nine years Details
8Iran's crude oil pipelines undamaged by heavy rain and flooding Details

8Nayara Energy operationalizes rail-fed oil depot in Maharashtra Details
8BRIEF: Moody's says Indian oil companies to continue with high dividend payments Details
8Regulator drops plan to force LNG terminals to reserve share for common use Details
8High dividend and share buybacks to stress India’s oil companies: Moody’s Details
8All state-run oil companies exceed capex target Details
8Saudi Aramco building global gas business to cut carbon footprint Details
8Siemens signs deal with China's SPIC in effort to revive gas turbine Details

8Shell Deer Park refinery production cut due to crude supply Details
8China's ShFE launches crude oil futures index; plans more products Details
8Developer confident Russia-Germany pipeline to get permit Details
8BRIEF: Aramco CEO says building international gas business Details
8OPINION: Hedge funds increase appetite for oil Details
8UK's National Grid forecasts Summer 2019 gas demand at 36.1 bcm Details
8Refiners invest $1 billion to meet shift to cleaner marine fuel - BP Details
8BP commits $100 million to fund new emissions reduction projects Details
8Oil prices dip after U.S. inventory gain Details
8Brazil's Petrobras fines Bolivia for failing to meet LNG deliveries Details
You can also click on Newsclips for more   Details
It is clearly unacceptable that Oil India Ltd's crude production was 23% off target in January, and another 20% in February. Output is running significantly lower during these months in the previous year.
8There was hope that January was an exceptional month but the fact that output continues to remain low in February is cause for serious introspection.
8It is a clear failure on the part of OIL management team, lead by Utpal Bora, that miscreants can just walk in and shut down oil fields in Assam, causing grievous damage to them, particularly when a muscular BJP government is in power in Assam.
8Something is terribly wrong somewhere. Is it just "miscreant activity" or is there more to it than meets the eye?
Click on Reports for more
Details
Project Name: Gas Based Combined Cycle Power Project
8Project Cost: 4500 crores
8Project Description: The long-awaited combined cycle gas power expansion project has faced a time overrun of 8 years.
8But, as of now, it is back on track.
8The EIA report has been prepared.
8Clearance from the MoEF and State approval is pending.
8RFQs for an EPC contractor is expected
8Start Date: Q3:2020
8Completion Date: Q4:2023
Click here for more details Access only through our sister website energylineindia.com
Details
Baker Hughes is a big multinational and its oil field equipment segment is showing a rapid rise in business globally.
8The company has a global focus, but it was from India that it won one of its largest recent orders for as many as 34 sub sea trees
8The India team has done well, and there is more business coming up
Click on Reports for more  
Details
Madras Fertilizers Ltd is expected to start running on gas sometime in June
8Find out more
 Click on Report to know the status of feedstock change, energy saving project and when and from where gas will be delivered.
Details
GAIL has claimed that IMC's Kandala to Samakhaili feeder LPG pipeline will run into capacity constraints when it comes to transportation through the Jamnagar-Loni LPG pipeline (JLPL)
8But IMC has countered this view, saying that it has tied up with a PSU with already booked capacity in the JLPL
8IMC is also looking at a JV for a cryogenic terminal at Kandla
Click on Reports for more  
Details
Tag Offshore may have been banned by ONGC last year for failure to mobilize one of its vessels on time against an LOA granted by the public sector E&P major.
8But that may not deter others from hiring Tag's vessels for tendering against ONGC's forthcoming requirements
Click on Details for more.
Details
Ammonia-Urea Brownfield Project
8Cost - Rs 4933 crore
8Project Event: The project is under consideration of Cabinet and is still pending, and it likely to be elicited after the general elections in May 2019, and RFQ for the EPC contractor is likely to be released after the cabinet approval.
Click here for more details
NPK-SSP & Sulphuric Acid Expansion Project
8Cost - Rs 15 crore
8Project Event: RFQ for a contractor is likely to be released after environmental clearance. The public hearing has been completed but environmental clearance is due and it is likely to be elicited in April 2019. The RFQ for the EPC contractor is likely to be released in April 2019.
Click here for more details
Details
Facing imminent blacklisting, Schlumberger has claimed before ONGC that it is being prosecuted for no reason whatsoever.
8"The problem was with ONGC and not with us," a Schlumberger source told this website.
8But despite Schlumberger's ardent plea, ONGC has already started the blacklisting process.
Click on Details for more
Details
Even as Schlumberger fights off the blacklisting process, the already blacklisted party, Halliburton, is also trying to scupper a blacklisting of one of its key services by ONGC.
8Halliburton was blacklisted for submitting patently false information, according to ONGC.
8But Halliburton's country manager Scott Cooper is not willing to take the blacklisting lying down.
Click on Details for more  
Details
ONGC has put together an ambitious Rs 1400 crore onshore exploration, development, and production of oil & gas from 40 wells in South India
8It is a six-year plan to look for shale gas, among other reserves.
8RFQ for a seismic survey programme is expected in Q3, 2019 and more RFQs are lined up for later
8Expenditure Approval: Q4/2018.
8RFQ Date: Q3/2019
8Release Date: Q3/2019.
8Start Date: Q2/2020
8Completion Date: Q2/2026
Click here for more details, including key contacts
Details
8Project Name: Onshore Oilfield Development
8Project Cost: Rs 150 crore
8Project Description: A small player is planning to float RFQs for the hiring of an EPC contractor for the QPF installation and pipeline network in Gujarat soon expected soon.The declaration of commerciality for the block has been recommended by DGH and but the field development plan has not been approved until now. The integrated drilling services contract for the project is also expected to be floated soon. 
8Project Event: RFQ for an EPC contractor for QPF and pipeline is expected by Q3 2019
RFQ for the hiring of rig services is expected by Q3 2019
8Expenditure Approval: Q4/2017.
8RFQ Date: Q3/2019
8Release Date: Q3/2019
8Start Date: Oct/2019
8Completion Date: Dec/2021