All content in this website is sourced legitimately

Page No: 1
Update on ONGC Gamij GGS
Jun 14: 8Project Name: GGS-IV Gamij
8Project Cost: Rs 97 crore.
8Project Description: Oil and Natural Gas Corporation Limited's construction project for the fourth Group Gathering Station (GGS-IV) at Gamij in Kheda District, Gujarat is on schedule and is expected to be commissioned by Q4 2019. Get details of the various contractors working on the job
8Expenditure Approval: Q2/2015
8Start Date: Q2/2018
8Completion Date: Q4/2019
Click here for more details

8Project Name: Oil Storage Tank
8Project Cost: Rs 44.64 crore
8Project Description: Oil and Natural Gas Corporation Limited has awarded the contract for the construction of crude oil storage tank near Gamij at Ahmedabad Asset in Gujarat to K L Projects Private Limited. Currently, the project is under process; mechanical and electrical works are expected to be complete by Q3 end 2019. The O&M contract will be executed by the company itself. 
8Expenditure Approval: Q1:2018
8Start Date: Q4/2018
8Completion Date: Q4/2019
Click here for more details


**********************************

Back  |  Top