All content in this website is sourced legitimately

Page No: 1
Power Sector: Latest project updates
Mar 07: Project Name: Thermal Power Expansion Project
8Project Cost: 6000 crores
8Project Description: A brownfield thermal power project is running on schedule. Boiler erection works at the main plant are in progress. Also, civil works are under progress at the balance of the plant area.
8The work at the site is being carried out by
Toshiba JSW Systems Private Limited
Doosan Power System India Limited
Bygging India Ltd
Desein Indure Pvt Ltd
ABB
Flsmidth
Power Mech Projects Ltd
Chemin C&I Pvt Ltd
GE Power India
REC Transmission Projects Company Limited
8Expenditure Approval: Sep/2015
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: Q2:2016
8Completion Date: Q1:2020
Click here for more details for project details and key contacts

8Project Name: Thermal Power Station - Installation of FGD
8Project Cost: 500 crores
8Project Description: Owner along with consultant is evaluating cost estimates for installation of an FGD system in a thermal power project.
8Find out the RFQs expected
8Expenditure Approval: Q3:2018
8RFQ Date: May/2019
8Release Date: May/2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details for project details and key contacts


**********************************

Back  |  Top