Rs 1500 crore drilling plan: RFQ for EPC contractor in Q2
Feb 11: 8Project Name: Drilling Site Development
8Project Cost: Rs 1500 crore
8Project Description: A 64 well development drilling project has finally been granted a TOR amendment after the owner had carried out revised public hearings. A 2000 HP pre-hired drilling rig and a company owned workover rig are planned to be used for the project.
8Project Event: RFQ for the hiring an EPC contractor is expected by Q2 2019.
8Expenditure Approval: Q2/2017.
8RFQ Date: Q2/2019
8Release Date: Q2/2019.
8Start Date: Q3/2019
8Completion Date: Dec/2021