Jan 11: Project Name: Greenfield Hydroelectric Project 8Project Cost: 1500 crores 8Project Description: The RFQs for E&M works are being delayed due to due to queries raised for changes in the technical parameters. The civil and H&M works bid is still not awarded. Further bids are expected soon. 8Project Event: RFQ for engineering, procurement, construction and commissioning of electro-mechanical works is expected by March 2019. Click here for more details Project Name: Thermal Power Plant - FGD Addition 8Project Cost: 500 crores 8Project Description: The RFQs for supply, installation, erection, and commissioning of four FGDs in a 920 MW (2x210 + 2x250 MW) thermal power plan is getting delayed due to delay in preparation of detailed project report 8Project Event: RFQ for supply, installation, erection, and commissioning of FGDs is expected by February 2019 now. Click here for more details