Jan 09: Ammonia-V Revamp Project: RFQ for the LSTK contractor is likely to be released in February 2019 8Cost - Rs 102 Crore 8Project Event: The detail engineering is ongoing and RFQ for the LSTK contractor is likely to be released February 2019. The project is expected to be commissioned by April 2020. Click here for more Ammonia-Urea Brownfield Project: Erection is ongoing 8Cost - Rs 6000 Crore 8Project Event: The erection of all the equipment is ongoing at the site, the purchase of a long lead item is ongoing, delivery at the site will take a minimum two to three months. The project is likely to be commissioned in December 2020. Click here for more details. SSP Expansion Project: RFQ for the EPC contractor is likely to be released in February 2019 8Cost - Rs 15 Crore 8Project Event: The public hearing is ongoing for the environmental clearance and RFQ for the EPC contractor is likely to be released in February 2019 in place of January 2018. Click here for more details