Agitation delays LPG pipeline project
Sep 19: An LNG terminal along with a pipeline from the jetty has met with serious objections from the local community.
But project authorities along with the EPC contractor and the state government has worked with an IIT to come up with some innovative solutions that can mitigate public anger
The National Green Tribunal is supportive of the effort made
8Project Event: RFQ for the LPG pump for terminal and Jetty is expected by November 2018. RFQ for the Mechanical and fire package work is expected by December 2018.
8Expenditure Approval: Jul/2014
8RFQ Date: Nov/2018
8Release Date: Dec/2018
8Start Date: Oct/2015
8Completion Date: Q2:2019