Refinery captive power plant: Transportation contact coming up
Sep 18: 8Project Cost: Rs 1034 crore 8Project Description: TheLSTK contractor has taken out bids for equipment for the 75 MW captive power plant 8Project Event: RFQ for material transportation and handling to the site are expected by November 2018. 8Expenditure Approval: Q4:2016 8RFQ Date: Nov/2018 8Release Date: Dec/2018 8Start Date: Q4:2018 8Completion Date: Q4:2020 Click here for more details