A Brownfield Super-Critical Thermal Power Project: RFQs for the EIA consultant in Oct, 2018
Sep 17: Project Name: Brownfield Supercritical Thermal Power Project
8Project Cost: 8264 crores
8Project Description: Owner has been accorded terms of reference for a 1320 super-critical thermal power expansion project at its existing ongoing facility of 1600 MW thermal power complex. The unit-1 has been commissioned. Moreover, another unit is in advanced stages of completion and is expected to get commissioned by November 2018. Currently, the owner is undertaking DPR activities for the expansion project by using in-house resources. Further bids are expected soon.
8Project Event: RFQ for the QCI-NABET consultant for conducting EIA studies is expected by October 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Oct/2018
8Release Date: Oct/2018
8Start Date: 2020
8Completion Date: 2024