Greenfield Early Production System: More RFQs coming up
Sep 10: 8Project Name:  Greenfield Early Production System
8Project Cost: Rs 290 crore
8Project Description: Oil and Natural Gas Corporation Limited is soon expected to release a set of RFQs for construction and civil works for the setting up of an Early Production System. The project will be executed package wise instead of a single EPC contractor basis for EPS and the Pipeline segments. However, the final project approval is still pending from the head office and is expected soon. 
8Project Event: RFQs for hiring services for civil and construction works is expected by November 2018
RFQs for hiring services for mechanical equipment installation and commissioning works is expected by December 2018
8Expenditure Approval: Q2/2016
8RFQ Date: Nov/2018
8Release Date: Dec/2018
8Start Date: Q4/2018
8Completion Date: Q4/2019