Greenfield Early Production System: More RFQs coming up
Sep 10: 8Project Name: Greenfield Early Production System 8Project Cost: Rs 290 crore 8Project Description: Oil and Natural Gas Corporation Limited is soon expected to release a set of RFQs for construction and civil works for the setting up of an Early Production System. The project will be executed package wise instead of a single EPC contractor basis for EPS and the Pipeline segments. However, the final project approval is still pending from the head office and is expected soon. 8Project Event: RFQs for hiring services for civil and construction works is expected by November 2018 RFQs for hiring services for mechanical equipment installation and commissioning works is expected by December 2018 8Expenditure Approval: Q2/2016 8RFQ Date: Nov/2018 8Release Date: Dec/2018 8Start Date: Q4/2018 8Completion Date: Q4/2019 Click here for more details