Rs 400 crore Pipeline Expansion Project: RFQs coming up
Sep 10: 8Project Name: Pipeline Expansion Project
8Project Cost: Rs 400 crore
8Project Event: RFQ for the composite Works (erection and installation) for integrated pumping station at Barwala is expected by October 2018.
RFQ for the composite work (erection and installation) for pumping station is expected by November 2018.
8Expenditure Approval: Q2:2016
8RFQ Date: Oct/2018
8Release Date: Nov/2018
8Start Date: Q1:2017
8Completion Date: Apr/2019