Software updates: Fertilizer projects
Sep 10: Phosphoric Acid & Sulphuric Acid Greenfield Project        
8Cost - Rs 18000 Crore
8Project Event: RFQ for a process licensor was released in February 2018, finalization is due in October in place of August 2018. due to delay in the evaluation. Tender for EPC contractor is likely to be released in November 2018.
Click here for more information  
NOx Emission Reduction Project    
8Cost - Rs 8 Crore
8Project Description: National Fertilizer Limited is planning to implement NOx Emission Reduction in Nitric Acid Plant at Nangal Fertilizer Complex in Punjab. The Project Consultant is PDIL
8Project Event: The NIT for LSTK contractor for the NOx Emission Reduction has been released and bid due date is 25 September 2018,  and it is likely to be finalized in November 2018.
Click here for more information
 

**********************************