EoI of an FGD in a thermal power station: RFQ expected in Q1, 2019
Sep 10: Project Name: Thermal Power Project - FGD Addition 8Project Cost: 210 crores 8Project Description: Owner is planning the installation of a flue gas desulphurization (FGD) unit in a 300 MW thermal power station. Currently, the owner is conducting a survey and investigation for the FGD by using in-house resources. The ESP has to be upgraded for revised environmental norms. An EoI for the FGD main package is expected soon. 8Project Event: RFQ for an EoI of an FGD main package is expected by the Q1 2019. 8Expenditure Approval: Q4:2018 8RFQ Date: Q1:2019 8Release Date: Q1:2019 8Start Date: 2020 8Completion Date: 2022 Click here for more information The above link will open only if you have access to our sister site, www.energylineindia.com