Green field petrochemical complex: Delayed for now
Sep 05: 8Project Cost: Rs 30000 crore
8Project Description: A detailed feasibility report is being prepared. The requirement for the technology licensor is yet to be finalized. The central government is however unwilling to put a Rs 5000 crore concession.
8Project Event: RFQ for the ODC equipment is expected by November instead of July 2018.
 RFQ for the Technology licensor is expected by December instead of September 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Nov/2018
8Release Date: Dec/2018
8Start Date: Q1:2019
8Completion Date: Q4:2022