Private Offshore Field Development: RFQ for sub contractor for subsea pipeline and subsea beds installation in November 2018
Aug 31: 8Project Name: Offshore Field Development 8Project Description: The private operator's RFQ for hiring a jackup rig for development drilling of 7 wells and installation of subsea pipelines is out. The IPM consultant hiring for the block is in the process of finalization and an LOA is to be issued soon. However the bidding for the EPCIC contractor is still going on. 8Project Event: RFQ for hiring the sub contractor for subsea pipeline and subsea beds installation expected by November 2018. 8Expenditure Approval: Q2/2016 8RFQ Date: Nov/2018 8Release Date: Q1/2019 8Start Date: Feb/2020 8Completion Date: Dec/2022 Click here for more details for key contacts and other details