Power Sector : Projects in Pipeline
Aug 30: Project Name: Thermal Power Expansion Project
8Project Cost: 7845 crores
8Project Description: The boiler contractor is getting postponed in coming out RFQs for the boiler auxiliaries in the owner's 800 MW brownfield ultra super-critical thermal power plant due to delay in the project management activities. The EPC contractor is undertaking turbo-generator structure erection works. Further bids are expected soon.
8Project Event: RFQ for the civil and architectural works of the coal handling plant is expected by the Q4 2018.
RFQ for the supply of the boiler auxiliaries is expected by the Q4 2018.
8Expenditure Approval: Sep/2015
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: Q2:2016
8Completion Date: Q1:2021
Click here for more information

8Project Name: Thermal Power Station Project
8Project Cost: 32 crores
8Project Description: Promoter plans for procurement of gearboxes for cooling tower fans approval are pending with the site office in the 3000 MW thermal power complex. Moreover, the owner is also planning to replace the old high-pressure preheater with a new one. Further RFQs are expected soon.
8Project Event: RFQ for the supply of gearboxes for cooling tower fans is expected by the Q4 2018.
RFQ for a new high-pressure preheater is expected by the Q4 2018, instead of Q3 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: Q1:2019
8Completion Date: Q3:2019
Click here for more information


**********************************