Rasayani Greenfield LPG Bottling Plant: Contracting mode not decided yet
Aug 22: 8Project Name: Rasayani Greenfield LPG Bottling Plant Project 8Project Cost: Rs 300 crore 8Project Description: Bharat Petroleum Corporation Limited is planning to install a new LPG bottling plant by installing 3X1450 MT mounded storage bullets for the storage system with a bottling capacity of 270 TMTPA. It has not been decided yet whether the project will be implemented through the EPC or EPCM route. 8Project Event: RFQ for a contractor expected by the first week of November 2018. 8Expenditure Approval: Q4:2017 8RFQ Date: Nov/2018 8Release Date: Dec/2018 8Start Date: Q1:2019 8Completion Date: Q1:2021 Click here for more details 8Business opportunity pipeline suppliers- Find out where A refinery is planning to float a bid for the manufacture, inspection, testing and supply of Seamless, ERW (Electric Resistance Welded) pipes and EFSW (Electric Fusion Welding) pipes. Click on Details for more