Mellbro Greenfield Captive Power Plant: RFQ for EPC contractor coming up
Aug 14: Project Description: Mellbro Sugars Pvt Ltd is planning to add a 30 MW co-generation power plant in its greenfield white sugar mill at village Shirur in Bagalkot district of Karnataka. The project is awaiting environmental clearance. The major requirement will be a boiler (125 TPH), steam turbine, turbine generator, condenser, cooling water system, pumps, valves, control unit, cyclone dust collector (and wet scrubber), stack, ventilation system, among others.
Project Event: The project is awaiting capital approval following which the owner will release the RFQ for an EPC contractor and the process will take a minimum 3 to 4 months.
8Expenditure Approval: Sept/ 2018
8RFQ Date: Oct /2018.
8Release Date: Oct/2019
8Start Date: March/2019
8Completion Date: Dec/2020