Aug 13: 8Project Name: Khordha Greenfield LPG Bottling Plant Project
8Project Cost: Rs 161 crore
8Project Description: Indian Oil Corporation Limited along with the EPCM contractor Shree Malani Foams Private Limited is planning to install an LPG bottling plant by installing 3X600MT mounded storage bullets for storage of LPG with a bottling capacity of 60 TMTPA. RFQ for the long lead items and mounded storage vessel work is already out. Currently, electrical and instrumentation work is going on. Investment of Rs 35 crores has been already done.
8Project Event: RFQ for the mechanical piping and firefighting work is expected by September 2018.
RFQ for the Carousel site and erection work is expected by October 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Q3:2017
8Completion Date: Q4:2019