Aug 13: 8Project Name:  Brownfield Thermal Power Project
8Project Cost: 9250 crores
8Project Description: Owner along with an EPC contractor is carrying out the erection activities of a brownfield 660 MW thermal power project. A separate bid of an EPC contract for development of an FGD is expected soon.
8Project Event: RFQ for design, engineering, supply, installation, construction and commissioning of an FGD (flue gas desulphurization unit) is expected by the Q4 2018.
8Expenditure Approval: 2012
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: May/2013    
8Completion Date: Mar/2019
Click here for more information
8Project Name: Thermal Power Plant - O&M Contract
8Project Cost: 2.5 crores
8Project Description: Promoter is getting delayed in preparing the notice inviting tender document for an O&M contract for electrical equipment in the 3000 MW thermal power complex. Further bid is expected soon.
8Project Event: RFQ for O&M of electrical equipment is expected by September 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Sep/2018
8Release Date: Sep/2018
8Start Date: Q1:2019    
8Completion Date: Q1:2021