Software updates: Fertilizer projects
Aug 07: Ammonia-Urea & Captive Power Plant Greenfield Project 
 
8Cost - Rs 10741 Crore
 
8Project Event: The purchase work for other services is ongoing. RFQ for LSTK contractor was floated in May 2017 for Generating Ammonia Syn. Gas & Carbon Dioxide Gas, finalization is due in September 2018. The tender for the ammonia-urea plant is extended from 30 July to 13 August 2018.
Click here for more information
Ammonia-Urea Energy Saving Project     
8Cost - Rs 481 Crore
8Project Event: The basic engineering is ongoing, the purchase of a long lead item is under process. The project is waiting environmental clearance and it is likely to be elicited in January 2019.
Click here for more information
SSP-Sulphuric Acid & NPK Fertilizer Expansion Project   
8Cost - Rs 75 Crore
8Project Event: The company is likely to be release the tender for the EPC contractor after the environmental clearance which is likely to be elicited in September 2018. the environmental clearance has been delay due to evaluation & specification issues.
Click here for more information


**********************************