Midstream projects: Future RFQs
Aug 06: 8Project Name: Greenfield Gas Pipeline Project
8Project Cost: Rs 2500 crore
8Project Event: RFQ for the next 140 Km laying work is expected by October 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Oct/2018
8Release Date: Nov/2018
8Start Date: Q2:2017
8Completion Date: Q4:2020
Click here for more details for key contacts

8Project Name: Crude Oil Terminal Augmentation Project
8Project Cost: Rs 170 crore
8Project Event: RFQ for the PMC contractor is expected by October 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Oct/2018
8Release Date: Nov/2018
8Start Date: Q4:2018
8Completion Date: Q4:2020
Click here for more details for more information

8Business opportunity equipment suppliers: Get the key contact here
The owner is planning to float an RFQ for an electric motor driven CNG booster compressor for a City gas distribution project. An EPCM contractor is involved.

**********************************