Software Updates : Power Projects
Aug 03: Project Name: Thermal Power Station - Limestone Handling and Gypsum Storage Project
8Project Cost: 116 crores
8Project Description: Owner is planning to come out with a bid for limestone handling plant and gypsum handling plant related to the installation of an FGD system in a 3000 MW thermal power station. Further bids are expected soon.
8Project Event: RFQ for limestone handling, crushing and Gypsum Storage Package is expected by the mid-August 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 14/Aug/2018
8Release Date: 16/Aug/2018
8Start Date: Q4:2018
8Completion Date: Q1:2020
Click here for more information

8Project Name: Thermal Power Plant Maintenance Project 
8Project Cost: 5 crores
8Project Description: A subsidiary company has planned a 25-day scheduled annual overhaul in the 710 MW thermal power station. The specification of the work includes replacement of boiler pressure parts, replacement of basket in air preheater, repairing of economizer hoppers and seals. Further bids are expected soon.
8Project Event: RFQ for required overhaul is expected by the second week of August 2018.
8
Expenditure Approval: Q1:2018
8RFQ Date: 8/Aug/2018
8Release Date: 10/Aug/2018
8Start Date: 1/Sep/2018
8Completion Date: 15/Sep/2018
Click here for more information
8Project Name: Greenfield Thermal Power Project
8Project Cost: 7530 crores
8Project Description: A subsidiary company along with EPC contractor has completed the piling works for a 1600 MW greenfield super-critical thermal power project. Further bids are expected soon.
8Project Event: RFQ for fire protection system package and raw water system package is expected by the end of August 2018, instead of June.
8Expenditure Approval: Q4:2016
8RFQ Date: 28/Aug/2018
8Release Date: 31/Aug/2018
8Start Date: Q2:2017
8Completion Date: Q4:2021
Click here for more information

**********************************