Software Updates : Power Projects
Jul 30: 8Project Name: Greenfield Hydroelectric Power Station
8Project Cost: 538 crores
8Project Description: The owner has prepared an EIA report for the 45 MW greenfield hydro power project. Further bids are expected soon.
8Project Event : RFQ for EPC (turnkey) contractor is expected to be out in Q4 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Q4:2018
8Release Date: Q1:2019
8Start Date: Q2:2019
8Completion Date: Q4:2023
Click here for more information
8Project Name: Thermal Power Station - FGD Addition
8Project Cost: 420 crores
8Project Description: The owner is planning the installation of a Flue Gas Desulphurization (FGD) unit at its 890 MW thermal power station in order to comply with environmental norms and conditions. Further bids are expected soon.
8Project Event : RFQ for supply of FGD is expected to be out by September 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Sep/2018
8Release Date: Oct/2019
8Start Date: 2019
8Completion Date: 2021
Click here for more information

**********************************