Greenfield product pipeline: Equipment requirement coming up
Jul 27: 8Project Name: Greenfield Product Pipeline
8Project Cost: Rs 2500 crore
8Project Description: An EPC contractor has been hired 
8Major equipment requirement coming up are: Mainline pipes, Pumps, Generators, Compressors,  Isolation Valves (Manually, Remotely, Automatically Operated), Relief Valves (Thermal or other types), Pipe bridges or other supports, Control Systems, Leak Detection System, Pig launcher and receivers, Motors, Transformers,Control Valves, Filters.
8Expenditure Approval: Sep/2015
8RFQ Date: Oct/2018
8Release Date: Nov/2018
8Start Date: Q3:2017
8Completion Date: Q3:2020