Jul 26: 8Project Name: Thermal Power Station - FGD Addition 8Project Cost: 220 crores 8Project Description: The owner is planning to install FGD in 1436 MW thermal power station. Tenders for the same is expected soon. 8Project Event : RFQs for supply of an FGD is expected to be out by Q4 2018. 8Expenditure Approval: Q1:2017 8RFQ Date: Q4:2018 8Release Date:Q4:2018 8Start Date:Q1:2021 8Completion Date: Q3:2022 Click here for more information 8Project Name: Thermal Power Greenfield Project 8Project Cost: 16327 crores 8Project Description: A joint venture company is going on with piling, concreting and foundation activities for the 1200 MW super-critical thermal power station. Further bids are expected soon. 8Project Event : RFQs for office buildings and township package is expected by the end of August 2018 8Expenditure Approval: Q1:2016 8RFQ Date: Aug/2018 8Release Date:Sep/2018 8Start Date:Q4:2016 8Completion Date: Q3:2020 Click here for more information