Software Updates : Power Projects
Jul 26: 8Project Name: Thermal Power Station - FGD Addition
8Project Cost: 220 crores
8Project Description: The owner is planning to install FGD in 1436 MW thermal power station. Tenders for the same is expected soon.
8Project Event : RFQs for supply of an FGD is expected to be out by Q4 2018. 
8Expenditure Approval: Q1:2017
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: Q1:2021
8Completion Date: Q3:2022
Click here for more information
8Project Name: Thermal Power Greenfield Project
8Project Cost: 16327 crores
8Project Description: A joint venture company is going on with piling, concreting and foundation activities for the 1200 MW super-critical thermal power station. Further bids are expected soon.
8Project Event : RFQs for office buildings and township package is expected by the end of August 2018
8Expenditure Approval: Q1:2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2016
8Completion Date: Q3:2020