Jul 25: 8Project Name: Refinery Greenfield Natural Gas Pipeline Project 8Project Cost: Rs 350 crore 8Project Event: RFQ for the station work is expected by September 2018. RFQ for the mainline work is expected by November 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: Jan/2018 8Completion Date: Q4:2021 Click here for more details 8Project Name: Multi Product Terminal Expansion Project 8Project Cost: Rs 1000 crore 8Project Event: RFQ for the EPC contractor is expected by September instead of July 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: Q4:2018 8Completion Date: Q3:2021 Click here for more details for key contacts, and project parameters 8Business opportunity for contracting services: Find key contacts 8The owner is planning to float a bid for short term contract for vibration monitoring and analysis of rotary equipment in its petrochemical complex with a tenure of three years. Click on Details for more