Rs 100 crore EPS+Gas Pipeline: Subcontracts in September
Jul 24: 8Project Name: Oil Field Development 8Project Cost: Rs 100 crore 8Project Description: The owners EPS and gas transmission pipeline is under active bidding at present. Currently, the bid evaluation for the EPC package for the EPS and the mechanical works for the pipeline package part is under process. However the civil works tender is still open for bidding. 8Project Event: RFQs for hiring subcontractor from EPC contractor's end is expected by September 2018. 8Expenditure Approval: Q4/2017 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: Jun/2019 8Completion Date: Jun/2020 Click here for more details