Jul 24: 8Project Name: Greenfield Hydroelectric Power Station 8Project Cost: 625 crores 8Project Description: Owner's 60 MW greenfield hydroelectric power project is getting delayed due to lack of DPR approval from the State Government. Further package wise bids are expected soon. 8Project Event: RFQ for a civil and hydro-mechanical works package is expected by the Q4 2018, instead of Q2 2018. 8Expenditure Approval: Q1:2019 8RFQ Date: Q4:2018 8Release Date: Q4:2018 8Start Date: 2020 8Completion Date: 2024 Click here for more information 8Project Name: Thermal Power Plant - Annual Rate Contract 8Project Cost: 5 crores 8Project Description: Promoter's RFQ for O&M for a coal handling plant in a 600 MW thermal power plant has been delayed due to lack of approval from the project office. Moreover, the notice inviting documents have not been prepared. Further bids are expected soon. 8Project Event:RFQ for an annual contract for the O&M of the coal handling plant is expected by September 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Sep/2018 8Release Date:Sep/2018 8Start Date:Dec/2018 8Completion Date: Dec/2019 Click here for more information