Rs 600 crore oil field development: RFQs from October
Jul 23: 8Project Name: Oil Field Development
8Project Cost: Rs 600 crore
8Project Description: Owner's RFQs for the hiring of an EPC contractor for 24 well development drilling at onshore block  are expected soon. The TOR for the project has been granted recently. The owner however is yet to apply for wild life clearance.
8Project Event: RFQ for the hiring of EPC contractor for GGS construction and laying of pipelines are expected by October 2018.
 RFQ for the hiring of equipment and oilfield chemicals are expected by November 2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Oct/2018
8Release Date: Dec/2018
8Start Date: Feb/2020
8Completion Date: Dec/2022