Software updates: RFQs coming up in midstream and downstream projects
Jul 23: 8Project Name: Refinery BS-VI Upgradation Project
8Project Cost: Rs 500 crore
8Project Description:  RFQ for equipment for a new FCC gasoline desulphurization unit are currently on in the project. 
8Project Event: RFQ for the composite work in the sulphur recovery unit is expected by last week of July 2018.
RFQ for the CRWS Package is expected by September 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Q2:2017
8Completion Date: Jun/2019
Click here for more details for key contacts and other information

8Project Name: Pipeline Expansion Project
8Project Cost: Rs 250 crore
8Project Description: There is a slight delay has occurred in the selection of PMC contractor due to delay in environment clearance.
8Project Event: RFQ for PMC contractor is expected by September instead of July 2018.
8Expenditure Approval: Q3:2016
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Q1:2019
8Completion Date: Q3:2021
Click here for more details for key contacts and other information

8Project Name: Greenfield LPG Bottling plant
8Project Cost: Rs 150 crore
8Project Description:  RFQ for the equipment is already out.
8Project Event: RFQ for the civil work is expected by last September 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Q4:2018
8Completion Date: Q3:2020
Click here for more details for key contacts


**********************************