Oil field development: Operator on the lookout for a drilling and a workover rig
Jul 19: 8Project Name: Oil Field Development
8Project Description: The owner is expected to come out with RFQs for hiring a drilling rig and a workover rig for its field. An RFQ was floated earlier but has now been revised.  The project involves development drilling of 9 wells and laying of an infield pipeline to connect with the nearest production facility (GGS).
8Project Event: RFQs for hiring a drilling rig and a workover rig are expected by mid August 2018.
8Expenditure Approval: Q4/2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4/2018
8Completion Date: Q2/2020