Greenfield LPG pipeline project: RFQ for mainline pipes is expected by September 2018
Jul 17: 8Project Name: Greenfield LPG Pipeline Project (KSPPL) 8Project Cost: Rs 1200 crore 8Project Description: The owner has hired an EPCM contractor 8Project Event: RFQ for mainline pipes is expected by September 2018. 8Expenditure Approval: Q1:2016 8RFQ Date: Oct/2018 8Release Date: Nov/2018 8Start Date: Q4:2018 8Completion Date: Q3:2020 Click here for more details for key contacts and other project parameters