Jul 17: 8Project Name:BS VI Motor Spirit Block Upgradation 8Project Cost: Rs 3400 crore 8Project Description: The owner along with the EPCM contractor has already completed the ordering of long lead items. Offsites civil and structural works, building work as well as piling work are under progress. Deloitte has started carrying out data collection, analysis, schedule tracking and performance evaluation. 3D model review for the Reactor-Regenerator and heater package is 0% completed. 8Project Event: RFQ for the electrical and instrumentation work is expected by September 2018. 8Expenditure Approval: Q2:2016 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: Q4:2016 8Completion Date: Feb/2020 Click here for more details 8Project Name: Greenfield LPG Bottling Plant Project 8Project Cost: Rs 75 crore 8Project Description: The owner's plans to set up an LPG Bottling Plant with a capacity of 450 MTPA by installing 3 X 150 MT mounded storage vessels and a 30 TMTPA bottling capacity has been held up slightly because of environment clearance 8Project Event: RFQ for the PMC contractor is expected by September instead of July 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: Q4:2018 8Completion Date: Q3:2020 Click here for more details