Upstream projects: Software updates
Jul 16: 8Project Name: Desalination Unit
8Project Cost: Rs 400 crore.
8Project Description: Owner's RFQs for the hiring of an LSTK contractor for a Sea Water Reverse Osmosis Desalination Project are expected shortly. The capital approval for the project is however still pending.
8Project Event New: RFQs for hiring an LSTK contractor is expected by September 2018.
8Expenditure Approval: Q1/2016
8RFQ Date: Sep/2018.
8Release Date: Nov/2018.
8Date: Q2/2019
8Completion Date: Q1/2021
Click here for more details

8Project Name: Offshore Cluster Development
8Project Cost: Rs 1400 crore
8Project Description: Owner's RFQs for hiring of a drilling rig for 48 well exploratory drilling in 13 ML Blocks of Western Onshore Basin, Gujarat are already out. Currently the tendering for drilling fluid is also going on.
8Project Event: RFQs for the equipments and oilfield chemicals are expected by September 2018.
8Expenditure Approval: Q3/2016
8RFQ Date: Sep/2018
8Release Date: Nov/2018
8Start Date: Jun/2019
8Completion Date: Dec/2021
Click here for more details


**********************************