Jul 16: 8Project Name: Refinery Greenfield Gasoline Hydrotreating Unit (BPCL) 8Project Cost: Rs 600 crore 8Project Description: The ownwer along with the PMC contractor is carrying out engineering activities to install a new Gasoline Hydrotreating Unit (GTU).The dismantling of existing NSU and CRU units were completed in May 2018 to make way for new constructions. The 3D model review is almost 90% completed. Bulk material and all major equipment have already been ordered and heater package work has been awarded. Moreover civil & structural work, Out Side Battery Limit (OSBL) mechanical work, is in progress. 8Project Event: RFQ for the Inside Battery Limit (ISBL) mechanical work is expected by September 2018. 8Expenditure Approval: Q1:2017 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: Q1:2017 8Completion Date: Q1:2020 Click here for more details for key contacts 8Project Name: Gujarat Greenfield 2G Bio-Ethanol Refinery 8Project Cost: Rs 600 crore 8Project Description: The owner along with licensor Praj Industries Limited is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously 8Project Event: RFQ for EPC contractor is expected by September instead of July 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: 2019 8Completion Date: 2022 Click here for more details for project configurations and key contacts 8Project Name: Refinery Modernization Project (VRMP) 8Project Cost: Rs 21000 crore 8Project Description: The owner along with PMC contractor and licensor Honeywell UOP is carrying out engineering activities to expand the capacity Larsen & Toubro Limited is appointed as the EPCC contractor for the Crude Distillation and Vacuum Distillation Unit. RFQ for the LSTK contractor for VGO Unit and Hydrogen Unit is already out and tendering process is going on. 8Project Event: RFQ for the equipment for the VGO Unit and Hydrogen Unit is expected by September instead of July 2018. 8Expenditure Approval: Q4:2016 8RFQ Date: Sep/2018 8Release Date: Oct/2018 Start Date: Q2:2017 Completion Date: Q2:2020 Click here for more details for key contacts and other details