Downstream and midstream opportunities coming up-I: RFQs in September
Jul 13: 8Project Name: Greenfield POL Pipeline Project
8Project Cost: Rs 175 crore
8Project Description: The owner has hired an EPC contractor and mainline pipes for this project has already been procured and delivered on site. Awards have already been given out for the PLC-based control system and fire alarm detection system in April 2018.
8Project Event: RFQ for the welding and lowering work is expected by September 2018.
8Expenditure Approval: Q1:2016
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Q2:2017
8Completion Date: Q4:2019
Click here for more details

8Project Name: Refinery BS VI Greenfield Project
8Project Cost: Rs 3000 crore
8Project Description: The owner along with the EPCM contractor and licensor UOP/Axens is carrying out engineering activities to construct following new units: DHDT of 2200 KTPA, HGU of 44 KTPA, SRU of TPD, ARU of 189 TPH and SWS unit of 56.7 TPH along with the revamping of existing DHDS unit from 700 KTPA to 1000 KTPA for the proposed BS–VI Quality Up-gradation as well as the Capacity Expansion of the PX / PTA in the existing premises of its refinery. 
8Project Event: RFQ for the instrumentation erection work is expected by September 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Q2:2017
8Completion Date: Q1:2019
Click here for more details

8A New POL terminal Is coming Soon- Find Out The Owner:
8The owner is planning to install a grassroot POL terminal with a capacity of 80000 KL. The cost is estimated for this project is approx 470 Crores and completion will be by October 2020.