Jul 10: 8Project Name: Greenfield Pumped Storage Project
8Project Cost: 1500 crores
8Project Description: A JV company is continuing with S&I for a 300 MW pumped storage scheme. Further bids are expected soon.
8Project Event: RFQs for consultancy services for preparation of detailed project report are expected by September 2018.
8Expenditure Approval: Q1:2019
8RFQ Date: Sep/2018
8Release Date: Sep/2018
8Start Date: Q2:2021   
8Completion Date: Q4:2025
Click here for more information

8Project Name: Super Thermal Power Maintenance Project
8Project Cost: 10 crores
8Project Description: Owner has planned a 40-day capital overhaul in the 3000 MW thermal power plant. The job requirement includes air pre-heater guide bearing replacement, replacement of nozzles in pre-heater, supply of corroded water tubes, checking and cleaning of condensate pumps, among others.
8Project Event: RFQs for the required capital overhaul are expected by the August 2018.