Jul 09: 8Project:  Pipeline Expansion Project
8Project Cost: Rs 400 crore
8Project Description: The owner along with the EPCM contractor is expanding  the pipeline and constructing separate booster pumps for POL & LPG along with mainline pumps.
8Project Event: RFQ for the trenching and laying work is expected by August 2018.
RFQ for the composite Works (erection and installation) for integrated pumping station at Barwala is expected by October 2018.
RFQ for the composite work (erection and installation) for Ramanmandi pumping station is expected by November 2018.
8Expenditure Approval: Q2:2016
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q1:2017
8Completion Date: Apr/2019
Click here for more details
8Project Name: Greenfield LNG Terminal
8Project Cost: Rs 6000 crore
8Project Description: The owner is planning to install an LNG Floating Storage and Regasification Unit (FSRU) with a regasification capacity of 5 MMTPA. The company has selected the EPC contractor. The company has already finalized the FSRU design with a South Korean company and is expected to take delivery of the same by December 2018. RFQ for the long lead equipment is already out. Environment Clearance for this project has already been achieved in the last week of the June.
8Project Event: RFQ for dredging work is expected by October 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Oct/2018
8Release Date: Nov/2018
8Start Date: Q3:2018
8Completion Date: Q2:2020
Click here for more details

8GAIL plans to go renewable for its prospective project, licensor has been already finalized