Pipeline expansion project: Dispatch and receiving terminals and intermediate pigging station RFQs coming up
Jul 06: 8Project Name: Pipeline Expansion Project 8Project Cost: Rs 8086 crore 8Project Description: The owner along with EPMC contractor Engineers India Limited is carrying out construction activities for the expansion of the pipeline. A slight delay has occurred in the selection of a contractor for the dispatch and receiving terminals and intermediate pigging stations. 8Project Event: RFQ for a contractor for the dispatch and receiving terminals and intermediate pigging stations is to be expected in September instead of June 2018. 8Expenditure Approval: Q2:2015 8RFQ Date: Sep/2018 8Release Date: Oct/2018 8Start Date: Q2:2017 8Completion Date: Q2:2019 Click here for more details