Jul 05: NPK Fertilizer Greenfield Project 8Cost - Rs 1517 Crore 8Project Event: RFQ for EPC contractor was floated in February 2017 and price bid has been opened, Finalization is due in August 2018 only due to delay in the evaluation. The tender for equipments are likley to be released in September 2018. Click here for more information Ammonia-Urea Energy Saving Project 8Cost - Rs 347 Crore 8Project Event: EOI has already been released for an LSTK contractor in November 2017 and NIT has not been floated yet, and it is likely to be floated at the end of July 2018 due to delay in the specification and evaluation. Click here for more information Ammonia-Urea Annual Maintenance Project 8Cost - Rs 30 Crore 8Project Event: Tender for a registered maintenance contractor is likely to be released in September 2018. Click here for more information